Transmission Line TL Review - PowerPoint PPT Presentation

1 / 21
About This Presentation
Title:

Transmission Line TL Review

Description:

... nominal width is 12 inches, reduce to 8' from below clamp to horns. ... Clamp every ... the silver-plating off the TL 'fingers' when clamping/unclamping. ... – PowerPoint PPT presentation

Number of Views:62
Avg rating:3.0/5.0
Slides: 22
Provided by: BDMacOffi7
Category:

less

Transcript and Presenter's Notes

Title: Transmission Line TL Review


1
Transmission Line (TL) Review
  • WBS 1.1.3 Power Supply System
  • Transmission Line (TL) Review
  • Nancy Grossman
  • FNAL
  • April 23, 2003

2
Outline
  • Overview Specifications (N. Grossman, 10)
  • Scope of review
  • General Layout Overall Specifications
  • Schedule, Concerns
  • Response to Recommendations (2/26/02 review)
    (N. Grossman, 10)
  • Testing at MI8 (J. Hylen, 15)
  • Remote clamp joint testing so far
  • Future plans
  • Ionization Calculations (J. Hylen, 10)
  • Cooling Calculations (A. Stefanik, 10)
  • TL through Block Beyond Design/Status (B.
    Boettinger, 45)
  • Design (clamps, connection, supports)
  • Heating/cooling (expansion) Vibration Issues
  • Service Considerations

3
Scope and Conceptual LayoutTarget Hall
Transmission
  • Material Aluminum, Dimensions 12 inches wide
    by 3/8 inch thick
  • Width Stripline nominal width is 12 inches,
    reduce to 8 from below clamp to horns.
  • Gap Stripline nominal spacing between bars is
    3/8 inch, can increase in flex region.

REMOVABLE 28 SECTION
REMOVABLE Z-BAR
ROCK WALL BETWEEN PS ROOM AND TARGET HALL- 23
REMOTE CLAMP
HORN 1 JOINT
REMOVABLE Z-BAR
REMOTE CLAMP
HORN 2 JOINT
4
Scope and Conceptual LayoutTarget Hall
Transmission
5
Scope/Charge to Group
  • Scope Includes
  • Transmission Line design from joint/remote clamp
    to connection at capacitor bank
  • Electrical Isolation Considerations
  • Heating/cooling (thermal expansion)
  • Vibration
  • Stands support structures to hold transmission
    line in place
  • Wedge clamps in the transmission line block
  • Support stands in the target hall
  • Three point support structure in 24 round
    penetration from hall to PS room
  • Service Considerations
  • Removing the section through the wall
  • Horn replacement
  • Cover to protect transmission line to be
    designed, simple slanted sheet metal
  • Charge
  • Look at overall design.
  • Consider QA, longevity, ESH issues.
  • Comment back to grossman_at_fnal.gov within a week.

6
MI-8 Fingers, Remote Clamp
Remote clamp plugged in _at_ MI-8
Horn 1 joint/electrical plug _at_ MI-8
Routine pulsing of prototype horn 1, production
horn 1 joint, remote clamp underway 370,000
pulses to date. Goal is 1 million pulses, 1/2
offset/flexed
7
Joints and Remote Clamp
Horn 1 joint, remote clamp at MI-8
Horn 2 joint in machine shop (now done)
8
Overall Specifications/Concerns
  • 1. Lifetime
  • Part of stripline connected to horn will be
    replaced each time a horn is replaced, gt1 year.
  • Part of stripline within stripline block
    (includes clamp) does not have to be replaced
    every time a horn is replaced, but we will most
    likely have a spare just in case.
  • Lifetime of NuMI 10 years
  • 2. Radiation Environment such that ceramics must
    be used near the beam, but
  • not necessary above the module/T-blocks.
  • Ceramics spacers from horn to top of module/block
  • G-10 spacers used beyond that as insulators
  • 3. Vibration, keep to a minimum everywhere.
  • Biggest horn vibration is from stripline (MI8
    measurements)
  • Not near horn natural frequencies (200 Hz),
    damping times short wrt rep-rate
  • Clamp every 12 in target hall
  • Pulsed for about 9.5 millions pulses at MI-8
    (non-joint portion of transmission line) with no
    problems clamping every 12
  • More on recent vibration measurements from Jim.

9
Overall Specifications/Concerns
  • 4. Cooling
  • Target chase cooled by 24,000 cfm flowing in the
    beam direction in the horn region and back in the
    opposite direction between the top of the
    T-blocks and the concrete cap.
  • Beam heating 183 KW/m3 (transmission line near
    the beam)
  • TL Electrical heating 27 KW/m3 (flex joint
    number)
  • Assume air cooling from target chase is
    sufficient (A. Stefanik talk)
  • Want air flow through TL shield block from top of
    module to horn (this air flow cools stripline)
  • Air dam is needed at the H-block cover between
    the module and the stripline along the target
    hall wall (intended to contain air-borne
    radiation).
  • 5. Service Considerations
  • Must not block survey holes in T-blocks just off
    module ends, need direct vertical line of sight.
  • Two removable sections to allow removal of
    section through the wall (28).
  • Removable z-bars at top of module/block.
    Allows replacement of horns.

10
Transmission Line Through the Block
11
Transmission Line Through the Block
( figure slightly out of date )
12
Transmission Line Through the Block
13
Transmission Line Beyond the Shielding
14
Transmission Line Beyond the Shielding
15
Transmission Line Beyond the Shielding
16
Transmission Line Through the Rock Wall
17
Transmission Line Through the Rock Wall
18
Response to Recommendations Horn PS/TL Review
(August 2001)
  • Consider using a dynamic type fastener (e.g.,
    spiralock nut) in the clamp joints and stripline
    support brackets.
  • This is being done, except in the block region
    where it is tack-welded to the fasteners.
  • Consider measuring bolt preload in critical
    connections by measuring bolt stretch as opposed
    to bolt torque.
  • Not sure how to implement this ideas?
  • Consider longitudinal damping along the TL
    section along the Target Hall wall to damp out
    possible undamped vibrations from electrical
    pulsing.
  • Using polyeruthane isolators and swinging
    end-links (see Bills talk).
  • Worry about scratching the silver-plating off the
    TL fingers when clamping/unclamping.
  • Have seen no damage in the silver-plating on the
    TL fingers out at MI-8 and they have been
    connected and disconnected a few times. (more
    from Jim)

19
Response to RecommendationsTL, Remote Clamp, TL
Block Review (Feb. 2002)
  • Flex Joint Comments (joint with slits)
  • No longer using a joint with slits. ANSYS shows
    we can get sufficient flexibility with the
    non-slitted design. Single strip force tests
    agree with the ANSYS analysis. Testing at MI-8
    of the horn1 joint is going well. More from Jim
    not specifically part of this review.
  • Suggest quantitative measurements be made at MI-8
    (deflection at specific points, resonant
    frequencies, etc.) to compare to ANSYS
    calculations (and any other calculations) and
    thus support longevity estimates.
  • We are making some quantitative measurements at
    MI-8 and will compare measurements with
    predictions Jim will talk about this.
  • Concerns abut a tight testing schedule at MI-8
    which might be hard to meet if problems are
    encountered.
  • Agree. We have encountered problems, testing is
    tight, and we hope to make it (more from Jim).
    Can delay installation of horn PS continue
    testing longer.
  • Concerns with human resources lack of.
  • This is a constant battle we continue to fight.
  • Suggest pre-assemble entire setup (power supply
    to horns) at MI-8.
  • We will do this to the extent that we can.

20
Schedule Concerns
  • Schedule
  • MI-8 testing until Horn PS removed for
    installation.
  • Test pulsing of horn 1 and horn 2 on test stand.

21
Schedule Concerns
  • Specific Concerns
  • Making sure all bolts on the TL clamps are
    tighten (and remain tightened)
  • Checkout checklist item
  • Periodic checks in Target Hall?
  • QA that clamps are put together correctly
  • If doesnt look like it is going together well,
    stop and ask expert.
  • Alignment rods at removable sections
  • General Concerns
  • Resources (manpower)
  • Engineering/drafting to get the design done and
    parts ordered/made
  • Technicians to get it assembled and installed
  • Fitting it all in with the target hall shield
    block installation Module installation
  • Concerns about damaging the TL parts
  • Final connections of the TL to the horns/PS are
    near the critical path
  • The transmission line (and joint) have always
    been underestimated in their complexity (cost,
    time to make, problems encountered in
    installation/testing).
Write a Comment
User Comments (0)
About PowerShow.com