Title: Annual Reconciliation aka True Up


1
Annual Reconciliationaka True Up
  • June 10, 2004
  • Mary Shellabarger, EPA

2
NOx Allowance Tracking System(NATS)
  • Maintains information on
  • accounts
  • the issuance of all allowances
  • the holdings of allowances in accounts
  • the deduction of allowances for compliance
    purposes
  • the transfer of allowances between accounts

3
Compliance Accounts
  • Unit Accounts
  • established for each affected unit via Account
    Certificate of Representation
  • populated with initial allocation
  • Overdraft accounts
  • automatically established for each plant with two
    or more units

4
Compliance Accounts, cont.
  • Account Numbers
  • 12 digits (but leading zeroes may be dropped)
  • first six digits are ORIS/facility code
  • second six digits are unit ID or OVERDF
  • example 004567000CT1 004567000CT2 004567O
    VERDF

5
General Accounts
  • Available for any individual or organization
  • Established by submitting form
  • name and contact information for AAR
  • signature
  • list of all persons with ownership interest in
    the allowances held in the account
  • Account number always starts 9999

6
Allowances
  • Identified by 12 digit serial number
  • first four digits are the compliance use date
    (aka vintage)
  • cannot use an allowance for compliance prior to
    its vintage year
  • Reported in blocks
  • example 200300123400 - 200300123499
  • represents block of 100 allowances

7
Compliance 2004
  • Ozone season ends Sept. 30
  • EDRs due Oct. 30
  • Allowance transfer deadline Nov. 30
  • eligible allowances 2003, 2004
  • no flow control
  • Compliance certification due Nov. 30

8
Eligible Allowances
  • Allowances used for compliance
  • only allowances of a vintage for the current year
    or an earlier year may be used
  • Allowance transfer freeze
  • the date after which allowances that may be used
    for compliance cannot be transferred into or out
    of a unit or overdraft account

9
Compliance Certification
  • One form (may be submitted electronically) for
    each AAR to EPA
  • ID for each affected unit
  • common-stack apportionment
  • compliance certification statement
  • signature of AAR
  • Option to identify serial numbers of allowances
    to be deducted

10
Process at EPA
  • Final allowance transfers received from sources
    and processed
  • Emissions data received from sources and
    quality-assured
  • Compliance certification information processed
  • assure complete reports received from all sources

11
Process, cont.
  • serial number specification recorded
  • common-stack apportionment recorded
  • Emissions and allowances compared by NATS
  • Deductions processed
  • Flow control calculated

12
New Unit Procedures
  • Reminder for new units that receive an allocation
    from a new unit set-aside
  • Check your states allocation rule for the
    end-of-ozone season take-back procedure
  • Make sure that its understood by allowance
    managers before allowance transfer deadline

13
New Units, cont.
  • Allocation adjusted to account for actual
    utiltization
  • allocation based on lowest permitted emissions
    rate times maximum design heat input
  • units only allowed to keep allowances equivalent
    to lowest permitted emissions rate times actual
    utilization
  • excess allowances deducted as part of compliance

14
Deduction Process
  • One unit at a time, in numerical order
  • Fulfill obligations of first unit before moving
    on to next unit
  • AAR-specified allowances first
  • flow control, if applicable, is used if AAR
    specifies banked allowances
  • other allowances second
  • current year allowances, then banked
  • flow control, if applicable, is used

15
Deduction Process, cont.
  • If a unit doesnt have enough allowances, go to
    overdraft account
  • no serial number specification
  • current year allowances first
  • no specification of serial numbers
  • banked allowances second
  • no specification of serial numbers
  • flow control, if applicable, is used

16
Deduction Process, cont.
  • If there still arent enough allowances, excess
    emission penalty deduction
  • dont make us go there!
  • Move on to next unit at the plant
  • Same steps, as necessary

17
Excess Emissions
  • When there are not enough allowances to cover
    emissions in the unit account or overdraft
    account
  • Allowances are deducted from following years
    allocation at 31 rate
  • 3 allowances for each ton of excess
  • Other enforcement action possible

18
Future Reference Flow Control
  • No flow control for 2004 compliance, possible for
    2005 compliance
  • Compare number of banked allowances to regional
    budget
  • If total number of banked allowances exceeds 10
    of regional budget, PFC is calculated for
    following year

19
Remember in 2004
  • When does your compliance season start?
  • May 1 or May 31
  • Will you have a new unit take back?
  • Allowance transfer deadline Nov. 30
  • Create a buffer!
  • Flexibility of overdraft accounts
  • Use the CAMD Business System!