Capital City Airport Master Plan
2
Capital City Airport
3
Airport Funding Sources
  • 95 Federal Aviation Administration (FAA)
  • 5 State Funds as follows
  • 2.5 Transportation Cabinet, Dept. of
    Aviation
  • 2.5 Department Military Affairs, Div. of
    Air Transport

4
Airport Reference Code (ARC)
  • (ARC) for the Capital City Airport is established
    as C-II
  • Aircraft with approach speeds between 121 and
    141 knots, and
  • Wingspans ranging from 49 to 78 feet

Hawker 800
Gulfstream III
Citation 500
5
Capital City Airport
6
Runway Extension (Construction should be
complete by fall 2006)
RUNWAY/TAXIWAY EXTENSION
FAA 3,900,000 - 95
STATE 205,000 - 5
7
Perimeter Security Fencing (Installation should
be complete by fall 2006)

FAA 424,650 - 95
STATE 22,350 - 5
8
Proposed Construction
RUNWAY
RUNWAY
RESURFACING (Completed 2005)
EXTENSION 900 (FY 06 07)
AIRCRAFT PARKING EXPANSION (FY 08 10)
5 HANGARS (FY 06
10)
TERMINAL BLDG.
MANUFACTURING PLANT (TBD)
NEW AIRPORT TERMINAL BUILDING (FY 08 10)
39 T-HANGARS ( 20 for FY 06)
9
Proposed Army Aviation Support Facility
PROPOSED AASF
RUNWAY EXTENSION
Estimated 31,000,000 Federal Funds
10