Title: Astronomy and Astrophysics Advisory Committee
 1Astronomy and Astrophysics Advisory Committee
- Astrophysics Division and Update 
 - May 11, 2006 
 - Rick Howard 
 - Astrophysics Division Director (Acting) 
 
  2 Astrophysics Division Operating Missions Status 
 3 Astrophysics Division Developmental Missions 
Status 
 4Astrophysics DivisionBudget Problems and Issues
- Budget problems and issues that must be dealt 
with during this summers budget formulation  -  Additional funding in slip of HST SM4 launch 
date beyond 12/07  -  Level of near term contingency for JWST 
 -  Funds required for SOFIA to support final 
decision on path forward  -  Additional funds to cover expected GLAST replan 
 -  Potential cost growth in Kepler 
 -  Decision on future of WISE 
 -  Restoration (full or partial) of funds to RA 
program  -  Adjustments to mix within Navigator program (TPF 
issue)  -  Direction within Balloon Program on future plan 
for ULDBs  
  5Astrophysics DivisionBudget Principles, 
Priorities  Constraints (1)
- General Principles 
 -  Follow priorities set by NRC surveys and reports 
 -  Support Administration goals and direction 
 - In Practice 
 -  Incremental budget solutions can lead to wrong 
global solution  -  Best approach is to solve all problems at one 
time each year (POP)  -  Slipping current missions not always the right 
answer  -  Only solves short term budget problems 
 -  Creates bow wave of funding requirements 
downstream  -  Increases total mission cost far more than 
inflation (marching army)  -  Cancellation may be more sensible option 
 -  Applying a tax across the board not a good 
approach  -  Spread the pain but weakens all programs 
 -  Once or twice may have minor impact eventually 
has significant impact on all projects  -  Reserve this approach for directed reductions 
(rescissions, hurricane tax, etc.)  
  6Astrophysics DivisionBudget Principles, 
Priorities  Constraints (2)
- Priorities 
 -  Continue healthy operating missions 
 -  Complete and launch missions in development 
 -  Provide for the future ( RA, technology, 
balloons, concept studies)  - Constraints 
 -  Congressional direction/mandates 
 -  Solution must balance each of the 5 years in the 
budget horizon  -  Currently working on FY08-12 budget 
 -  Only guaranteed budget is the single year 
approved by Congress in the Operating Plan  - Considerations 
 -  Mission size/launch frequency 
 -  Wavelength 
 -  Mission Phase 
 -  Long term strategy
 
  7Wavelength Mix 
 8Science Theme Mix 
 9Mission Size Mix 
 10The Astrophysics Content of FY07 Budget
 Future Explorer Budget is in Heliophysics 
Division budget 
 11Astrophysics DivisionBudget Example
- Hypothetical Issue Restore15 RA funding 
reduction  - Solution 1 Reduce Beyond Einstein Program 
funding  -  Hold budget to the FY06 level for FY07-08 ( 
14M per year)  -  Restores 10 (7M) in FY07 and FY08 
 -  Restores full 15 starting in FY09 (11M per 
year)  -  Slips first Beyond Einstein mission 
 - Solution 2 Apply an across the board tax 
 -  Approximate 1 reduction to all programs 
 -  Some programs may be protected (e.g. HST SM4) 
 - Solution 3 Restore as part of overall 
Astrophysics budget solution during FY08-12 POP  -  Allows more flexible solution space 
 -  Solution is part of Divisions overall strategy