Linac Coherent Light Source LCLS - PowerPoint PPT Presentation

1 / 23
About This Presentation
Title:

Linac Coherent Light Source LCLS

Description:

The PMCS group is composed of 5 Project Controls/Scheduling analysts ... Additional marching army costs. Impacted milestones. Inflation/escalation ... – PowerPoint PPT presentation

Number of Views:65
Avg rating:3.0/5.0
Slides: 24
Provided by: hel85
Category:

less

Transcript and Presenter's Notes

Title: Linac Coherent Light Source LCLS


1
Linac Coherent Light Source (LCLS)
  • Earned Value Management System
  • Trish Mast
  • September 18, 2007

2
  • Project Controls Team
  • The Plan for the Plan
  • Critical Path

3
PMCS Team
  • The PMCS group is composed of 5 Project
    Controls/Scheduling analysts
  • The entire PMCS group is contract labor through
    Deltek, Inc.
  • The PMCS team supports the Project Office and
    CAMs
  • Trish Mast Project Office, Undulator,
    Commissioning
  • Jeff Chan Installation
  • Manny Abela Injector, Linac, and E-Beam Systems
    Controls
  • Jay Doubrava Photon Systems and Photon Systems
    Controls
  • Anita Malahowski Conventional Facilities

4
The Plan for the Plan (or How We Spent our Summer
Vacation)
  • Initially developed offline database that
    represented the 2007 CR Effects which was
    presented at the July Lehman Review
  • Database was called CRFN
  • Used Actuals thru April 2007
  • 2007 CR effects were calculated for Oct 06-
    April 07
  • Estimate to Complete reflected CR effects on
    future work

5
The Plan for the Plan
  • July Lehman Review requested CR effects
    modifications plus full Estimate to Complete
  • Database to contain complete rebaseline of ETC
  • Rebaseline to be completed by end of August
  • CR Effects to be isolated
  • Lehman Review recommendations to be implemented
  • Results to be presented at September 18th Mini
    Lehman Review

6
The Plan for the Plan
  • August Rebaseline effort broken into 3 Steps
  • Step 1 Update database to include actuals thru
    June 2007 (CRR1)
  • Step 2 Update the Database with the Lehman CR
    related recommendations to produce a final CR
    Effects total (CRR2)
  • Step 3 Implement all pending BCRs, rate updates,
    and baseline corrections for a comprehensive
    Estimate to Complete (CRR3)

7
Step 1
  • Data at last Lehman Review was presented with
    April Actuals
  • For this review we have updated the data with
    June Actuals

8
Step 2
  • Only CR Effects will be reviewed
  • CR Cost Impacts to 1st two quarters of FY07
  • CR Cost and Schedule impacts to ETC
  • CR Effects that were realized are
  • Schedule delays
  • Additional marching army costs
  • Impacted milestones
  • Inflation/escalation
  • Redistribution of costs from OPC to TEC
  • Recalculation of contingency and management
    reserve

9
Step 3
  • Add in all pending BCRs
  • Refine, correct and validate the ETC to fit
    within the allocated funding profile
  • Finalize the plan for the transition to
    operations
  • Update the overhead and escalation rates Changes
  • OH OPC Labor _at_ 40
  • OH TEC Non-Labor _at_ 4.32, OPC Non-Labor _at_ 5.04
  • SLAC/LLNL Escalation rates _at_ 4.0/Year
  • ANL Escalation rates _at_ 4.5/Year
  • Validate the database and start the BOE
    documentation in preparation for the EIR in
    October
  • Bottoms up contingency analysis and Monte Carlo
    Analysis was performed

10
Critical Path Analysis
  • Top three critical paths were run and analyzed
  • All constraints removed from database except
  • Funding constraints
  • Shutdown constraints
  • Top three paths to CD4 were calculated
  • Critical path to Initiate Early Experimental
    Operations calculated

11
Backup Slides
12
(No Transcript)
13
Detailed Cost Estimate Report (DCE)
14
Budget and Funding Analysis
15
Milestone Hierarchy
  • Defined Level 1, 2, 3 and 4 Milestones
  • Level 1 controlled by DOE HQ
  • Level 2 controlled by DOE Stanford Site Office
  • Level 3 controlled by LCLS Project
    Director/Deputy Project Director
  • Level 4 controlled by System Manager
  • Level 1-3 Milestones are under formal
    configuration control.

16
Resource Loaded Schedules
17
Integrated Schedules
18
CPR Drilldown (Level 2)
19
BCWS, BCWP,ACWP Report (SPA)
20
Obligation Report (OSCUM)
21
Milestone Dictionary
22
WBS Dictionary
23
Responsibility Assignment Matrix (RAM)
Write a Comment
User Comments (0)
About PowerShow.com