Single Inclusive Jet Cross Sections at D0 - PowerPoint PPT Presentation

1 / 9
About This Presentation
Title:

Single Inclusive Jet Cross Sections at D0

Description:

Have 5 fully tested DFEA MBs (for mid-April) ... TTs implemented, what we needed by mid-April, and should last us long given schedule for AFEs ... – PowerPoint PPT presentation

Number of Views:40
Avg rating:3.0/5.0
Slides: 10
Provided by: levanbab
Category:

less

Transcript and Presenter's Notes

Title: Single Inclusive Jet Cross Sections at D0


1
D? Trigger Meeting, March 15, 2001, Fermilab
L1 Tracking Digital Firmware Installation
Levan Babukhadia
SUNY at Stony Brook
http//www-d0.fnal.gov/blevan/upgrade.html
2
for the CTPT DFE firmware group
  • Levan Babukhadia
  • Mrinmoy Bhattacharjee
  • Jerry Blazey
  • Brian Connolly
  • Satish Dasei
  • Paul Grannis
  • Steve Lynn
  • Manuel Martin
  • Jamieson Olsen
  • Ricardo Rodrigez
  • Qichun Xu

3
DFE Hardware
  • Platform cables in place, PS need more work, ORC
    issues, 1553/DFEC, 1month
  • All DFE motherboards here and tested
  • All DFEA SWDBs (808) here, testing in
    progress at PREP
  • Have 5 fully tested DFEA MBs (for mid-April)
  • Fully stuffed 3 CTOC and 4 CTQD DWDBs here,
    testing in progress
  • Have 2 fully tested DWDBs
  • 5 with problems, placement (BEST), vias, ?
  • 1 CTOC and 1 CTQD DWDBs any time from BEST, fully
    stuffed in 1 week thereafter
  • 1 DFEF DWDB with XCV1000E FPGAs
  • Failed JTAG chain, back at BEST to reflow
  • 36 XCV600 FPGAs for the remaining of CTOC, and
    CTTT, FPSS, FPTT DWDBs on order with AVNET, here
    by the end of March, fully stuffed and tested end
    of April
  • 34 XCV1000E FPGAs for DFEF PO in the system, at
    AVNET by early next week, 3-4 weeks lead time,
    fully stuffed tested by end of May

4
DFE Firmware General
  • Data skewed across LVDSs (out of AFEs) worse than
    expected
  • ?8ns across 4(5) LVDSs out of AFE8(12), degrading
    by about ?1ns through each tier of DFE boards
    (Expected was lt ?1/4 RF cycle)
  • As a result, can not remove skew across different
    DFE boards. This means that we need to
    re-synchronize in every DFE board!
  • Had to significantly modify existing deskewing
    algorithm from synchronizing clocks (?1/4 RF
    cycle) to synchronizing records (?1 RF cycle)
  • Synchronization of records is different for L1
    and L2. Therefore two flavors of the algorithm
    might be needed
  • The L1 flavor now works in functional as well as
    in timing simulations for N links (worst case N
    10) using Virtex RAMs
  • Realization that the same RAMs could be used for
    de-skew and L1 pipeline was crucial
  • L3 Sender is also now implemented along with
    de-skew in L1FE (L1 Front End) module
  • L1FE implemented and being tested in CTTT

5
DFE Firmware L1 FPS
  • Important milestone was reached on Feb 2 the
    entire L1 FPS chain, DFEF?FPSS?FPTT successful in
    SoftBench. Next, do the same in TestStand,
    awaiting working DFEF DWDB.
  • DFEF (32) Levan
  • L1 done (passed TestStand)
  • L2 simplified algorithm in place, need some time
    to go back and implement with proper functional
    model of Xilinx RAMs and test
  • As needed, develop L2 priority reporting to
    better handle truncation, any biases
  • FPSS (4) Mrinmoy
  • L1 done (passed TestStand)
  • Develop and implement L2 algorithm
  • FPTT (1) Satish
  • L1 done (passed TestStand)
  • L1 ? L3 Sender nearly completed, imple-mented in
    L1FE, and L1FE in CTTT
  • Need to complete L3 Record header generation,
    expect by the end of this week

FPS
6
DFE Firmware L1 CFT/CPSax
  • DFEA (80) Jamieson
  • Track firmware done (4 FPGAs)
  • Occupancy calculation nearly done
  • Modifications to follow updated protocols
  • Develop SoftBench (a la FPS ? Levan)
  • Backend (5-th) FPGA, CPS cluster finding and
    track matching, needs more work
  • CTOC (8) Brian/Ricardo
  • Both L1/L2 firmware completed and tested in
    TestStand for 8 links
  • Modification in Occupancy Level calculation and
    transfer protocols implemented (Brian)
  • Need more extensive tests, good SoftBench
  • CTTT (1) Levan/Manuel
  • News now have TMO, THT1, and THT2 TTs
    implemented, what we needed by mid-April, and
    should last us long given schedule for AFEs
  • Uses L1FE module, that will become front end
    firmware module in basically all DFE boards
  • Expect track (TTK, TTA, TEL, TPQ, TNQ) TTs in few
    weeks
  • No implementation difficulties foreseen

7
DFE Firmware L2 CTQD CPSst
  • CTQD (4) Steve (new)
  • Work in progress on L2CFT functionality, started
    to use RAMs instead of flip-flops, issues with
    synthesis/implementation
  • Work on L2CPS has not started yet, slightly more
    complex than L2CFT
  • Can not expect this sooner than a couple of
    months
  • DFES (10) Qichun
  • Cluster finder VHDL written and tested with-out
    4-bit cluster merging implemented yet
  • Need implementation with realistic constraints,
    expect in about couple of weeks
  • Develop handful of TestVectors and robust
    SoftBench, then TestStand expect in 1-2 months
  • CPSS (4) Qichun
  • Not started yet

8
http//www-d0.fnal.gov/blevan/upgrade.html
9
Outlook
  • Hardware lagging firmware
  • Because of AFE8s, ORC issues, download to DWDBs
    (DFEC), access, , can only have hit trigger in
    L1 CFT/CPSax by mid-April
  • Have all digital boards for partial installation
    (5 DFEAs, 1 CTOC, 1 CTTT)
  • Have L1 CTOC and now CTTT firmware, but need more
    extensive tests
  • Need DFEA completion, partial, i.e. with
    occupancy count and proper protocols
  • Chain SoftBench and TestStand
  • Assemble chain in DAB3 and exercise firmware and
    remote operations (1553) there for the next month
    or so
  • Next, need to implement full DFEA, CTOC, and CTTT
    firmware for L1 (and then for L2)
  • As soon as we have working DFEF DWDB, L1 FPS
    chain TestStand (have all FPS TTs)
  • Complete pieces of firmware for L2 CPSst and
    CFT/CPSax (CTQD) in a couple of months
Write a Comment
User Comments (0)
About PowerShow.com