Title: e-Manifest Tracking System Project
1e-Manifest Tracking System Project
2Overview
- 1. Introduction Problem Statement
- 2. Project Overview
- 3. Project Challenges
- 4. Project Team
- 5. Project Tasks and Schedule
- 6. Project Controls
- 7. Current Status
3Introduction Problem Statement
- Problem Example Michigan receives 40,000 paper
manifests/mo - 2,800/day - Each manifest reviewed by State to verify
- the waste shipment amounts, and
- that shipments have been delivered to treatment,
storage, and disposal (TSD) facilities in a
timely manner - Once paper manifests are received, some states
transfer them to electronic formats - scanning,
microfilm, and/or manual data entry - Manual validation processing requires full-time
resources - leads to data quality problems, and
- timing issues related to regulatory response time
4Michigan DEQ Hazardous Waste Manifest Processing
UnitApril, 2007
52. Project Overview
- Goals
- Pilot an electronic manifest process using the
Exchange Network as the enabler - Eliminate current paper based processing burden,
including manual validation by state regulators - Drastically improve intra-state and inter-state
cradle to grave tracking of hazardous waste by
providing rapid access to data consumers
62. Project Overview (contd)
73. Project Challenges
- Challenges/Risks
- Private industry interest and acceptance
- Compatibility with National electronic
manifesting initiative - Adoption by EPA Office of Solid Waste
84. Project Team
- Roles
- Team Members EPA, Massachusetts, New Jersey,
Minnesota and Michigan, Windsor Solutions - Project Management
- Michael Beaulac, MDEQ
- Mark Breithart, MDIT
- Jason Bunker, Windsor Solutions
- Steering Committee
- Subject Matter Experts (SMEs)
- Project Support
- Contractor
94. Project Team (contd)
- Project Manager Responsibilities
- Chair project team
- Resource coordination
- Facilitate issue resolution
- Monitor project status
- Ensure project objectives requirements are met
- Deliverable acceptance and sign-off
104. Project Team (contd)
- Steering Committee Responsibilities
- Main agency project representative
- Approve project schedule
- Commit agency resources
- Authorize scope, resource and budget
modifications - Ensure senior management project commitment
114. Project Team (contd)
- SME Responsibilities
- Provide vision for business and application
designs - Participate in requirements gathering and design
sessions - Review and comment on delivered documentation
- Participate in testing phases of prototype
solution - Subject matter experts identified
125. Project Tasks and Schedule
- Major Phases
- Phase 1 Project Initiation, Business Process
Analysis, Technology Research, Infrastructure
Preparation - Phase 2 Design and Development of a Central
e-Manifest Tracking System - Phase 3 State e-Manifest Data Flow Design and
Development - Phase 4 State e-Manifest Data Flow Installation
- Phase 5 Post Implementation/Lessons Learned
135. Project Tasks and Schedule (contd)
- Phase 1 Tasks
- Initiation and Project Management
- Business Process Analysis and Technology Research
- State Readiness Assessment
- Infrastructure Preparation to Support e-Manifest
Data Flow
145. Project Tasks and Schedule (contd)
- Phase 2 Tasks
- Development of a Central e-Manifest Schema for
Data Exchange - Central Manifest Tracking System Design and
Development - Agreement for, and Acquisition of Mobile Devices
155. Project Tasks and Schedule (contd)
- Phase 3 Tasks
- State-Specific Data Flow System Design Documents
- State-Specific Data Flow Development
- Phase 4 Tasks
- Configure test and production environments
- Migration and Data Flow Installation
- Conduct e-Manifest Tracking System User
Training - Phase 5 Tasks
- Post Production Support
165. Project Tasks and Schedule (contd)
Task Start Date End Date
e-Manifest Tracking System Project Plan 1/24/2007 11/5/2008
Phase 1. Project Initiation, Business Process Analysis, Technology Research, Infrastructure Preparation 1/24/2007 4/16/2007
Project Initiation and Project Management 1/24/2007 3/9/2007
Business Process Analysis and Technology Research 2/13/2007 4/16/2007
State Readiness Assessment 3/12/2007 4/11/2007
Infrastructure Preparation to support e-Manifest data flow 3/12/2007 4/13/2007
Phase 2. Design and Development of a Central e-Manifest Tracking System 4/17/2007 11/8/2007
Develop Central e-Manifest Schema 4/17/2007 10/16/2007
Design and Develop CMTS 4/17/2007 11/8/2007
Develop Mobile CMTS 6/22/2007 11/6/2007
Phase 3. State e-Manifest Data Flow Design and Development 11/9/2007 3/24/2008
Design State Specific e-Manifest Data Flows 11/9/2007 3/24/2008
Develop State Specific e-Manifest Data Flows 12/20/2007 3/4/2008
Phase 4. State e-Manifest Data Flow Installation 3/25/2008 7/28/2008
Configure Test and Production Environments 3/25/2008 6/5/2008
Migration and Data Flow Installation / Implementation 6/6/2008 7/14/2008
Conduct e-Manifest Tracking System User Training 6/6/2008 7/21/2008
Produce System Documentation 7/15/2008 7/28/2008
Phase 5. Post Implementation / Lessons Learned 7/29/2008 11/5/2008
Post Production Support 7/29/2008 10/29/2008
175. Project Tasks and Schedule (contd)
186. Project Controls
- Communication
- Project Web site
- Status reporting
- Meeting minutes
- Deliverables and documentation
- Acceptance Criteria
- Issue Management
- Risk Management
197. Current Status
- To Date
- Developed detailed Project Plan
- Project Web Site
- http//www.windsorsolutions.biz/emanifest
- http//emanifest.windsorsolutions.biz
- Implemented project management protocols
207. Current Status
- To Date
- Business Process Analysis Technology Research
- Coordinated and scheduled initial state
requirements gathering workshops - Worked with industry lobby (Environmental
Technology Council) and EPA to acquire industry
representatives
21Contact
- Michael Beaulac
- State Assistant Administrator
- Executive Division
- 517-241-7808
- beaulacm_at_michigan.gov