Title: Bonneville Power Administration RTO Update


1
Bonneville Power AdministrationRTO Update
Washington State Governors Staff February 21,
2002
2
RTO West, Filing Utilities
  • RTO West formed
  • NW utilities began working together in Fall 1999
  • Created consensus principles to guide development
    of proposal
  • Hired independent consultants and launched
    extensive public process to foster regional
    participation
  • Krogh Leonard, RTO West Coordinating Team
  • www.rtowest.org
  • RTO Filing Utilities
  • One federal Power Marketing Agency (BPA), one
    Canadian Power Authority, and eight
    Investor-Owned Utilities
  • Avista Corp. ? Bonneville Power
  • British Columbia Hydro Auth. ? Idaho Power
    Company
  • Montana Power ? PacifiCorp
  • Portland General Electric ? Puget Sound Energy
  • Nevada Power, Sierra Pacific Resources

3
Why RTOs? FERCs View
  • Access to competitive power resources
  • Non-discriminatory access to all transmission
    grids by all market participants
  • Increased reliability
  • Improved regional planning and expansion
  • Increased efficiencies from existing systems
  • Reduce Tx rate pancaking

4
BPAs Participation in RTO
  • Began with
  • DOE General Counsel opinion that BPA could join
    with standards, monitoring, and a right to
    withdraw
  • NW Delegation letter to BPA encouraging its
    participation
  • DOE Memo to PMAs (Power Marketing Administrations
    ? federal power agencies) ordering their
    participation

5
BPAs Participation in RTO
  • Today is
  • To bring public purpose to RTO development
  • The transmission tie that binds the region ?
    without BPA other filing utilities are more
    segregated and lack RTO efficiencies
  • To ensure benefits. BPA wants an RTO to maintain
    and enhance a secure and reliable transmission
    system
  • To remain in drivers seat with regional
    stakeholders. Rather than have FERC dictate.

6
BPA Principles
  • BPA developed principles to address
  • NATIONAL OBJECTIVES
  • Transmission Reliability
  • Open Wholesale Markets
  • Improve Efficiency
  • Public Equity
  • FERC Characteristics and Functions
  • NORTHWEST ISSUES
  • Transitions to an RTO
  • Financial Impacts
  • Sustainable Financial Structure
  • Preserve US Obligations
  • Remote Utilities
  • Address Fish Issues
  • Environmental Ethic
  • Public Involvement
  • Non-Discriminatory Treatment
  • Governance fair to stakeholders

7
Milestones to Date
  • Stage I filings
  • Oct. 16 23, 2000
  • December 1, 2000
  • FERC issued RTO West/TransConnect Order April 26,
    2001
  • Approved proposed Governance, Scope and Geography
  • Requested follow up by Dec. 1, 2001 on Seams
  • Disapproved Liability (Now open for new review as
    part of complete proposal after request for
    rehearing)
  • Preliminary approval of TransConnect, request
    more detail on planning and expansion roles
  • Dec. 1, 2001 Status Report to FERC
  • Interregional Coordination

8
Stage II Activities
  • Preparation of March Filing
  • RTO West Benefits-Cost Analysis
  • Supplemental Activities by Bonneville
  • Public Outreach
  • Stakeholders
  • State PUCs
  • FERC
  • NW Delegation, etc.

9
The Proposal
  • Transmission Operating Agreement
  • Bylaws
  • Pricing
  • Congestion Mgmt.
  • Ancillary Svcs
  • Liability Agreement

10
The Proposal (cont.)
  • Planning and Expansion
  • Facilities Listing
  • Marketing Monitoring
  • Paying Agent Agreement
  • Scheduling Coordinator Agreement
  • Liability Agreement

11
Stage II Activities
  • Preparation of March Filing
  • RTO West Benefits-Cost Analysis
  • Supplemental Activities by Bonneville
  • Public Outreach
  • Stakeholders
  • State PUCs
  • FERC
  • NW Delegation, etc.

12
Benefit Cost Analysis
  • Filing Utilities hired independent consultant
  • Tabors Caramanis Associates (TCA).
  • To provide information that
  • Is responsive to stakeholder, NW Delegation
    requests
  • Provides unbiased assessment of potential
    benefits and costs of RTO West
  • Describes potential impacts to the region
  • Scope of Current Analysis
  • Comparison of alternate futures, with and without
    RTO West.
  • Assess potential benefits and costs using a
    base-case, then adjust for various sensitivities
    (e.g. water levels, gas prices)

13
Benefit Cost Analysis
  • Key Milestones
  • Consultant presented preliminary report (base
    case)
  • Currently performing requested sensitivity
    analyses, other market power elements of study
  • Feb. 28 Final Report
  • Supplemental Activities by Bonneville
  • Bonneville will perform additional analysis in
    response to public customer representatives
    requests
  • Additional sensitivities with TCA -- RTO West
    with or without Bonneville
  • Additional Reliability benefits analysis
  • Reports Expected Feb. 22/28

14
Benefits Preliminary Results
  • Increased Economic Efficiency from Eliminating
    Pancaked Transmission Rates and Loss Charges
  • 350M in RTO West Benefits
  • Fuel Reduction (More Efficient Generators Run)
  • Operating Reserves Savings
  • Lower Transmission Congestion Costs
  • Increased Transmission Capacity Available Over
    Major Transmission Paths
  • Limited Only By True Physical Constraints
  • Results Reduction of Wholesale Power Prices in
    RTO West
  • Distribution of These Benefits is Allocated
    Through Rate Setting Processes

15
Benefits Preliminary Results
  • Reduction in Regulating Reserve Costs from
    Consolidation of Control Areas (10/2000 Study)
  • 364MW valued at 28M
  • Increased Reliability from Coordinated System
    Expansion and Planning, and Consolidated
    Operation
  • Results expected in Mid-February
  • Qualitative Benefits
  • Coordination of Tx. Maintenance and Construction
    Outages
  • Lower Transaction Cost (One-Stop Shopping for Tx.
    Services)
  • Greater Price and Cost Transparency
  • Market Monitoring and Oversight

16
Costs Preliminary Results
  • Benchmarked Annual Costs of Operating RTOs in US
  • 125M - 145M
  • Estimated Annual Cost of RTO West in 10/2000
    Study Consistent with Benchmarking -- Slightly
    Less
  • Annual Costs Include Operating Costs and
    Amortization of Capital Start-up Costs

17
Stage II Activities
  • Preparation of March Filing
  • RTO West Benefits-Cost Analysis
  • Supplemental Activities by Bonneville
  • Public Outreach
  • Stakeholders
  • State PUCs
  • FERC
  • NW Delegation, etc.

18
Changes, With or Without RTO West
  • New facilities need to be built to meet demand
    and address reliability concerns
  • We face challenges maintaining reliability
  • System efficiency will require accurate load
    forecasts for each customer
  • Congestion has to be managed
  • Better regional coordination of transmission
    planning for cost-efficient results
  • Pressure exists to finish energy restructuring
  • Even without BPA participation, pressure remains
    to create an RTO for the region

19
Regional Priorities
  • Protection for rights to serve load obligations.
  • Benefit-Cost analysis that produces useable
    information.
  • No west-wide RTO.
  • Ensuring stakeholder needs are met through
    collaboration in region.
  • Ensuring NW Delegation representatives have ample
    opportunity to engage on issues and RTO West
    development, prior to BPA joining an RTO.
  • Regional flexibility to develop an RTO to meet
    regional needs. Avoid mandated standardization.
  • Improved Collaboration with, and defined role of
    State Commissions.

20
Western Market Vision
  • One Seamless West-Wide Market
  • Common Business Practices
  • No Trade Barriers
  • Minimum Transaction Costs
  • Three RTOs - a Necessary First Step
  • Retain Regional Accountability for Capital
    Expenditures, Reliability and Planning
  • Retain Regional Operating Knowledge
  • Share Services
  • Capture Symbiotic Benefits (e.g., act as back-up
    control center for each other)
  • Potential for fewer RTOs in the Future

21
Next Steps
  • Where do we go from here?

22
To Make a March Filing
  • Weve met with our public customers and have
    support for our participation
  • BPA must have Delegation Support, based on
    stakeholder input
  • Completion of a Benefit-Cost analysis
  • BPA must assure weve met our principles
  • Either we have met the principles or have a
    reasonable chance to meet them.
  • - Steve Wright Feb., 2002

23
Filings beyond March
  • Tariff
  • Generation Integration Agreement
  • Load Integration Agreement
  • Follow-up/Response to FERC Orders

24
Milestones to Startup
  • Stage II Filing Development
  • March, 2002
  • FERC Approval Process
  • 6-9-12 months?
  • State Commission Approval Process
  • 6-12 months
  • Congressional Briefings
  • On-going
  • Implementation
  • 12-36 months
  • RTO West Operational 2004/05/06?