CLS PROJECT STATUS - PowerPoint PPT Presentation

1 / 13
About This Presentation
Title:

CLS PROJECT STATUS

Description:

Kicker magnets (Danfysik) delivered by mid-February 2003 ... Install one sector by mid-December 2002. Install remaining sectors by end of February 2003 ... – PowerPoint PPT presentation

Number of Views:51
Avg rating:3.0/5.0
Slides: 14
Provided by: daniel111
Category:

less

Transcript and Presenter's Notes

Title: CLS PROJECT STATUS


1
  • CLS PROJECT STATUS
  • M.S. de Jong
  • Project Leader
  • November 16, 2002
  • Annual Users Meeting

2
Synchrotron Facility
Transfer Line Booster ring
E-gun Linac
Storage ring
Beamline End Station
3
Sector (1 of 12)
  • Beamlines on a single CLS sector
  • Two bending magnet lines
  • One or more ID lines
  • Use of chicanes to get 2 undulator lines per
    straight
  • Needed to meet demand for insertion device
    beamlines

4
Injector Status
  • Linac and transfer line to Booster
  • Modifications for 1 Hz operation complete
  • Continuing to improve control system and
    diagnotics
  • Booster (Turn-key system from Danfysik)
  • Commissioning of technical systems started in
    June and were completed in August (more detail in
    Les Dallins talk)
  • Formal acceptance of Booster completed by
    mid-September
  • Booster now shut down until needed for Storage
    ring commissioning

5
Storage Ring Status - 1
  • Major Sub-systems
  • Dipole magnets (Tesla) - delivered
  • Quadrupole and Sextupole magnets (Sigma-Phi)
    first set delivered, rest by year-end 2002
  • Corrector magnets (Budker Institute) delivered
    by year-end 2002
  • Kicker magnets (Danfysik) delivered by
    mid-February 2003
  • DC Power supplies (IE Power) 50 delivered,
    remained by year-end 2002
  • RF amplifier (Thales) commissioning at CLS
  • LHe plant (Linde) operating at CLS
  • RF cavity (ACCEL) delivery by year-end
  • Vacuum chambers (FMB) 8 sectors delivered,
    remainder by year-end
  • Supports and girders (Saskatoon) - delivered

6
Storage Ring Status - 2
  • Installation
  • Water cooling and support pillar installation
    started in November
  • Install one sector by mid-December 2002
  • Install remaining sectors by end of February 2003
  • Commissioning of sub-systems will be done in
    parallel, so far as possible
  • Target first injected beam in March 2003
  • Commissioning
  • Beam tests in evenings and week-ends
  • Main building must be evacuated until
    commissioning radiation surveys confirm design
    radiation levels
  • 3-week on / 3-week off schedule likely
  • Target light for first beamlines by mid-summer
    2003

7
IT Infrastructure
  • Phase I of IT infrastructure complete
  • Dual Cisco 6509 switches (1Gb ?10Gb)
  • Voice-over-IP telephones
  • Redundant multi-mode and single-mode fibre
    network throughout facility
  • Direct fibre connection available for each
    beamline
  • Virtual LANs for office, controls, users,
    beamlines, etc.
  • Phase II implementation started
  • 1-3 Terabyte Storage Area Network
  • Improved user connectivity to external Internet
    and CA4.net
  • Possible upgrading of local computational
    resources

8
Beamlines IR
  • High-resolution Far-IR Spectroscopy
  • Quotations received on spectrometer
  • RFPs for design-build of UHV and HV portions of
    optical system out by mid-December
  • Hutch construction started
  • 13 of budget committed by 2002 Oct 31
  • Start commissioning September, 2003
  • Mid-IR Microscopy
  • Quotations due on spectrometer
  • RFPs for design-build of UHV and HV portions of
    optical system out by mid-December
  • Hutch construction started
  • 25 of budget committed by 2002 Oct 31
  • Start commissioning October, 2003

9
Beamlines PGM SGM
  • VLS Plane Grating Monochromator
  • All major components ordered
  • Delivery of most components by 2003 June, except
    for Fixed-aperture High-Heat-Load most (2003
    October)
  • 185mm PPM undulator ready by 2003 June
  • ID vacuum chambers (APS) to be delivered in 2003
    July
  • 70 of budget committed by 2002 October 31
  • High-resolution Spherical Grating Monochromator
  • Same as above for most components
  • Shipment of existing SGM components from Madison
    at the end of summer 2003
  • 45 mm PPM undulator ready by mid-summer 2003
  • 80 of budget committed by 2002 October 31

10
Beamline Spectromicroscopy
  • Soft X-ray Spectromicroscopy
  • Mirrors, gratings and monochromator ordered
  • Mirror manipulator tenders under evaluation
  • Started design specification of microscopy
    end-station
  • ID vacuum chambers (APS) to be delivered in 2003
    July
  • All beamline components, including EPU
    (Elliptically Polarized Undulator), should be
    available by 2003 fall
  • ID straight designed to accommodate a second
    chicaned EPU
  • 40 of budget committed by 2002 October 31

11
Beamline CMCF-I
  • Canadian Macromolecular Crystallography Facility
  • Mirrors and beamline components ordered, with
    delivery scheduled for 2003 September
  • Work continues on white beam transport line and
    endstation specifications
  • Started work on specification of control and IT
    requirements
  • Magnets ordered for Small-gap Undulator (SGU),
    work continues on specification of vacuum chamber
  • Beamline completion planned by 2003 Fall, but SGU
    might not be ready until early 2004
  • 40 of budget committed by 2002 October 31

12
Beamline Micro-XAFS
  • Hard X-ray XAFS / Micro-probe
  • Micro-probe capability (2 µm resolution) and
    some powder diffraction capability added to
    design
  • Uses 31 mm multi-pole superconducting wiggler
  • Preliminary Design Report under review now
  • RFP for beamline and wiggler design-build
    expected to be issued by year end
  • Some risk that delivery completion will not be
    possible before early 2004
  • 7 of budget committed by 2002 October 31

13
SUMMARY
  • Injection System Operational
  • Storage Ring installation has started
  • First injected beam in early spring 2003
  • First light for beamlines in mid-summer 2003
  • Five beamlines ready for light by fall 2003
  • Two IR lines
  • Three soft X-ray lines
  • CMCF line ready by fall 2003, except for ID may
    be delayed until early 2004
  • Micro-XAFS line ready in early 2004
Write a Comment
User Comments (0)
About PowerShow.com