Renewables and System Services - PowerPoint PPT Presentation

1 / 16
About This Presentation
Title:

Renewables and System Services

Description:

Demand Side Units. Inter system exchanges. Loading of already synchronised plant. ... The plant becomes slower to react to system needs the longer it remains off load. ... – PowerPoint PPT presentation

Number of Views:60
Avg rating:3.0/5.0
Slides: 17
Provided by: Bui673
Category:

less

Transcript and Presenter's Notes

Title: Renewables and System Services


1
Renewables and System Services
  • Ann Scully

2
Existing Transmission System
400 kV - 440 km 220 kV - 1,830 km 110 kV -
4,000 km
3
(No Transcript)
4
Context
Weekly Peaks 2006 2007
  • Operational Generation Capacity 6,618 MW
  • Certified Generation Capacity 6,325 MW
  • Number of Generation Customers Certified
    Operational 26
  • Total Connected Renewable Generation Capacity
    1,071 MW

5
Context
Electricity Consumption by Generation Source 2007
6
Context
Installed Renewable Capacity
Note 2008 Figures are projected based on
connection dates
7
Context
  • We need services which the TSO believes will
    enhance secure, reliable and economic operation
    of the transmission system
  • With the introduction of large-scale wind
    generation additional variability arises.
  • Increased dependence on wind forecasting.
  • Forecasting errors

8
Context
  • Under generation
  • The additional reserve to meet these requirements
    will be needed in the range of minutes to hours.
  • You can obtain the reserve in these time frames
    from the following sources
  • Demand Side Units
  • Inter system exchanges.
  • Loading of already synchronised plant.
  • Off load available plant.
  • Open cycle gas turbines.
  • Pump storage plant.
  • Others?

9
Proposed New Services
  • Off load Plant Warming Contracts and Maintenance
    of Heat State
  • Combined Cycle Gas Turbines (CCGT) Multimode
    Operation
  • Some proposed services, others will be considered
    based on consultation with industry

10
Off load Plant Warming Contracts and Maintenance
of Heat State
  • Conventional steam plant that is not connected to
    the system but available to start becomes colder,
    takes longer to re-synchronise, and is slower to
    load up, the longer it is off load.
  • The warmth state of a unit, which directly
    relates to its time to resynchronise, moves from
    hot to warm to cold after desynchronising.
  • The plant becomes slower to react to system
    needs the longer it remains off load.
  • Plant that can change to or maintain a hotter
    warmth state will reduce quick start plant
    running periods, Open Cycle Gas Turbine (OCGT)
    capacity requirements, and meet additional
    reserve requirements.
  • We are proposing two new products
  • The ability to change to and maintain a hotter
    warmth state
  • The ability to maintain hot warmth state after
    resynchronisation

11
The Payment
  • Payment would be a fixed rate per hour to
    maintain warmth state.
  • The service would be tested by the TSO a test
    failure would incur a charge.
  • Delivery or non-delivery of the service would be
    assessed by the TSO by reviewing the time to
    synchronise of the unit. Non delivery would incur
    a charge.
  • There would be an interaction between warming
    contracts and the SEM which would need to be
    considered in developing the warming contract
    arrangements.

12
Combined Cycle Gas Turbines (CCGT) Multimode
Operation
  • CCGTs can operate in either open or closed cycle
    modes.
  • If the steam turbine is bypassed using boiler gas
    side bypassing, the gas turbine will operate
    independently at efficiencies of approximately
    30 and be fully available within relatively
    short timeframes (lt20 mins) for full gas turbine
    output.
  • Steam Turbine not started steam not used
  • Open cycle operation with boiler bypassing
    provides a fast run up ability similar to an OCGT

13
Combined Cycle Gas Turbines (CCGT) Multimode
Operation
  • The product required is
  • Open Cycle Gas Turbine operation
  • Flexibility to continue to closed cycle operation
    after dispatched on open cycle
  • OCGT operation would be paid on the basis of the
    difference between SEM income and an agreed
    income for operating in OCGT mode (determined on
    a costs plus basis in the procurement process).

14
Other changes
  • Wind grid code introduced
  • Specific renewable integration cross functional
    group created
  • Gate process introduced to handle incorporation
    of large amounts of wind
  • Wind farms paid for the provision of Reactive
    Power were capable and in line with Grid code

15
Reactive Power Payment for Wind
  • Commercial arrangements for the provision of
    Reactive Power Ancillary Services
  • Required
  • Grid Code requirements met.
  • Arrangements reflects those for thermal/ hydro.
  • utilisation payments (for production or
    consumption of Reactive Power) and, where
    appropriate, capability payments (for being
    available to produce or consume Reactive Power).
  • Reactive Power capability payments will only be
    made to WFs that can maintain Reactive Power
    capability that is not dependant on energy
    production.
  • interim in nature pending all-island
    harmonisation of Ancillary Services.

16
  • www.EirGrid.com
Write a Comment
User Comments (0)
About PowerShow.com