Title: Workstream 2 Dispatchability and Variability Management Studies
1Workstream 2Dispatchability and Variability
Management Studies
- Leslie Bryans SONI
- Paul Smith ESB National Grid
- (for the Working Group)
2Background and key issuesLeslie Bryans
Study scope, programme etc.Paul Smith
3Background and key issuesLeslie Bryans
Study scope, programme etc.Paul Smith
4The issues
- Effect of non-wind renewables upon the ability to
manage - Variability and uncertainty management from wind
and like technologies - Effect of better forecasting and advanced wind
management schemes - Effect of generation mix and load flexibility on
the overall picture
5Types of generation
- Renewable and Embedded Generation with
traditional certainty - Availability
- Certainty
- Wind and like technologies with high uncertainty
/ variability
6Non-wind issues
- Suppose there was ???1000MW ??? of non-wind
embedded generation - What plant would the embedded generation
displace? - Would embedded generation be fully dispatchable
(a size issue)? - Would it provide needed ancillary services?
- If so its just like traditional generation
albeit in different locations Grid Code
provisions are useful but do not apply to very
small plant - If not then we need to understand what this
???1000MW??? means for system management?
7Key questions
- For generation dispatch scenarios
- How much embedded is likely as
- dispatchable
- partially dispatchable
- non-dispatchable
- Where?
- When?
8Energy balance and unit commitment / dispatch
with wind like technologies
- What do we mean by wind variability and
uncertainty? - How can we assess the impacts?
- How to manage wind variability and uncertainty?
9Wind Energy Variability
10Variability analysed
96 confidence
Be careful available not Operating level
11Variability geo-diversity one farm and
all-island (44 farms)
Improvement 29 Probably saturates With
penetration
Improvement 75 probably Improves further With
penetration
12Wind Variability and forecast
Real prediction from Anemos
13(No Transcript)
14Natural Uncertainty Better local forecasting
Improvable Uncertainty Better general forecasting
Gain by forecasting
15Power System Reserve
- Rescue flows
- Load prediction errors
- Wind prediction errors
16(No Transcript)
17Power System Reserve
- Very Rapid 5 sec
- spinning reserve
- Disconnectable load
- Rapid
- Energy storage
- Medium
- Standing OCGTs and like plant 10 min
- Progressively longer
- Hot, warm and cold thermal plant 24 hour
No option Some options All options
18System Inertia
- Non-synchronous generators may not contribute to
system inertia - This could hamper the ability to deal with
frequency transients - Will this limit the penetration of renewables?
19Background and key issuesLeslie Bryans
Study scope, programme etc.Paul Smith
20Workstream 2(b)
- Detailed accurate modelling of commitment and
dispatch taking account of uncertainties - Probably 3 later years each with 5 renewables
scenarios - Renewables, especially wind, time series will be
required - Plant capacity, replacement, emissions and cost
assumptions - Demand management assumptions
- Wind forecasting accuracy assumptions
21Basic Presumption
- Governments want to maximise contribution of
renewables to policy objectives such as - Reduction of greenhouse gas and other emissions
- Reduction of dependence on external primary
energy sources - Reduction of future cost uncertainty
- Local economic and social benefits
- Security of energy supplies
- Changes in renewable generation output, either
predictable or unpredictable, must be covered by
demand management schemes, generation or
interconnection to UK.
22Basic Study Objective
- Model future operation of system so as to
estimate - Future operation costs
- Future plant emissions
- For a number of renewables scenarios
- Identify and analyse measures to facilitate
greater levels of renewables
23A modelling challenge
- Modelling current system operation for production
cost studies, constraints studies, ancillary
services budgets etc. is a challenge, even though
we know how the system is operated. - For this study, we need to model system operation
where we dont yet know how the system will be
operated
24Tasks
- Propose and discuss methodology
- Develop commitment and dispatch model and test on
2005 case - Construct renewable generation time series
- Carry out detailed dispatch studies for base
scenarios, estimating costs, emissions etc. - Investigate options to improve dispatch,
integrate more renewables - Prepare overall report
252005 model verification case
- Plant mix as now
- Load as recorded
- Renewables as installed (using scaled 2004 wind
data which is available and coded)
26Validation
- Model variability matches observed pattern
- Estimation of variability change with wind farm
penetration - Dispatch model mirrors real dispatches
- Models are extensible with similar error rates
27Scenarios
- 2005 validate model
- 2010
- 2015
- 2020
- Renewables scenarios based on results of
screening study (WS 2(a)) - Impact of different plant mix, more storage,
demand-side controls to be assessed
28Results required - 1
- Limits to renewable generation and techniques to
overcome those limits - System operation costs for each scenario
- Emissions of CO2, SO2 and NOx for each scenario
- Utilisation of other plant throughout the year
(load factors, starts, typical output profiles) - Commitment and dispatch techniques assumed for
the model - Dispatches for common reference points summer
min, max, summer average, system average, winter
average , winter peak
29Results required - 2
- How limiting dispatches are managed
- Management of extreme events
- Impact of reducing uncertainty (e.g. by improved
output forecasting) - Analysis of cost differences between scenarios,
to show key drivers of cost differences - Plant mix, energy storage and controllable load
impacts - Dispatch rules emerging from studies
- Any outputs required for WS3 WS4
30Method of Working
- Close co-operation with TSOs throughout
- Timely interim reports
- Regular consultations with stakeholders
- High quality final reports
- Presentation of findings to stakeholders
31Timings
- Study to be let about end of March or early April
2006 - Methodology discussions on-going
- Methodology report - mid-summer
- Test case late summer
- Draft final report late autumn
32Key Selection Criteria
- Very well developed understanding of dispatching
power systems - Knowledge or experience of managing uncertainty
and variability in power systems - Well able to interface with TSOs, peer and
intellectual reviewers - Meetings with short-listed bidders may be
required
33Question time
34Wind Variability and Uncertaintythese slides are
for reference and not part of presentation
35Variability
36Objective function and constraints
- Objective
- Within security standards -Total dispatch cost
minimisation (including start-up etc and fixed
heat - Constraints
- Ramp rates
- Time constraints and emissions limits
- Security operating constraints
37Structure methodology
- Review dispatch methodologies in use / under
development with high penetrations of renewables - Agree dispatch methodology and reserve strategies
with TSOs for - Routine daily management
- Extreme events
- Test methodology for realism and accuracy
38Future value factors
- Primary fuel costs
- Coal up to / tonne
- Gas up to / tonne
- gas to be unconstrained up to pipeline capacity
- Oil up to / tonne
- Carbon emissions maket price /tonne
- Nox and Sox not considered significant
39Structure
- Scenarios deal with different renewables
penetration and mix - Base Cases / per scenario to be set up as a datum
from which to measure - Base case new plant added to the system and
replacement plant will be CCGT - Developed cases show quantified benefits or not
over base cases - Plant mix, controllable load, energy storage,
better forecasting - Consultant to propose optimisation of methods and
number of studies