Professor Rudi Klein, Barrister - PowerPoint PPT Presentation

1 / 26
About This Presentation
Title:

Professor Rudi Klein, Barrister

Description:

March 2004: Gordon Brown (as Chancellor) announces review of Construction Act ... correct and clerical/ typographical error arising by accident/omission ... – PowerPoint PPT presentation

Number of Views:151
Avg rating:3.0/5.0
Slides: 27
Provided by: carolc76
Category:

less

Transcript and Presenter's Notes

Title: Professor Rudi Klein, Barrister


1
Society of Construction Law Oxford Region
23 April 2009
Construction Act Reforms
  • Professor Rudi Klein, Barrister
  • Chief Executive, Specialist Engineering
    Contractors Group

2
How did we get here?
  • March 2004 Gordon Brown (as Chancellor)
    announces review of Construction Act against
    background of continuing payment problems.
  • Original proposal was for an RRO.
  • Formal consultations in 2005 2007.

3
  • Draft Construction Contracts Bill published for
    consultation in July 2008.
  • Revised Bill receives 1st Reading in the House of
    Lords on 4 December 2008 (some changes from
    original draft)

4
  • Our amendments.will create greater
    certainty and clarity of cash flow for all in
    the construction supply chain (emphasis
    added).
  • Baroness Andrews in 2nd Reading debate in
    House of Lords on 17.12.2008

5
AMENDMENTS TO THE PAYMENT PROVISIONS
6
CURRENT WEAKNESSES
  • S.110(1)(a) Contracts must have adequate
    mechanism for determining what payments become
    due and when
  • This is essential for operating ss.111 112
    (withholding and suspension)

7
  • The absence of.a means for resolving
    deadlock.renders inadequate the machinery for
    determining when payments are due.
  • Lord Macfadyen in Maxi Construction v Merton
    Rolls 2001 CILL 1784

8
CURRENT WEAKNESSES
  • Likelihood is that majority of contracts do not
    have an adequate mechanism
  • Scheme not helpful there is only a list of what
    may be included in interim payments together
    with due dates and final payment dates

9
THE CHANGESNEW S.111
  • PAYER MUST PAY NOTIFIED SUM ON OR BEFORE THE
    FINAL DATE FOR PAYMENT

10
NOTIFIED SUM
  • The sum specified in notice issued by
  • Payer
  • Payee
  • Payee, where payer fails to issue notice

11
  • Notices must comply with new s.110(A)
    replacing s.110(2) requiring payer to issue
    payment notice

12
NOTICE REQUIREMENTS
  • Contracts to indicate which party to issue
    notices
  • Notices to be issued no later than 5 days after
    payment due date
  • Amount of sum considered due must be stated
    together with basic calculation

13
PAYERS FAILURETO ISSUE NOTICE
  • Payee can issue notice instead but final date for
    payment extended from expiry of 5 days
  • But final date for payment intact if payee issues
    application before payment due date (provided
    such application is required/ permitted by
    contract)

14
NOTICE TO PAY LESS
  • Payer can issue notice of intention to pay less
    than notified sum
  • Notice must indicate sum payer considers due on
    date notice is served and basis of calculation
  • Must be given no later than the prescribed
    period before date for payment

15
Payment ProcedureOption A
Notified sum to be discharged (on/before final
day for payment
Payer/payee to issue notified sum
5 days
Final Date for payment
Payment due date
16
Payment ProcedureOption B
Payer/payee issues notified sum
Payer issues Reduction Notice
Reduced notified sum discharged
5 days
Prescribed period
Final date for payment
Payment due date
17
Payment ProcedureOption C
Extended by 3 days
Payee operates default procedure
Payer fails to issue notified sum
5 days
3 days
Final date for payment
Payment due date
18
CONDITIONAL PAYMENT PROVISIONS
  • Adequate mechanism requirement not satisfied
    where payment made conditional on performance of
    obligations under another contract or decision by
    any person as to whether such obligations have
    been performed
  • New sub-section 110(1)A

19
CONDITIONAL PAYMENTPROVISIONS (2)
  • Will 110(1)(A) actually outlaw pay-when-certified
    clauses?
  • Will 110(1)(A) conflict with current s.113?
  • Pay-when-paid exemption in s.113 not removed

20
OTHER CHANGES
  • No requirement to pay sum due where payee became
    insolvent after prescribed period and contract
    permits payer not to pay sum due in this event
    (prompted by Melville Dundas case)
  • Improvement to suspension (s.112) allowing payee
    to recover reasonable compensation for costs and
    expenses reasonably incurred during suspension
  • Payee can suspend any or all of his contractual
    obligations

21
AMENDMENTS TO ADJUDICATION PROVISIONS
22
S.107 REQUIREMENT FOR CONTRACTS TO BE IN
WRITING(RJT Consulting Engineers v DM
Engineering (2002) BLR 217
  • S.107 repealed oral or oral/partly written
    contracts within scope of Act
  • BUT provisions relating to adjudication (8
    compliance points) must be in writing to comply
    with s.108

23
SLIP RULE(New s.108(3)A)
  • Contracts must include provisions that
    adjudicator has power to correct and clerical/
    typographical error arising by accident/omission
  • What about time limits on exercise of power?

24
COSTS IN ADJUDICATION(New 108A)
  • Agreement allocating costs relating to the
    adjudication ineffective unless made in writing
    after giving notice of intention to refer the
    dispute to adjudication
  • This also refers to the fees and expenses of the
    adjudicator

25
VERDICT
  • Payment provisions getting there but are very
    complex and still lean towards payer
  • Abolition of s.107 welcome
  • Abolition of Bridgeway v Tolent welcome
  • What about adjudicators fees and costs?
  • Need for single adjudication procedure but is
    this too intrusive into freedom of contract?

26
Society of Construction Law Oxford Region
23 April 2009
Construction Act Reforms
  • Professor Rudi Klein, Barrister
  • Chief Executive, Specialist Engineering
    Contractors Group
Write a Comment
User Comments (0)
About PowerShow.com