Title: Project Planning, Scheduling, and Controlling
1Project Planning, Scheduling, and Controlling
Project Planning 1. Setting goals 2. Defining the
project 3. Tying needs into timed project
activities 4. Organizing the team
Project Scheduling 1. Tying resources to specific
activities 2. Relating activities to each
other 3. Updating and revising on regular basis
Project Controlling 1. Monitoring resources,
costs, quality and budgets 2. Revising and
changing plans 3. Shifting resources to meet
demands
Before Project
During Project
2Project Management Models
- PERT Program Evaluation and Review Technique
- CPM -Critical Path Method
3Six Steps Common toPERT and CPM
- 1. Define the project and all of its significant
activities or tasks. - 2. Develop relationships among the activities.
Decide which activities must precede and which
ones must follow others. - 3. Draw the network connecting all of the
activities. - 4. Assign time and/or cost estimates to each
activity - 5. Compute the longest time path through the
network. This is called the critical path. - 6. Use the network to help plan, schedule,
monitor, and control the project.
4Questions That May Be Addressed by PERT and CPM
- 1. When will the project be completed?
- 2. What are the critical activities or tasks in
the project? - 3. Which are the noncritical activities?
- 4. What is the probability that the project will
be completed by a specific date? - 5. Is the project on schedule, ahead of schedule,
or behind schedule? - 6. Is the project over or under the budgeted
amount? - 7. Are there enough resources available to finish
the project on time? - 8. If the project must be finished in less than
the scheduled amount of time, what is the best
way to accomplish this at least cost?
5Advantages of PERT/CPM
- useful at several stages of project management
- straightforward in concept, and not
mathematically complex - uses graphical displays employing networks to
help user perceive relationships among project
activities - critical path and slack time analyses help
pinpoint activities that need to be closely
watched - networks generated provide valuable project
documentation and graphically point out who is
responsible for various project activities - applicable to a wide variety of projects and
industries - useful in monitoring not only schedules, but
costs as well
6Limitations of PERT/CPM
- project activities must be clearly defined,
independent, and stable in their relationships - precedence relationships must be specified and
networked together - time activities in PERT are assumed to follow the
beta probability distribution -- this may be
difficult to verify - time estimates tend to be subjective, and are
subject to fudging by managers - there is inherent danger in too much emphasis
being placed on the critical path
7Example of a Gantt Chart
A
B
C
Activities
D
E
Time
10-5
8PERT/CPM TERMS
- ES earliest time activity can begin
- EF earliest time activity can end
- EF ES t
- LS latest time activity can begin without
delaying project - LS LF - t
- LF latest time activity can end without
delaying project
9PERT/CPM TERMS
- SLACK TIME free time
- LS - ES or LF - EF
- CRITICAL PATH longest path, or the one with NO
slack
10Methods of Diagramming Projects
A
- Activity on arrow
A
- Activity on node
10-7
11EXHIBIT 10.3 CPM Network for Computer Design
Project
8
7
F
C
21
2
A
G
4
5
2
B
E
D
10-8
12Crash and Normal Times and Costs
Activity Cost
Crash
Crash Cost - Normal Cost
34,000 33,000 32,000 31,000 30,000
Crash Cost/Week
Normal Time - Crash Time
Crash Cost
34,000 - 30,000
3 - 1
4,000
2,000/Week
2 Weeks
Normal
Normal Cost
1
2
3
Time (Weeks)
Crash Time
Normal Time
PG 13.19
13CRASH COSTING
- 1. Find critical path.
- 2. Find cheapest act. in critical path
- 3. Reduce time until
- a. Cant be reduced
- b. Another path becomes critical
- c. Increase in direct costs exceeds savings from
shortening project - 4. Return to Step 1, as long as savings.
14 Time-Cost Trade-Off
10-9
15Beta Probability Distribution with Three Time
Estimates
Probability
Probability of 1 in 100 (b) Occuring
Probability of 1 in 100 (a) Occuring
Optimistic Time (a)
Most Likely Time (m)
Pessimistic Time (b)
Activity Time
PG 13.8
16Time Estimates (in weeks) for project
Optimistic a
Most Probable- m
Pessimistic b
Expected Time t (a 4m b)/6
Variance (b - a)/62
Activity
A B C D E F G H
1 2 1 2 1 1 3 1
2 3 2 4 4 2 4 2
3 4 3 6 7 9 11 3
2 3 2 4 4 3 5 2
Total 25 weeks
17Probability of Project Meeting the Deadline
Project Standard Deviation, ?T
Project Variance
Due Date - Expected Completion Date
Z
?T
16 - 15
0.57
1.76
.57 Standard Deviations
Probability (T ? 16 Weeks) is 71.6
16 Weeks
15 Weeks
Time