Title: Proposed Houston Solar Community Project
1ProposedHouston Solar Community Project
- A Renewables Integration and Smart Grid
Demonstration - Presented to
- CCET Board of Directors
- January 9, 2009
2Presentation Overview
- I. Project Background, Objectives, and Status
-
- II. Description of Individual Tasks for Planning
Document (In Preparation) -
- III. Questions, Comments, Discussion
3 Purposes
- Understand how a large renewable energy
Distributed Generation source a) will interact
with the grid and b)its overall electrical
patterns. - 2. Test technical and economic aspects of other
emerging technologies including community and
home battery storage, electric vehicle charging,
load controllable appliances, wind integration,
and interoperabilty of devices.
4 Purposes (Cont)
- 3. Evaluate the above combined with an Enhanced
DR community-based DR program - 4. Recommend policy changes needed to eliminate
barriers to these type of developments and
technologies.
5Project Overview--Status
- Two TAG meetings on-site with Land Tejas
- Several concept papers
- One meeting on site with Energy Efficiency
program managers from Oncor and CenterPoint--want
a more detailed Project Plan by early February - Project Plan to CCET Board in March
6Project BackgroundDiscovery at Spring Trails
Baseline
- Land Tejas building a 3000-home master-planned
community north of Houston - Each home will have between 1 and 3 Kw of rooftop
photovoltaic and meet extremely rigorous energy
conserving requirements - Overall electric savings is in 30 to 40
- Community will operate a 250 kW solar farm to
offset community infrastructure needs - AMI on residences by CenterPoint
7Project Overview (Cont)
- Duration 4 to 5 years
- Costs 2.7 million (rough estimate)
- Funding
- a) Energy Efficiency program (RD or MT)
- b) EPRI (tailored collaboration)
- c) DoE (either part of Regional Demonstation
Program or other) - d) NSF (for participating university
researchers)
8Presentation Overview
- I. Project Background, Objectives, and Status
-
- II. Description of Individual Tasks for Project
Plan (In Preparation) -
- III. Questions and Answers
9Project Plan Contents
- 1. Purposes
- 2. Executive Summary
- 3. Discovery at Spring Trails Development Plan
- 4. Project Tasks and Schedule
- 5. Project Costs
- 6. Participants and Roles
- 7. Project Management
- 8. Detailed Task Descriptions
- 9. Project Funding Plan
10- 10 Years Developing in the Houston area
- Averaged 2000 lot sales per year
- Resort style communities with reasonably-priced
homes 130s 400s - Environmentally Friendly Energy Efficient
- Mandates technologies throughout communities
11(No Transcript)
12Land Tejas Development Team
13Location and Amenities
- Spring, Tx, Montgomery County, piney woods along
Spring Creek - 1200 Acres - 3000 1-3 kW Solar Homes
- Rec. Center, Clubhouse, Lakes, Trails
- Fiber to Home Network - Energy Mgmt
- Community-Wide Water Reuse Program
- 250 kW central solar array
-
14(No Transcript)
15Project Plan Contents
- 1. Purposes
- 2. Executive Summary
- 3. Discovery at Spring Trails Development Plan
- 4. Project Tasks and Schedule
- 5. Project Costs
- 6. Participants and Roles
- 7. Project Management
- 8. Detailed Task Descriptions
- 9. Project Funding Plan
16Project Tasks and Schedule13 Tasks
- 1. Baseline power monitoring,
- 2. Comparative energy use profiles,
- 3. Decentr. EV charging
- 4. Centralized EV chrg.
- 5. Decentr battery strg.
- 6. Community bat.strg.
- 7. Enhanced DR Ph. I
- 8. Enhanced DR Ph. 2
- 9. Load interruptible appliances
- 10. Storing wind generated power
- 11. Interoperability
- 12. Univ. Research Prjs
- 13. Data integration and analysis
17Overall Schedule
- 2009Baseline Monitoring, Submit Proposals.
- 2010Begin all tasks except Phase II Enhanced DR
and Decentralized Battery Storage. - 2011-All tasks underway with Phase I DR
completed. - 2012All tasks underway.
- 2013--Project completion and Final Reporting
18Project Plan Contents
- 1. Purpose
- 2. Executive Summary
- 3. Discovery at Spring Trails Development Plan
- 4. Project Tasks and Schedule
- 5. Project Costs
- 6. Participants and Roles
- 7. Project Management
- 8. Detailed Task Descriptions
19Overall Costs (Rough Estimate)
- Capital Costs Battery Storage gt600,000,
monitoring and measurements gt200,000, Other
250,000 for 1.1 million - Labor and services University research
projects, data gathering and analysis, management
and integration contractor 1.6 million - As project gets better defined and individual
cost estimates come in, better precision.
20Project Plan Contents
- 1. Purpose
- 2. Executive Summary
- 3. Discovery at Spring Trails Development Plan
- 4. Project Tasks and Schedule
- 5. Project Costs
- 6. Participants and Roles
- 7. Project Management
- 8. Detailed Task Descriptions
- 9. Funding Plan
21Some Possible Participants and Roles
22Project Plan Contents
- 1. Purpose
- 2. Executive Summary
- 3. Discovery at Spring Trails Development Plan
- 4. Project Tasks and Schedule
- 5. Project Costs
- 6. Participants and Roles
- 7. Project Management
- 8. Detailed Task Descriptions
- 9. Funding Plan
23Project Management
- CCET Management Team
- Direct Funders and,
- In-Kind Service Providers (including Land Tejas)
- PI, Management and/or Integrating Contractor
reporting to CCET COO
24Project Plan Contents
- 1. Purpose
- 2. Executive Summary
- 3. Discovery at Spring Trails Development Plan
- 4. Project Tasks and Schedule
- 5. Project Costs
- 6. Participants and Roles
- 7. Project Management
- 8. Detailed Task Descriptions
- 9. Funding Plan
25Project PlanSection 8 Details
- 1. Purpose
- 2. Subtasks
- 3. Schedules and
- Milestones
- 4. Equipment
- 5. Labor
- 6. Data flows
- 7. Costs (materials, time)
- 8. Data analysis, task integration
- 9. Unresolved issues
26Task 1Baseline Power Monitoring
- Purpose
- To measure voltages and power flows within
the community and along the feeder serving the
community to better understand impacts of
distributed renewable generation. - Author CenterPoint
- Status Rough draft was submitted this week
27Task 2Comparative Energy Use Profiles
- Purpose To provide quantifiable energy savings
from Discovery at Spring Trails (DST) both as a
community and individual homes vis-Ã -vis very
similar adjacent masterplanned community without
solar and ultra high efficiency measures. - Author CenterPoint
- Status Rough draft received this week.
28Task 3Decentralized EV/PHEV Charging
- Purpose Determine demand patterns for
garage-based electric vehicle charging systems - Author CenterPoint
- Status No drafts received
29Task4Centralized EV Charging
- Purpose Design, construct, demonstrate and
evaluate a community-based electric vehicle
overnight charging station - Author CenterPoint
- Status No drafts received
30Task 5Decentralized Battery Storage
- Purpose Evaluate cost effectiveness of
individual residential battery storage units - Author GridPoint
- Status Cost estimates received, no write up
31Task 6Centralized Battery Storage
- Purpose Determine how large scale community
battery storage could be used with 250 kW solar
array as a possible DSM resource and in future
micro grid application. - Author Xtreme Power? Others?
- Status Rough price estimate from Xtreme Power
32(No Transcript)
33Task 7Community Wide Enhanced DR Phase I
Critical Peak Pricing
- Purpose Demonstrate and evaluate efficacy of a
critical peak pricing-based DR program in a
masterplanned green community designed
cooperatively. To be designed by several REPs
with one REP serving as load aggregator. - Author Bob Davis (need inputs from REPs)
- Status Strawman only
34Critical Peak Pricing Strawman
- Ten to 20 times per year residents who opt into
the program will be given one days notice of a
CPP event - Rates during event may five times normal
- 100 residences allowed to participate in exchange
for cash awards - One cooling season (May through Sept 2010) Phase
I - Could be combined with a summer time on-peak and
off-peak time of use rates
35Task 8Community Wide Enhanced DR Phase II Real
Time Pricing
- Purpose Demonstrate use of real time pricing in
a masterplanned green community - Author Bob Davis (need inputs from REPs)
- Status Strawman only
36Real Time Pricing
- Access real time wholesale prices via ERCOT
- Develop pricing program
- Measure demand price responsiveness through a
cooperatively developed offer to the aggregated
load manager - One full year duration (2011)
- Phase IIa in third year (2012)in which REPs
develop proprietary real time pricing with
limited data sharing among all participants
37Task 9DR with Interruptible Load Appliances
- Purpose Demonstrate use of load controllable
appliances in HAN and Enhanced DR - Author GE (Patrick McElheny)
- Status Write up underway
38GE Load Controllable Devices
Signal from REP
Smart Electrical Communications Hub
39Task 10Wind Integration/ Storage
- PurposeEvaluate feasibility of storing wind
generated power via PPA for storage on site in
community battery storage. - Author None
- Status No action
40Task 11Interoperability Analyses
- Purpose Assess features of communication within
the home and outside the meter to determine needs
for application of standards. - Author None
- Status No action
41Task 12University Research Agenda
- Purpose Conduct targeted RD to deal with
issues arising in the preceding tasks (e.g.,
improving charging efficiencies in centralized
station, evaluating DR programs, interoperability
issues, etc) - Author None
- Status No action
42Task 13Data Integration and Analyses
- Purpose Assure that methods and quality of data
collected is uniform and sufficient to support
the objectives of each task. - Author None
- Status No action
43Questions?