Proposed Houston Solar Community Project - PowerPoint PPT Presentation

1 / 43
About This Presentation
Title:

Proposed Houston Solar Community Project

Description:

... be given one day's notice of a CPP 'event' Rates during event may five times normal ... Author: None. Status: No action. Task 12 University Research Agenda ... – PowerPoint PPT presentation

Number of Views:144
Avg rating:3.0/5.0
Slides: 44
Provided by: bob4135
Category:

less

Transcript and Presenter's Notes

Title: Proposed Houston Solar Community Project


1
ProposedHouston Solar Community Project
  • A Renewables Integration and Smart Grid
    Demonstration
  • Presented to
  • CCET Board of Directors
  • January 9, 2009

2
Presentation Overview
  • I. Project Background, Objectives, and Status
  • II. Description of Individual Tasks for Planning
    Document (In Preparation)
  • III. Questions, Comments, Discussion

3
Purposes
  • Understand how a large renewable energy
    Distributed Generation source a) will interact
    with the grid and b)its overall electrical
    patterns.
  • 2. Test technical and economic aspects of other
    emerging technologies including community and
    home battery storage, electric vehicle charging,
    load controllable appliances, wind integration,
    and interoperabilty of devices.

4
Purposes (Cont)
  • 3. Evaluate the above combined with an Enhanced
    DR community-based DR program
  • 4. Recommend policy changes needed to eliminate
    barriers to these type of developments and
    technologies.

5
Project Overview--Status
  • Two TAG meetings on-site with Land Tejas
  • Several concept papers
  • One meeting on site with Energy Efficiency
    program managers from Oncor and CenterPoint--want
    a more detailed Project Plan by early February
  • Project Plan to CCET Board in March

6
Project BackgroundDiscovery at Spring Trails
Baseline
  • Land Tejas building a 3000-home master-planned
    community north of Houston
  • Each home will have between 1 and 3 Kw of rooftop
    photovoltaic and meet extremely rigorous energy
    conserving requirements
  • Overall electric savings is in 30 to 40
  • Community will operate a 250 kW solar farm to
    offset community infrastructure needs
  • AMI on residences by CenterPoint

7
Project Overview (Cont)
  • Duration 4 to 5 years
  • Costs 2.7 million (rough estimate)
  • Funding
  • a) Energy Efficiency program (RD or MT)
  • b) EPRI (tailored collaboration)
  • c) DoE (either part of Regional Demonstation
    Program or other)
  • d) NSF (for participating university
    researchers)

8
Presentation Overview
  • I. Project Background, Objectives, and Status
  • II. Description of Individual Tasks for Project
    Plan (In Preparation)
  • III. Questions and Answers

9
Project Plan Contents
  • 1. Purposes
  • 2. Executive Summary
  • 3. Discovery at Spring Trails Development Plan
  • 4. Project Tasks and Schedule
  • 5. Project Costs
  • 6. Participants and Roles
  • 7. Project Management
  • 8. Detailed Task Descriptions
  • 9. Project Funding Plan

10
  • 10 Years Developing in the Houston area
  • Averaged 2000 lot sales per year
  • Resort style communities with reasonably-priced
    homes 130s 400s
  • Environmentally Friendly Energy Efficient
  • Mandates technologies throughout communities

11
(No Transcript)
12
Land Tejas Development Team
13
Location and Amenities
  • Spring, Tx, Montgomery County, piney woods along
    Spring Creek
  • 1200 Acres - 3000 1-3 kW Solar Homes
  • Rec. Center, Clubhouse, Lakes, Trails
  • Fiber to Home Network - Energy Mgmt
  • Community-Wide Water Reuse Program
  • 250 kW central solar array

14
(No Transcript)
15
Project Plan Contents
  • 1. Purposes
  • 2. Executive Summary
  • 3. Discovery at Spring Trails Development Plan
  • 4. Project Tasks and Schedule
  • 5. Project Costs
  • 6. Participants and Roles
  • 7. Project Management
  • 8. Detailed Task Descriptions
  • 9. Project Funding Plan

16
Project Tasks and Schedule13 Tasks
  • 1. Baseline power monitoring,
  • 2. Comparative energy use profiles,
  • 3. Decentr. EV charging
  • 4. Centralized EV chrg.
  • 5. Decentr battery strg.
  • 6. Community bat.strg.
  • 7. Enhanced DR Ph. I
  • 8. Enhanced DR Ph. 2
  • 9. Load interruptible appliances
  • 10. Storing wind generated power
  • 11. Interoperability
  • 12. Univ. Research Prjs
  • 13. Data integration and analysis

17
Overall Schedule
  • 2009Baseline Monitoring, Submit Proposals.
  • 2010Begin all tasks except Phase II Enhanced DR
    and Decentralized Battery Storage.
  • 2011-All tasks underway with Phase I DR
    completed.
  • 2012All tasks underway.
  • 2013--Project completion and Final Reporting

18
Project Plan Contents
  • 1. Purpose
  • 2. Executive Summary
  • 3. Discovery at Spring Trails Development Plan
  • 4. Project Tasks and Schedule
  • 5. Project Costs
  • 6. Participants and Roles
  • 7. Project Management
  • 8. Detailed Task Descriptions

19
Overall Costs (Rough Estimate)
  • Capital Costs Battery Storage gt600,000,
    monitoring and measurements gt200,000, Other
    250,000 for 1.1 million
  • Labor and services University research
    projects, data gathering and analysis, management
    and integration contractor 1.6 million
  • As project gets better defined and individual
    cost estimates come in, better precision.

20
Project Plan Contents
  • 1. Purpose
  • 2. Executive Summary
  • 3. Discovery at Spring Trails Development Plan
  • 4. Project Tasks and Schedule
  • 5. Project Costs
  • 6. Participants and Roles
  • 7. Project Management
  • 8. Detailed Task Descriptions
  • 9. Funding Plan

21
Some Possible Participants and Roles

22
Project Plan Contents
  • 1. Purpose
  • 2. Executive Summary
  • 3. Discovery at Spring Trails Development Plan
  • 4. Project Tasks and Schedule
  • 5. Project Costs
  • 6. Participants and Roles
  • 7. Project Management
  • 8. Detailed Task Descriptions
  • 9. Funding Plan

23
Project Management
  • CCET Management Team
  • Direct Funders and,
  • In-Kind Service Providers (including Land Tejas)
  • PI, Management and/or Integrating Contractor
    reporting to CCET COO

24
Project Plan Contents
  • 1. Purpose
  • 2. Executive Summary
  • 3. Discovery at Spring Trails Development Plan
  • 4. Project Tasks and Schedule
  • 5. Project Costs
  • 6. Participants and Roles
  • 7. Project Management
  • 8. Detailed Task Descriptions
  • 9. Funding Plan

25
Project PlanSection 8 Details
  • 1. Purpose
  • 2. Subtasks
  • 3. Schedules and
  • Milestones
  • 4. Equipment
  • 5. Labor
  • 6. Data flows
  • 7. Costs (materials, time)
  • 8. Data analysis, task integration
  • 9. Unresolved issues

26
Task 1Baseline Power Monitoring
  • Purpose
  • To measure voltages and power flows within
    the community and along the feeder serving the
    community to better understand impacts of
    distributed renewable generation.
  • Author CenterPoint
  • Status Rough draft was submitted this week

27
Task 2Comparative Energy Use Profiles
  • Purpose To provide quantifiable energy savings
    from Discovery at Spring Trails (DST) both as a
    community and individual homes vis-à-vis very
    similar adjacent masterplanned community without
    solar and ultra high efficiency measures.
  • Author CenterPoint
  • Status Rough draft received this week.

28
Task 3Decentralized EV/PHEV Charging
  • Purpose Determine demand patterns for
    garage-based electric vehicle charging systems
  • Author CenterPoint
  • Status No drafts received

29
Task4Centralized EV Charging
  • Purpose Design, construct, demonstrate and
    evaluate a community-based electric vehicle
    overnight charging station
  • Author CenterPoint
  • Status No drafts received

30
Task 5Decentralized Battery Storage
  • Purpose Evaluate cost effectiveness of
    individual residential battery storage units
  • Author GridPoint
  • Status Cost estimates received, no write up

31
Task 6Centralized Battery Storage
  • Purpose Determine how large scale community
    battery storage could be used with 250 kW solar
    array as a possible DSM resource and in future
    micro grid application.
  • Author Xtreme Power? Others?
  • Status Rough price estimate from Xtreme Power

32
(No Transcript)
33
Task 7Community Wide Enhanced DR Phase I
Critical Peak Pricing
  • Purpose Demonstrate and evaluate efficacy of a
    critical peak pricing-based DR program in a
    masterplanned green community designed
    cooperatively. To be designed by several REPs
    with one REP serving as load aggregator.
  • Author Bob Davis (need inputs from REPs)
  • Status Strawman only

34
Critical Peak Pricing Strawman
  • Ten to 20 times per year residents who opt into
    the program will be given one days notice of a
    CPP event
  • Rates during event may five times normal
  • 100 residences allowed to participate in exchange
    for cash awards
  • One cooling season (May through Sept 2010) Phase
    I
  • Could be combined with a summer time on-peak and
    off-peak time of use rates

35
Task 8Community Wide Enhanced DR Phase II Real
Time Pricing
  • Purpose Demonstrate use of real time pricing in
    a masterplanned green community
  • Author Bob Davis (need inputs from REPs)
  • Status Strawman only

36
Real Time Pricing
  • Access real time wholesale prices via ERCOT
  • Develop pricing program
  • Measure demand price responsiveness through a
    cooperatively developed offer to the aggregated
    load manager
  • One full year duration (2011)
  • Phase IIa in third year (2012)in which REPs
    develop proprietary real time pricing with
    limited data sharing among all participants

37
Task 9DR with Interruptible Load Appliances
  • Purpose Demonstrate use of load controllable
    appliances in HAN and Enhanced DR
  • Author GE (Patrick McElheny)
  • Status Write up underway

38
GE Load Controllable Devices
Signal from REP
Smart Electrical Communications Hub
39
Task 10Wind Integration/ Storage
  • PurposeEvaluate feasibility of storing wind
    generated power via PPA for storage on site in
    community battery storage.
  • Author None
  • Status No action

40
Task 11Interoperability Analyses
  • Purpose Assess features of communication within
    the home and outside the meter to determine needs
    for application of standards.
  • Author None
  • Status No action

41
Task 12University Research Agenda
  • Purpose Conduct targeted RD to deal with
    issues arising in the preceding tasks (e.g.,
    improving charging efficiencies in centralized
    station, evaluating DR programs, interoperability
    issues, etc)
  • Author None
  • Status No action

42
Task 13Data Integration and Analyses
  • Purpose Assure that methods and quality of data
    collected is uniform and sufficient to support
    the objectives of each task.
  • Author None
  • Status No action

43
Questions?
Write a Comment
User Comments (0)
About PowerShow.com