Description:

April 6, 2005. Dennis Moran, Director. Mid-Atlantic CHP Application Center. 2 ... PJM and other groups to form Mid-Atlantic Distributed Resources Initiative ... – PowerPoint PPT presentation

Number of Views:67
Avg rating:3.0/5.0
Slides: 14
Provided by: northe7
Category:

less

Transcript and Presenter's Notes

Title: Overview of PJM Interconnection Standards


1
Overview ofPJM Interconnection Standards MADRI
  • Presented to
  • Realizing the Benefits of a Regional CHP Market
  • April 6, 2005

Dennis Moran, Director Mid-Atlantic CHP
Application Center
2
Interconnection Background
  • IEEE 1547 Standard issued in June 2003
  • FERC issued NOPR for the Standardization of Small
    Generator Interconnection Agreements and
    Procedure on Aug 19, 2003
  • NARUC prepared a DG Interconnection Model for
    voluntary adoption by States
  • PJM states (NJ, MD, DC and PA) expressed
    interest in developing a regional approach to
    interconnection
  • DOE played key role in IEEE 1547 development and
    supports activities that will result in IEEE 1547
    being formally implemented

3
Mid-Atlantic Approach
  • PJM formed Small Generation Interconnection
    Working Group in early 2004
  • DOE worked with PJM and other groups to form
    Mid-Atlantic Distributed Resources Initiative
  • SGIWG developed uniform standard for
    interconnection
  • Identified all utility interconnection
    requirements that went beyond IEEE 1547
  • Worked with utilities to eliminate most of them
  • MADRI is focused on state implementation of rules
    and procedures that are favorable to DR programs
  • Addressing distributed generation, CHP and demand
    reduction

4
(No Transcript)
5
PJM SGIWG Status
  • Initially focused on standard for systems lt 2MW
  • Held 5 WG meetings and multiple subcommittee
    meetings to develop consensus standard
  • Under 2MW Technical Standard
  • Approved by PJM Reliability Committee
  • Approved by Members Committee
  • Tariff changes submitted to FERC in Jan 2005
  • Started work on 2 10 MW initiative on Feb 24
  • Will begin work on extending to Western PJM soon

6
SGIWG information is posted athttp//www.pjm.org
/committees/working-groups/sgiwg/sgiwg.html
7
MADRI
  • Primary Objective Develop and promote regional
    policies and market-enabling activities to
    support distributed generation and demand
    response in the Mid-Atlantic region.
  • Steering committee
  • Utility Commissioners from Mid-Atlantic States
  • DOE
  • US EPA
  • PJM Interconnect
  • NY PSC invited to join as associate member (in
    March)
  • Organizing meeting held June 13-14, 2004
  • Monthly initiative meetings began Sept 27
  • Rich Sedano of the Regulatory Assistance Project
    is serving as facilitator

8
MADRI info is posted athttp//www.energetics.com
/madri/
9
MADRI Sub-Working Groups
  • Interconnection Standards (Joe Kerecman, PJM)
  • Advanced Metering (Susan Covino, PJM)
  • Environmental (Tom Kerr, EPA)
  • Market Demonstration (Brad Johnson, ORNL)
  • Development of Tradable Commodity Markets for DR
    (PJM defining product)
  • Pricing Policies (discussion underway)
  • Regulatory Framework for Electric Distribution
    Companies (discussion underway)

10
(No Transcript)
11
(No Transcript)
12
(No Transcript)
13
THANK YOU FOR YOUR ATTENTION!
Dennis Moran 301-405-4681 dmoran_at_umd.edu
Write a Comment
User Comments (0)
About PowerShow.com