How to Construct a House - PowerPoint PPT Presentation

1 / 22
About This Presentation
Title:

How to Construct a House

Description:

At this point, the footings are to be formed so that the concrete can be poured. ... Actually, a basement is poured in three pieces: the footings, then the walls (or ... – PowerPoint PPT presentation

Number of Views:2338
Avg rating:5.0/5.0
Slides: 23
Provided by: wind226
Category:

less

Transcript and Presenter's Notes

Title: How to Construct a House


1
How to Construct a House
2
Introduction
  • When going through the process of designing a
    house, the knowledge of the how one is
    constructed is a vital tool. The steps to
    building a house are as follows
  • Site preparation
  • Foundation
  • Floors
  • Walls
  • Roof framing
  • Windows doors
  • Roof
  • Cladding (brick or siding)
  • Rough plumbing
  • Rough electrical
  • Insulation
  • Drywall
  • Garage slab
  • Finishing-up

3
Site Preparation
  • The first crew on the site handles site
    preparation. Often, this crew the foundation
    crew are the same people, but sometimes not
    (especially if there are a lot of trees on the
    lot). Houses are generally built on a foundation
    that is a basement. The site-preparation crew
    typically arrives on the site with a backhoe /or
    bulldozer. The crew's job is to clear the site of
    any trees, rocks debris, level the site if
    necessary dig as necessary for the foundation
    being built.

This track loader has a stump grinder attachment
that grinds tree stumps and roots into shreds,
while they are still in the ground.
4
foundation
  • After a site is prepared a hole about 8
    (2500mm) deep is dug for the foundation, the
    footings are started. At this point, the
    footings are to be formed so that the concrete
    can be poured.

In these pictures, you can see a crew pouring
concrete taking down forms for footings.
5
foundation
  • At the bottom of the hole is a concrete slab,
    and then concrete or cinder-block walls form the
    outer walls of the basement. Actually, a
    basement is poured in three pieces the footings,
    then the walls (or in concrete block form),
    then the concrete slab floor inside the walls,
    like this diagram

This approach helps keep the basement
waterproof. The L-shaped piece is a steel
reinforcing bar to bind the footing the wall
together. NOTE the concrete slab floor is
poured after the rough plumbing is complete. In
the picture on the right, you can see a completed
basement wall being covered with parging (tar) to
seal it from moisture.
6
Floors
  • The framing crew is the next group of people on
    the site to start building the floor. The floor
    begins with a sill-plate made of pressure-treated
    lumber bolted to the basement wall. Then the
    floor is constructed on the sill with 2x10(50 x
    254mm) lumber. These are called the floor
    joists. From here, sheets of plywood cover the
    floor joists making what is called the sub-floor.

The picture on the left shows a constructed
floor with its floor joists exposed. The picture
on the right is a completed floor including
sub-floor. Note This process is repeated after
the first floor walls are built if you have a
two-story house.
7
walls
  • The framing crew next starts on the walls. A
    wall is made of 2x6(50 x 152mm) studs of lumber
    covered on the outside with a plywood
    sheathing. The studs are placed apart 16(406mm)
    from the centre of each stud. Using plywood as
    the sheathing gives the wall rigidity.

As you can see from all the lumber on the floor,
walls are assembled on the ground then raised
into place.
8
walls
  • In this wall, one thing interrupts the
    consistent 16(406mm) pattern, a window. The
    plywood will be cut out of the window opening as
    construction proceeds. Above the window is a
    header, which is actually three 2x10(50 x
    254mm) pieces of lumber then there is a
    2x6(50 x 154mm) piece of lumber along the
    bottom.

You see these headers over all windows and
doors. They give the wall enough strength over
the window or door to support the floor above or
roof. Note This process is repeated for the
second story in a two-story house.
9
Roof framing
  • Trusses are pre-fabricated, triangulated wooden
    structures used to frame support the roof.
    Trusses are quite common these days because they
    have five big advantages from the builder's
    standpoint
  • Trusses are incredibly strong.
  • Because they are built strictly from shorter
    lengths of 2x6(50 x 154) lumber, they are
    generally a lot less expensive than the
    alternative.
  • You can have just about any shape custom-built,
    this allows interesting features like cathedral
    ceilings at low cost.
  • You can span a large distance with a truss the
    truss transmits all of the weight to the exterior
    walls decreases your number of load-bearing
    walls.
  • Trusses go up quickly!

10
Roof framing
  • The trusses are put into place by a crane tied
    to the walls with small metal plates. Once the
    trusses are up, the roof is covered in plywood,
    which gives the roof tremendous rigidity.

The picture on the left show a crane putting
trusses into place the picture on the right is
of a completed framed roof including the plywood
covering.
11
Windows doors
  • Inside the house, things are now beginning to
    look enclosed. The next step in enclosure is
    windows and doors. Today, the windows used are
    standard vinyl windows. The windows and doors
    arrive in one shipment and are unloaded from the
    truck into a stack as shown here

The middle picture shows the plastic stripping
stapled to the inside of all window and door
openings. They are placed in each rough opening
and stapled in place on the outside.
12
roof
  • This house uses standard asphalt shingles for
    the roof. The first step is to cover the roof
    with building paper (tar paper). The shingles
    then go on very quickly

In the lower right photograph, you can see the
aluminum flashing that keeps water away from the
walls at the points where the shingles touch the
walls.
13
cladding
  • The cladding on a house, being brick or siding,
    protects the structure from incurring any
    moisture which could be very damaging.

brick
Out of the different types of cladding, brick is
the most used desired material. Firstly,
L-shaped metal ties are nailed to the exterior
walls so that tabs are protruding out ready for
the bricks to laid. The bricks are laid with
mortar in between.
In the picture on the left, you can see a brick
layer starting the cladding on a house using
2x4(50 x 102mm) pieces of lumber to assist him
in keeping them inline.
14
siding
  • Siding is made from thin, flexible sheets of
    plastic or aluminum about 1/16(2mm) thick,
    pre-colored bent into shape during
    manufacturing. You start at the bottom the
    sheets interlock into each other as you go up.

In the picture on the left, you can see a close
up of siding being nailed to the exterior of the
wall. The picture on the right is showing a wall
completed with siding.
15
Rough plumbing
  • You may have wondered why you find these funny
    loops of pipe under every sink in your house.
    The idea is that water gets trapped in the "P."
    This water blocks the fumes from the septic tank
    or sewer keeps them from entering the bathroom.
    In addition, the fumes can simply bubble through
    the water in the trap cause the same problem.
    Therefore, there is the concept of a vent pipe,
    which allows the pressure to escape, as shown in
    the diagram

The middle photograph demonstrates plumbing
coming through the main floor into the
basement. The photograph on the right shows the
rough plumbing in the basement before the
concrete slab floor is poured over it.
16
Rough electrical
  • The purpose of the electrical system in a house
    is to distribute the power safely to all of the
    different rooms appliances. The electrician
    will first place all of the boxes for electrical
    outlets, lights switches. They will then run
    wires from the fuse box to each box. A lot of
    drilling is necessary, both down into the
    basement up into the ceiling, as well as
    through studs to run wires between boxes.

The pictures (from left to right) show the
progression of the rough electrical work ending
with an electrical box all wired-up.
17
insulation
  • Today, fiberglass insulation in typically used
    installed between the exterior wall studs. Over
    the insulation is a thin plastic vapor barrier.
    The idea behind the vapor barrier is to keep
    moisture that develops inside the house inside.
    Without the barrier, here is what happens inside
    the wall in winter Warm, moist air moves through
    the drywall into the insulated wall cavity at
    some point inside the cavity it becomes cold
    enough for the moisture to condense, soaking the
    insulation. The vapor barrier prevents this
    process.

The picture lets you see the insulation up in
the wall the ceiling before it is covered with
drywall.
18
drywall
  • On the outside, the house now looks complete
    but inside, it won't look "like a house" until
    the drywall goes up. Drywall is a ½(12mm)-thick
    layer of plaster or gypsum sandwiched between two
    thick sheets of paper. It is remarkably solid
    heavy. The Drywall nailed-up into place then
    reinforced with drywall screws. To "tape" the
    drywall means to cover all of the cracks
    nails/screws with drywall mud (spackling
    compound) so that the walls are completely smooth.

In the photograph on the left, you can see the
stacked ready to install. The photograph on
the right shows you what a wall looks like with
the drywall process completed before its
painted.
19
Garage slab floor
  • The floor of the garage is a 4(102mm)-thick
    concrete slab poured very late in the process.
    Another 4(102mm)s of gravel are placed on the
    ground covered with reinforcing wire first.
    Around the edges, ½(12mm) thick homosote will
    allow the slab to contract expand with
    temperature changes. Once the prep work is
    finished, a concrete truck will pour the concrete
    to create the slab.

The picture on the left shows a close-up of the
homosote which will allow for expansion
contraction. On the right, you can see the
preparation for the concrete.
20
Finishing-up
  • At this point, the steps that remain are all
    "finishing steps" are things you can see in
    your own home by opening doors removing cover
    plates. The finishing steps include
  • HVAC - The HVAC contractor will install the
    heating air conditioning unit (a.k.a. the
    furnace), the vents all duct work. Some of the
    HVAC in the walls or between floors would have
    had to be install before the drywall went up in a
    two-story design.
  • Finish electrical - The electrician will return
    install all light fixtures, wall outlets,
    switches cover plates.
  • Kitchen bathroom cabinets counters - The
    cabinet company will install kitchen bathroom
    cabinets. They are simply aligned on the wall
    screwed into the wall studs. Countertops are
    screwed on top of the cabinets.
  • Finish plumbing - Once the cabinets are in, the
    plumber will return install sinks, toilets
    faucets. The plumber will also install the water
    heater if it was not installed during rough
    plumbing.

21
Finishing-up
  • Installation of well septic system or hook-up
    to city water sewer - Depending on where the
    house is located, it will either have a private
    well septic system or it will hook up to
    municipal water sewer lines. If a private well
    septic tank are needed, the contractor will
    bring in a well-drilling subcontractor a
    septic-tank subcontractor. Otherwise, the
    contractor will call someone (either the
    municipality or a subcontractor) to extend the
    municipal lines to the house. The plumber will
    hook up the water sewer lines.
  • Wall trim - Once the cabinets are in, the
    interior doors are installed the molding around
    the doors, windows baseboards goes in.
  • Paint - Once the molding is on, it is time to
    paint wallpaper the interior of the house.
  • Carpeting tile - Once the paint is done, carpet
    tile goes down.
  • Deficiency list - At this point, the builder
    inspects the house, noting any problems. All
    problems are noted on a deficiency list. The
    different contractors return to fix all of the
    problems.

22
The house is complete!
  • Now that you understand how a house is built,
    keep in mind this process when designing let it
    guide you to a better house.
Write a Comment
User Comments (0)
About PowerShow.com