NMMS Nodal Network Mgmt and Monitoring System Update PowerPoint PPT Presentation

presentation player overlay
1 / 5
About This Presentation
Transcript and Presenter's Notes

Title: NMMS Nodal Network Mgmt and Monitoring System Update


1
NMMSNodal Network Mgmt and Monitoring System
Update
  • TPTF Meeting
  • August 2007
  • Raj Chudgar

2
NMMS Document Update
  • Updating documents for Baseline 2 as needed
  • Detailed design is in progress and should be
    complete by Sept 2007
  • Use cases and test cases have been developed and
    are being modified
  • Most Test scripts are developed
  • Installation procedures in progress (issues with
    installation script documented back to Siemens)

3
CIM Update
  • ERCOT Net CIM ready for any MP to transfer
  • File has been sent to ERCOT vendors that require
    importer development
  • ERCOT CIM will continue to be updated as AREVA
    data is converted to CIM format
  • ERRCOT CIM development scheduled to be completed
    in 1Q2008
  • Legal has developed a generic NDA for MPs that
    are interested in obtaining the file (35 mbs
    zipped)
  • Contact ERCOT wholesale client service rep for
    more information
  • CIM user conference being held at ERCOT in
    October 2007. If your company is interested in
    attending please send an email to ERCOT
  • ERCOT has noticed that many QSEs have no
    experience with CIM. If QSE is planning to work
    with vendors for CIM importer ERCOT can assist

4
NMMS Solution Update
  • Development
  • Phase 1a completed and deployed in June 2007
  • Phase 1b FAT completed in August 2007
  • A couple critical defects found. Siemens
    scheduled conference call with ERCOT to address
    defects this week
  • Phase 1b will only be completed after all
    critical defects are solved
  • Phase 1c FAT scheduled in September 2007
  • Data Management and reconciliation
  • Settlement Price point rules drafted and list to
    be developed for end of August TPTF review
  • List of Electrical Bus names being developed with
    TSPs presently. Scheduling to complete by end of
    September
  • Data loading into NMMS in October/November 2007

5
NMMS Planning
  • Lots of work is planned for next 6 months
  • NMMS Development completion
  • NMMS Training for QSE complete (4Q2007) by
    training group
  • NMMS addl training for TSPs 4Q2007 by 4Q2007
  • NMMS data mgmt and reconciliation complete by
    3Q2007
  • NMMS Market testing and trials starting in 4Q2007
  • NMMS testing with EMS/MMS starting in 4Q2007
  • ERCOT has brought in temp staff to handle current
    ERCOT workload so that most of ERCOT network
    modeling staff can work on NMMS (as planned)
  • TSPs and QSEs that are planning to use CIM data
    should be working on comparable solutions at this
    point as well