Title: Sustainable Procurement Project
1Sustainable Procurement Project
- Jimmy Brannigan Dr Neil Smith
- ESD Consulting Ltd University of Southampton
2Sustainable Procurement Project
- Structure
- Brief background on the project
- Hear from the University of Southampton on how
they took the project forward - Summary of the key findings and progress
3Sustainable Procurement Project
- What is the challenge?
- Public commitment to sustainability and
sustainable procurement - Some staff engaged and enthused
- Lots of guidance
- Growing understanding of the need to be doing
something!
4Sustainable Procurement Project
- What is the challenge?
- Still a gap between the policy and practice
- Lots of guidance but not always helpful
- Sustainable procurement perceived to be too
difficult - People dont always know where to start
5Sustainable Procurement Project
- Background
- Three year project
- Reducing negative environmental and social
impacts through purchasing - Steering group, partners from Further Education
and Higher Education - Worked with 16 colleges and universities
- Action learning, networks and dialogue and hands
on support
6Sustainable Procurement Project
- Year One
- Establishing baselines, gaining an understanding
of the different challenges from colleges and
universities, work up action plans for each
institution - Year Two
- Running training, developing the tools and
skills amongst the partners, action plan review,
production of guidance documents - Year Three
- Hands on Support work with the institutions to
train staff, implement action plans, communicate
to the institution
7Sustainable procurement at University of
Southampton
Dr Neil Smith 1st April 2008
8Aims
- Background
- Project approach
- What went well not so well
- What have we achieved
- Recommendations
9Background
We use more than 1 million sheets of A4/A3
copier/printer paper every week
- 5,000 staff 20,000 students
- 110M non-manpower spend in 2005/6
- Devolved budgets
- lt20k no Procurement involvement
- No sustainable procurement policy
10Project approach
- Sponsors
- Malcolm Ace, Director of Finance
- Kevin Monaghan, Director of Estates
- Project team
- Justin Candy, Head of Procurement (Executive)
- Neil Smith, Environment Manager (Manager)
- John Gordon, Senior Procurement Officer
- Jon Beale, Business Community Services Manager
- Inez Scudder, ISS Manager
- Candy Snelling, SU Environment Ethics Officer
- Prof Richard Lamming, Head of School of
Management - Dr Ian Williams, School of Civil Engineering
Environment
11Project approach
- Change in behaviour and attitudes of staff,
students and suppliers - Commitment senior managers
- Support guidance staff, students suppliers
- Supplier selection PQQ tender evaluation
- Measure KPIs, Supplier audit
- Work with others SUPC, HEIs, Las etc
- Communication Inform to raise awareness
12What went well
- Senior management commitment
- EAUC workshops
- Specific items
- Paper
- Food (HELO)
- Communication
13What didnt go so well
- Change to internal processes
- Mis-match between supplier claims practice
- Market place not ready to respond
14What have we achieved?
- Opportunity to introduce sustainable procurement
into University - Achieved Level 1 of flexible framework by April
2007 - More to do
15Recommendations
- Get senior management support
- Cross-functional team approach
- Use EAUC support
- Concentrate on specific items/products
- Look at internal processes
- Good luck!
16Sustainable Procurement Project
- Summary of progress
- Procuring the Future
- Partner progress
- Key learning from the project
17Procuring the Future
18The Flexible Framework
19Sustainable Procurement Project
- People trained / capacity built
- Level 1 achieved
- At the start of the project 8
- At the end of the project 92
20Sustainable Procurement Project
- Policy, strategy and communications
- Level 1 achieved
- At the start of the project 25
- At the end of the project 100
21Sustainable Procurement Project
- Procurement process
- Level 1 achieved
- At the start of the project 8
- At the end of the project 92
22Sustainable Procurement Project
- Supplier engagement
- Level 1 achieved
- At the start of the project 8
- At the end of the project 92
23Sustainable Procurement Project
- Measurement and results
- Level 1 achieved
- At the start of the project 8
- At the end of the project 100
24Sustainable Procurement Project
- Level 3 or above by April 2009
- People 67
- Policy / strategy 67
- Procurement process 67
- Supplier engagement 41
- Measurement results 41
25Sustainable Procurement Project
- Key learning from the project
- Its a journey
- Its ok not to have all the answers
- Its about building confidence
- Its about creating a space for people to
explore, innovate and learn - What next?
26Sustainable Procurement Project
- Jimmy Brannigan
- ESD Consulting Ltd
- jbrannigan_at_esdconsulting.co.uk