Sustainable Procurement Project - PowerPoint PPT Presentation

About This Presentation
Title:

Sustainable Procurement Project

Description:

Hear from the University of Southampton on how they took the project forward ... Inez Scudder, ISS Manager. Candy Snelling, SU Environment & Ethics Officer ... – PowerPoint PPT presentation

Number of Views:202
Avg rating:3.0/5.0
Slides: 27
Provided by: Christo145
Category:

less

Transcript and Presenter's Notes

Title: Sustainable Procurement Project


1
Sustainable Procurement Project
  • Jimmy Brannigan Dr Neil Smith
  • ESD Consulting Ltd University of Southampton

2
Sustainable Procurement Project
  • Structure
  • Brief background on the project
  • Hear from the University of Southampton on how
    they took the project forward
  • Summary of the key findings and progress

3
Sustainable Procurement Project
  • What is the challenge?
  • Public commitment to sustainability and
    sustainable procurement
  • Some staff engaged and enthused
  • Lots of guidance
  • Growing understanding of the need to be doing
    something!

4
Sustainable Procurement Project
  • What is the challenge?
  • Still a gap between the policy and practice
  • Lots of guidance but not always helpful
  • Sustainable procurement perceived to be too
    difficult
  • People dont always know where to start

5
Sustainable Procurement Project
  • Background
  • Three year project
  • Reducing negative environmental and social
    impacts through purchasing
  • Steering group, partners from Further Education
    and Higher Education
  • Worked with 16 colleges and universities
  • Action learning, networks and dialogue and hands
    on support

6
Sustainable Procurement Project
  • Year One
  • Establishing baselines, gaining an understanding
    of the different challenges from colleges and
    universities, work up action plans for each
    institution
  • Year Two
  • Running training, developing the tools and
    skills amongst the partners, action plan review,
    production of guidance documents
  • Year Three
  • Hands on Support work with the institutions to
    train staff, implement action plans, communicate
    to the institution

7
Sustainable procurement at University of
Southampton
Dr Neil Smith 1st April 2008
8
Aims
  • Background
  • Project approach
  • What went well not so well
  • What have we achieved
  • Recommendations

9
Background
We use more than 1 million sheets of A4/A3
copier/printer paper every week
  • 5,000 staff 20,000 students
  • 110M non-manpower spend in 2005/6
  • Devolved budgets
  • lt20k no Procurement involvement
  • No sustainable procurement policy

10
Project approach
  • Sponsors
  • Malcolm Ace, Director of Finance
  • Kevin Monaghan, Director of Estates
  • Project team
  • Justin Candy, Head of Procurement (Executive)
  • Neil Smith, Environment Manager (Manager)
  • John Gordon, Senior Procurement Officer
  • Jon Beale, Business Community Services Manager
  • Inez Scudder, ISS Manager
  • Candy Snelling, SU Environment Ethics Officer
  • Prof Richard Lamming, Head of School of
    Management
  • Dr Ian Williams, School of Civil Engineering
    Environment

11
Project approach
  • Change in behaviour and attitudes of staff,
    students and suppliers
  • Commitment senior managers
  • Support guidance staff, students suppliers
  • Supplier selection PQQ tender evaluation
  • Measure KPIs, Supplier audit
  • Work with others SUPC, HEIs, Las etc
  • Communication Inform to raise awareness

12
What went well
  • Senior management commitment
  • EAUC workshops
  • Specific items
  • Paper
  • Food (HELO)
  • Communication

13
What didnt go so well
  • Change to internal processes
  • Mis-match between supplier claims practice
  • Market place not ready to respond

14
What have we achieved?
  • Opportunity to introduce sustainable procurement
    into University
  • Achieved Level 1 of flexible framework by April
    2007
  • More to do

15
Recommendations
  • Get senior management support
  • Cross-functional team approach
  • Use EAUC support
  • Concentrate on specific items/products
  • Look at internal processes
  • Good luck!

16
Sustainable Procurement Project
  • Summary of progress
  • Procuring the Future
  • Partner progress
  • Key learning from the project

17
Procuring the Future
18
The Flexible Framework
19
Sustainable Procurement Project
  • People trained / capacity built
  • Level 1 achieved
  • At the start of the project 8
  • At the end of the project 92

20
Sustainable Procurement Project
  • Policy, strategy and communications
  • Level 1 achieved
  • At the start of the project 25
  • At the end of the project 100

21
Sustainable Procurement Project
  • Procurement process
  • Level 1 achieved
  • At the start of the project 8
  • At the end of the project 92

22
Sustainable Procurement Project
  • Supplier engagement
  • Level 1 achieved
  • At the start of the project 8
  • At the end of the project 92

23
Sustainable Procurement Project
  • Measurement and results
  • Level 1 achieved
  • At the start of the project 8
  • At the end of the project 100

24
Sustainable Procurement Project
  • Level 3 or above by April 2009
  • People 67
  • Policy / strategy 67
  • Procurement process 67
  • Supplier engagement 41
  • Measurement results 41

25
Sustainable Procurement Project
  • Key learning from the project
  • Its a journey
  • Its ok not to have all the answers
  • Its about building confidence
  • Its about creating a space for people to
    explore, innovate and learn
  • What next?

26
Sustainable Procurement Project
  • Jimmy Brannigan
  • ESD Consulting Ltd
  • jbrannigan_at_esdconsulting.co.uk
Write a Comment
User Comments (0)
About PowerShow.com