Title: The Complete PMO


1
The Complete PMO
  • Chapter 16 - Project Recovery

2
Please Note that the following Slide text is
derived from the content in The Complete Project
Management Handbook by Gerald Hill
3
Project Recovery
  • Project recovery implies the existence of
    variations in project performance significant
    enough to warrant that the PMO and senior
    management examine processes and practices
    contributing to problems encountered by project
    managers.

4
PMO Project Recovery Responsibility
  • The PMO develops/influences project recovery
    actions within the PM environment.
  • Distinguish between routine project corrective
    actions and defined project recovery efforts.
  • Specify composition/attributes of project
    recovery teams.
  • Prescribe criteria/process for implementing
    project recovery efforts.
  • Build a library of project corrective actions for
    use by project managers.

5
Project Recovery Activities Across the PMO
Continuum
6
Project Recovery Activities across the PMO
Continuum
  • The PMO serves as the focal point for identifying
    problems and prescribing/implementing remedies to
    correct troubled projects.
  • Project Office Uses established criteria to
    identify project problems/issues/difficulties and
    applies standard remedies to performance
    variations until the PMO or senior management
    elevates the problems to a higher-level review.
  • Mid-range PMO Establishes a fundamental to
    advanced capability for defining what constitutes
    a troubled project and specifying criteria to
    deal with them i.e. form qualified project
    recovery teams, processes to assess/rectify
    encountered problems, evaluating project recovery
    intervention effectiveness, and tools to manage
    project recovery efforts.
  • Center of Excellence Analyzes the use and
    effectiveness of project recovery processes to
    develop better indicators for troubled projects
    and better solutions encountered problems within
    the relevant organization.

7
Project Recovery Function Model
8
Develop Recovery Assessment Process
9
Identify Recovery Indicators
  • The PMOs awareness of the relevant
    organization's culture, nature of projects, and
    business interests helps it establish an
    effective project recovery approach that includes
    evaluating/prescribing indicators to use in
    defining troubled projects in the relevant
    organization.
  • Scope Indicators.
  • Alignment of project plans with official scope
    changes.
  • Variation in stakeholder versions of the scope
    statement.
  • Frequency and cause of project scope changes.
  • Cost Indicators.
  • Variation in planned versus actual cost.
  • Reliability of cost estimates.
  • Schedule Indicators.
  • Variation in planned versus actual schedule.

10
Assess Project and Identify Problem Areas
  • The PMO collaborates with the project recovery
    team to examine project performance to assess
    project recovery.
  • Assess Application of the Current PM Methodology.
  • Timely and accurate achievement of key PM
    planning deliverables.
  • Project definition (requirements, scope,
    objectives, deliverables, etc.).
  • Project charter (project management authority,
    funding, etc.)
  • Project work breakdown structure (WBS) and work
    plan (cost, schedule, and resource utilization).
  • Resource responsibility matrix (requirements,
    competency level, tasks, etc.).
  • Adjunct project plans (risk, quality,
    communication, etc.).
  • Timely and accurate achievement of key PM
    execution deliverables.
  • Project team formation and management activities.

11
Assess Project and Identify Problem Areas -
Continued
  • Assess the Current Project Management Support
    Structure.
  • Executive and senior management participation and
    support.
  • Business unit involvement and support activities.
  • PMO involvement and support activities.
  • Accomplishment of required training for project
    team members.
  • Availability, assignment, and use of project
    management and technical tools.
  • Availability, assignment, and use of technical
    equipment and new technology.
  • Functional alignment of project team (resource
    manager implications).
  • Assess the Current Business Interests and Issues.
  • Project priority (e.g., business importance,
    internal visibility, customer retention).

12
Assess Project and Identify Problem Areas -
Continued
  • Assess the Current Project Work Plan.
  • Project scope and WBS.
  • Initial validation of project scope with the
    customer.
  • Formal documentation and collaboration of project
    scope changes.
  • Frequency of project scope changes.
  • Occurrence of scope creep outside of a formal
    change-management process.
  • Identification of internal and external events
    affecting scope change.
  • Customer decisions, indecision, and unilateral
    changes in requirements.
  • Incidental influence (expansion or reduction) of
    project team on work efforts.
  • Scope representation in the WBS (e.g., work-flow
    gaps, critical activities, etc.).

13
Assess Project and Identify Problem Areas -
Continued
  • Assess the Current Project Team and Key
    Stakeholders.
  • Project manager.
  • Workload.
  • Competence and experience relative to project
    size, type, value, etc.
  • Technical skill and capability to provide
    technical oversight.
  • Authority and control (e.g., excessive or
    insufficient).
  • Response to business guidance.
  • Personality and professional behavior
    constraints.
  • Project team.
  • Workload.

14
Prepare Recovery Decision Package
  • The PMO constructs a standard document and
    approach to the project recovery decision.
  • Project recovery assessment activities.
  • Assessment team composition.
  • Identification of areas of project performance
    examined.
  • Overview (statement) of assessment findings.
  • Statement of project condition.
  • Project performance problems and their root
    causes.
  • Impacts of project performance problems (i.e.,
    business, industry, customer, etc.).
  • Project performance improvement actions needed to
    achieve project success.
  • Project recovery recommendation.

15
Coordinate Project Recovery Decision
  • The PMO collaborates with key person in the
    business environment to coordinate project
    recovery decisions within the PM environment.
  • Project manager and project sponsor.
  • Project team members.
  • Vendor and contractor engagement managers.
  • Customer engagement manager.
  • Business unit representative.
  • Resource managers.
  • Other project managers.

16
Plan and Conduct Project Recovery
17
Establish Project Recovery Team
  • The PMO defines project recovery team
    roles/responsibilities as the basis for convening
    a project recovery team.
  • Senior Management.
  • Fund the project recovery effort.
  • Allocate new/additional resources required for
    the project recovery effort.
  • Adjust project portfolio priorities and decisions
    to accommodate project recovery.
  • Evaluate impacts on other projects resulting from
    project recovery needs.
  • Reassign key project professionals.
  • Review strategic business interests affected by
    project recovery actions.
  • Participate in project recovery status reviews
    and updates.
  • Facilitate PMO development/implementation of
    process guidance in the PM environment to avoid
    recurring project recovery needs.

18
Establish Project Recovery Team - Continued
  • Project Recovery Manager Serves as the new
    project manager during the project recovery
    period and possibly the remaining duration of the
    project.
  • Gain early awareness of the project condition
  • Review project recovery decision package.
  • Review viable project planning documents.
  • Review viable project tracking documents and
    reports.
  • Manage project recovery team formation.
  • Inform current project team members of approach
    to project recovery.
  • Select new project recovery facilitators and core
    managers.
  • Introduce/integrate current/new project team
    members.
  • Establish guidance and responsibilities for
    operating in project recovery mode.

19
Establish Project Recovery Team - Continued
  • Project Team Members Combines original project
    team members with selected team members who
    facilitate project recovery efforts.
  • Recognize the effort as one of project recovery
    and business importance.
  • Advise the project recovery manager in areas of
    professional and technical expertise.
  • Conduct/communicate risk management activities in
    areas of responsibility.
  • Provide frequent and timely project status
    reports.
  • Perform assigned project tasks in a timely
    manner.
  • Collaborate with the project recovery manager on
    issues/problems.
  • Vendors and Contractors.
  • Customers.
  • Review/concur with the recovery plan.

20
Develop Project Recovery Plan
  • The PMO facilitates creating a project recovery
    plan that demonstrates the commitment of the
    relevant organization to recovering the project.
  • Revised project work plan.
  • Work breakdown structure Incorporates tasks and
    actions to rectify adverse findings and implement
    prescribed solutions.
  • Cost Re-estimated project cost figures.
  • Schedule Re-estimated project timelines.
  • Resource utilization Re-estimated project
    resource utilization requirements.
  • Updated project risk management plan.
  • Preparation of a new plan to address the elements
    of the revised project work plan.
  • Specifies general risk management
    responsibilities of all project team members and
    specific responsibilities of team members
    assigned to the project recovery team.
  • Identifies increased frequency for conducting
    project risk reviews and reporting of results to
    the project recovery manager.

21
Develop Project Recovery Plan - Continued
  • Revised project communication plan.
  • Enhances close collaboration of plans/progress
    among project team members and other
    stakeholders.
  • Outlines the roles/responsibilities of the
    project recovery manager and new participants on
    the project recovery team.
  • Presents revised requirements for reporting
    project status to senior management.
  • Highlights adjusted thresholds for reporting
    cost, schedule, and resource utilization
    variations and elevating issues/problems
    encountered.
  • Reiterates the required change-control process
    and provides guidance for coordinating/distributin
    g revised project plans, technical documents, and
    other documents.
  • Possible additional project recovery guidance
    plan.
  • Customer relationship management plan.
  • Internal incident (rumor) control plan.
  • Public information and media management plan.

22
Stabilize Project Using Recovery Solution
  • The PMO monitors the performance of the project
    recovery work plan to enable the project recovery
    team to implement the revised/refined project
    solution to reestablish control and stabilize the
    project.
  • Recovery solution implementation.
  • Stakeholder communication management.
  • Project tracking and controlling.
  • Cost tracking and controlling.
  • Schedule tracking and controlling.
  • Resource utilization tracking and controlling.
  • Change management Changes to project scope,
    plans, specifications, and customer
    contracts/agreements are closely monitored and
    strictly controlled.
  • Request Specify details of a needed change in a
    project-change request.
  • Analyze Needs/benefits/impacts of the change
    request.

23
Conclude Project Recovery
  • The PMO develops a process that specifies
    indicators to determine when project recovery
    concludes and the project transitions back to
    normal operations i.e. a stabilized project with
    PM indicators under control.
  • Compile recovery project data.
  • Prepare project analysis and recommendation
    report.
  • Specify transition activities.
  • Specify review/coordination/approval activities.
  • Design project manager (project recovery manager,
    new project manager, or original project
    manager).
  • Disperse project recovery team (.
  • Re-designate project team roles/responsibilities.
  • Designate approach to project recovery document
    and material collection.
  • Specify planned internal information
    announcements.

24
Capture Recovery Lessons Learned
25
Examine PM Indicators
  • The PMO facilitates information
    collection/analysis for lessons learned from
    project recovery by examining the project
    recovery assessment reports to establish an
    approach to monitor PM indicators during the
    recovery effort.
  • Validate current PM project performance
    indicators and criteria.
  • Recommend current PM project performance
    indicators and criteria need to be modified.

26
Examine Project Selection Criteria
  • The PMO examines the project selection process to
    determine if indicators and criteria precluded
    selecting the troubled project i.e. insufficient
    business case for project selection or negative
    impacts of associated resource allocation.

27
Examine Project Recovery Process
  • The PMO reviews the current project recovery
    process relative to the completed recovery effort
    to determine the effectiveness of the process and
    if it contributed to PM difficulties during the
    project recovery effort.
  • Project recovery process utilization Project
    recovery team member access/use of project
    recovery methods.
  • Process availability.
  • Process familiarity.
  • Process applicability.
  • Project recovery process effectiveness.
  • Project recovery participants roles.
  • Description of procedures and activities for
    project recovery.
  • Management tools and templates for project
    recovery.
  • Project recovery support Adequacy of guidance
    to obtain technical/business support during
    project recovery.

28
Update Routine Project Recovery Remedies
  • The PMO uses lessons learned during project
    recovery to initiate corrective actions to apply
    to project recovery and routine PM efforts.