Title: The Complete PMO
1The Complete PMO
- Chapter 16 - Project Recovery
2Please Note that the following Slide text is
derived from the content in The Complete Project
Management Handbook by Gerald Hill
3Project Recovery
- Project recovery implies the existence of
variations in project performance significant
enough to warrant that the PMO and senior
management examine processes and practices
contributing to problems encountered by project
managers.
4PMO Project Recovery Responsibility
- The PMO develops/influences project recovery
actions within the PM environment. - Distinguish between routine project corrective
actions and defined project recovery efforts. - Specify composition/attributes of project
recovery teams. - Prescribe criteria/process for implementing
project recovery efforts. - Build a library of project corrective actions for
use by project managers.
5Project Recovery Activities Across the PMO
Continuum
6Project Recovery Activities across the PMO
Continuum
- The PMO serves as the focal point for identifying
problems and prescribing/implementing remedies to
correct troubled projects. - Project Office Uses established criteria to
identify project problems/issues/difficulties and
applies standard remedies to performance
variations until the PMO or senior management
elevates the problems to a higher-level review. - Mid-range PMO Establishes a fundamental to
advanced capability for defining what constitutes
a troubled project and specifying criteria to
deal with them i.e. form qualified project
recovery teams, processes to assess/rectify
encountered problems, evaluating project recovery
intervention effectiveness, and tools to manage
project recovery efforts. - Center of Excellence Analyzes the use and
effectiveness of project recovery processes to
develop better indicators for troubled projects
and better solutions encountered problems within
the relevant organization.
7Project Recovery Function Model
8Develop Recovery Assessment Process
9Identify Recovery Indicators
- The PMOs awareness of the relevant
organization's culture, nature of projects, and
business interests helps it establish an
effective project recovery approach that includes
evaluating/prescribing indicators to use in
defining troubled projects in the relevant
organization. - Scope Indicators.
- Alignment of project plans with official scope
changes. - Variation in stakeholder versions of the scope
statement. - Frequency and cause of project scope changes.
- Cost Indicators.
- Variation in planned versus actual cost.
- Reliability of cost estimates.
- Schedule Indicators.
- Variation in planned versus actual schedule.
10Assess Project and Identify Problem Areas
- The PMO collaborates with the project recovery
team to examine project performance to assess
project recovery. - Assess Application of the Current PM Methodology.
- Timely and accurate achievement of key PM
planning deliverables. - Project definition (requirements, scope,
objectives, deliverables, etc.). - Project charter (project management authority,
funding, etc.) - Project work breakdown structure (WBS) and work
plan (cost, schedule, and resource utilization). - Resource responsibility matrix (requirements,
competency level, tasks, etc.). - Adjunct project plans (risk, quality,
communication, etc.). - Timely and accurate achievement of key PM
execution deliverables. - Project team formation and management activities.
11Assess Project and Identify Problem Areas -
Continued
- Assess the Current Project Management Support
Structure. - Executive and senior management participation and
support. - Business unit involvement and support activities.
- PMO involvement and support activities.
- Accomplishment of required training for project
team members. - Availability, assignment, and use of project
management and technical tools. - Availability, assignment, and use of technical
equipment and new technology. - Functional alignment of project team (resource
manager implications). - Assess the Current Business Interests and Issues.
- Project priority (e.g., business importance,
internal visibility, customer retention).
12Assess Project and Identify Problem Areas -
Continued
- Assess the Current Project Work Plan.
- Project scope and WBS.
- Initial validation of project scope with the
customer. - Formal documentation and collaboration of project
scope changes. - Frequency of project scope changes.
- Occurrence of scope creep outside of a formal
change-management process. - Identification of internal and external events
affecting scope change. - Customer decisions, indecision, and unilateral
changes in requirements. - Incidental influence (expansion or reduction) of
project team on work efforts. - Scope representation in the WBS (e.g., work-flow
gaps, critical activities, etc.).
13Assess Project and Identify Problem Areas -
Continued
- Assess the Current Project Team and Key
Stakeholders. - Project manager.
- Workload.
- Competence and experience relative to project
size, type, value, etc. - Technical skill and capability to provide
technical oversight. - Authority and control (e.g., excessive or
insufficient). - Response to business guidance.
- Personality and professional behavior
constraints. - Project team.
- Workload.
14Prepare Recovery Decision Package
- The PMO constructs a standard document and
approach to the project recovery decision. - Project recovery assessment activities.
- Assessment team composition.
- Identification of areas of project performance
examined. - Overview (statement) of assessment findings.
- Statement of project condition.
- Project performance problems and their root
causes. - Impacts of project performance problems (i.e.,
business, industry, customer, etc.). - Project performance improvement actions needed to
achieve project success. - Project recovery recommendation.
15Coordinate Project Recovery Decision
- The PMO collaborates with key person in the
business environment to coordinate project
recovery decisions within the PM environment. - Project manager and project sponsor.
- Project team members.
- Vendor and contractor engagement managers.
- Customer engagement manager.
- Business unit representative.
- Resource managers.
- Other project managers.
16Plan and Conduct Project Recovery
17Establish Project Recovery Team
- The PMO defines project recovery team
roles/responsibilities as the basis for convening
a project recovery team. - Senior Management.
- Fund the project recovery effort.
- Allocate new/additional resources required for
the project recovery effort. - Adjust project portfolio priorities and decisions
to accommodate project recovery. - Evaluate impacts on other projects resulting from
project recovery needs. - Reassign key project professionals.
- Review strategic business interests affected by
project recovery actions. - Participate in project recovery status reviews
and updates. - Facilitate PMO development/implementation of
process guidance in the PM environment to avoid
recurring project recovery needs.
18Establish Project Recovery Team - Continued
- Project Recovery Manager Serves as the new
project manager during the project recovery
period and possibly the remaining duration of the
project. - Gain early awareness of the project condition
- Review project recovery decision package.
- Review viable project planning documents.
- Review viable project tracking documents and
reports. - Manage project recovery team formation.
- Inform current project team members of approach
to project recovery. - Select new project recovery facilitators and core
managers. - Introduce/integrate current/new project team
members. - Establish guidance and responsibilities for
operating in project recovery mode.
19Establish Project Recovery Team - Continued
- Project Team Members Combines original project
team members with selected team members who
facilitate project recovery efforts. - Recognize the effort as one of project recovery
and business importance. - Advise the project recovery manager in areas of
professional and technical expertise. - Conduct/communicate risk management activities in
areas of responsibility. - Provide frequent and timely project status
reports. - Perform assigned project tasks in a timely
manner. - Collaborate with the project recovery manager on
issues/problems. - Vendors and Contractors.
- Customers.
- Review/concur with the recovery plan.
20Develop Project Recovery Plan
- The PMO facilitates creating a project recovery
plan that demonstrates the commitment of the
relevant organization to recovering the project. - Revised project work plan.
- Work breakdown structure Incorporates tasks and
actions to rectify adverse findings and implement
prescribed solutions. - Cost Re-estimated project cost figures.
- Schedule Re-estimated project timelines.
- Resource utilization Re-estimated project
resource utilization requirements. - Updated project risk management plan.
- Preparation of a new plan to address the elements
of the revised project work plan. - Specifies general risk management
responsibilities of all project team members and
specific responsibilities of team members
assigned to the project recovery team. - Identifies increased frequency for conducting
project risk reviews and reporting of results to
the project recovery manager.
21Develop Project Recovery Plan - Continued
- Revised project communication plan.
- Enhances close collaboration of plans/progress
among project team members and other
stakeholders. - Outlines the roles/responsibilities of the
project recovery manager and new participants on
the project recovery team. - Presents revised requirements for reporting
project status to senior management. - Highlights adjusted thresholds for reporting
cost, schedule, and resource utilization
variations and elevating issues/problems
encountered. - Reiterates the required change-control process
and provides guidance for coordinating/distributin
g revised project plans, technical documents, and
other documents. - Possible additional project recovery guidance
plan. - Customer relationship management plan.
- Internal incident (rumor) control plan.
- Public information and media management plan.
22Stabilize Project Using Recovery Solution
- The PMO monitors the performance of the project
recovery work plan to enable the project recovery
team to implement the revised/refined project
solution to reestablish control and stabilize the
project. - Recovery solution implementation.
- Stakeholder communication management.
- Project tracking and controlling.
- Cost tracking and controlling.
- Schedule tracking and controlling.
- Resource utilization tracking and controlling.
- Change management Changes to project scope,
plans, specifications, and customer
contracts/agreements are closely monitored and
strictly controlled. - Request Specify details of a needed change in a
project-change request. - Analyze Needs/benefits/impacts of the change
request.
23Conclude Project Recovery
- The PMO develops a process that specifies
indicators to determine when project recovery
concludes and the project transitions back to
normal operations i.e. a stabilized project with
PM indicators under control. - Compile recovery project data.
- Prepare project analysis and recommendation
report. - Specify transition activities.
- Specify review/coordination/approval activities.
- Design project manager (project recovery manager,
new project manager, or original project
manager). - Disperse project recovery team (.
- Re-designate project team roles/responsibilities.
- Designate approach to project recovery document
and material collection. - Specify planned internal information
announcements.
24Capture Recovery Lessons Learned
25Examine PM Indicators
- The PMO facilitates information
collection/analysis for lessons learned from
project recovery by examining the project
recovery assessment reports to establish an
approach to monitor PM indicators during the
recovery effort. - Validate current PM project performance
indicators and criteria. - Recommend current PM project performance
indicators and criteria need to be modified.
26Examine Project Selection Criteria
- The PMO examines the project selection process to
determine if indicators and criteria precluded
selecting the troubled project i.e. insufficient
business case for project selection or negative
impacts of associated resource allocation.
27Examine Project Recovery Process
- The PMO reviews the current project recovery
process relative to the completed recovery effort
to determine the effectiveness of the process and
if it contributed to PM difficulties during the
project recovery effort. - Project recovery process utilization Project
recovery team member access/use of project
recovery methods. - Process availability.
- Process familiarity.
- Process applicability.
- Project recovery process effectiveness.
- Project recovery participants roles.
- Description of procedures and activities for
project recovery. - Management tools and templates for project
recovery. - Project recovery support Adequacy of guidance
to obtain technical/business support during
project recovery.
28Update Routine Project Recovery Remedies
- The PMO uses lessons learned during project
recovery to initiate corrective actions to apply
to project recovery and routine PM efforts.