EO1 MISSION READINESS REVIEW - PowerPoint PPT Presentation

1 / 16
About This Presentation
Title:

EO1 MISSION READINESS REVIEW

Description:

ALI and Hyperion are Primary Instruments/Technologies ... Pointing Accuracy 0.022o, Jitter 5 arcsec, 20 arcsec instrument alignment ... – PowerPoint PPT presentation

Number of Views:51
Avg rating:3.0/5.0
Slides: 17
Provided by: josefaw
Category:

less

Transcript and Presenter's Notes

Title: EO1 MISSION READINESS REVIEW


1
EO-1 MISSION READINESS REVIEW
  • INDEPENDENT READINESS ASSESSMENT
  • Josef A. Wonsever
  • October 5, 2000

2
EO-1 MISSION READINESS REVIEWINDEPENDENT
READINESS ASSESSMENT
  • Review and Mission Assurance Approach
  • Modified GSFC Independent Review Program
    Conducted by Code 300
  • Spacecraft
  • Primary Instruments
  • Mission Operations
  • EO-1 MAR Imposed for S/C and Instruments
  • Some compromises for Better, Faster, Cheaper
    approach
  • EO-1 Ground Rules
  • Technology Demonstration Mission Would have
    been Class C per NMI 8010.1A
  • Design Mission Life 1 year
  • ALI and Hyperion are Primary Instruments/Technolog
    ies
  • X-Band Phased Array technology needed for science
    downlink
  • AC, LFSA, PPT, CCR, EFF are significantly less
    important
  • KSC Responsible for Delta 7320-10 ELV, including
    DPAF

3
EO-1 MISSION READINESS REVIEWINDEPENDENT
READINESS ASSESSMENT
  • EO-1 Spacecraft/Mission Reviews
  • Review Date RFAs Status
  • S/C Requirements Review 6/7/96 Working Meeting
    - No RFAs
  • Design Convergence Review 11/21/96 Working
    Meeting - No RFAs
  • Gnd. Syst. Requirements Review 2/27/97 Working
    Meeting - No RFAs
  • Confirmation Review 5/6/97 21 Closed
  • Critical Design Review 6/25-27/97 40 Closed
  • Mission Operations Review 11/6/97 23 Closed
  • Delta Critical Design Review 9/23/98
    18 Closed
  • Delta Confirmation Review 10/14/98 6 Closed

4
EO-1 MISSION READINESS REVIEWINDEPENDENT
READINESS ASSESSMENT
  • EO-1 Spacecraft/Mission Reviews (continued)
  • Review Date RFAs Status
  • L-1 Review 1/22/99 28 Closed
  • Delta Mission Operations Review 1/28/99
    20 Closed
  • Pre-environmental Review 6/10/99
    2316 Closed
  • T/V Readiness I/II/III Reviews 9/7-10/1/99
    10 Closed
  • Flight Operations Review 11/16-17/99 15 Closed
  • Pre-Ship Review 12/15/99 289 Closed
  • T/V II Readiness Review 6/12/00 3 Closed
  • Delta Pre-Ship Review 8/9-10/00 22
    In Review
  • Operations Readiness Review 10/3/00 3 1
    Open

5
EO-1 MISSION READINESS REVIEWINDEPENDENT
READINESS ASSESSMENT
  • EO-1 Instrument Reviews - ALI
  • Review Date RFAs Status
  • Requirements Review 6/7/96 Working Meeting -
    No RFAs
  • Design Convergence Review 1/29/97 Working
    Meeting - No RFAs
  • Critical Design Review 6/4-5/97 30 Closed
  • Pre-Environmental Review 8/5/98 10 Closed
  • Pre-Ship Review 1/20/99 5 Closed

6
EO-1 MISSION READINESS REVIEWINDEPENDENT
READINESS ASSESSMENT
  • EO-1 Instrument Reviews - HYPERION
  • Review Date RFAs Status
  • Concept Design Review 8/6/98 47 Closed
  • Pre-Environmental Review 4/13/99 16 Closed
  • Pre-Ship Review 6/30/99 10 Closed

7
EO-1 MISSION READINESS REVIEWINDEPENDENT
READINESS ASSESSMENT
  • Except as noted, All RFAs For EO-1 Reviews Have
    Been Closed
  • Remaining Reviews
  • Flight Readiness Review 11/9/00
  • Launch Readiness Review 11/15/00

8
EO-1 MISSION READINESS REVIEWINDEPENDENT
READINESS ASSESSMENT
  • EO-1 RESIDUAL RISK ASSESSMENT
  • Issue Residual Risk Mitigation
  • Single string design Medium - None
  • with complex mission
  • EEE Parts level Medium - None
  • Grade 3, Some commercial
  • WARP - No EM unit,Troubled Medium -
    Successful extended test period
  • development/test history

9
EO-1 MISSION READINESS REVIEWINDEPENDENT
READINESS ASSESSMENT
  • EO-1 RESIDUAL RISK ASSESSMENT (Continued)
  • Issue Residual Risk Mitigation
  • AST Startracker - Troubled Medium - Known
    problems have been
  • history, DS-1 failure addressed,
  • - IMAGE tracker working well
  • Project understaffing and Medium - Schedule
    slips have helped
  • schedule pressure relieve pressure,
  • - Additional temporary staff
  • augmentation for part of IT
  • Late paperwork closeout Medium - Augmented
    staff helped work
  • through large bow wave of paper,
  • - Recently paperwork has
  • been kept reasonably current

10
EO-1 MISSION READINESS REVIEWINDEPENDENT
READINESS ASSESSMENT
  • EO-1 RESIDUAL RISK ASSESSMENT (Continued)
  • Issue Residual Risk Mitigation
  • Transponder - Late replacement, Low - Passed
    all tests,
  • Inconclusive failure analysis - Workmanship
    issues believed
  • not applicable to Triana unit,
  • - Minor ACG spikes probably not
  • related to original EO-1 failure
  • DPAF first flight Low - Thorough Boeing
    process for
  • new hardware
  • Personnel turnover Low - None
  • (Very few left from 96)

11
EO-1 MISSION READINESS REVIEWINDEPENDENT
READINESS ASSESSMENT
  • EO-1 RESIDUAL RISK ASSESSMENT (Continued)
  • Issue Residual Risk Mitigation
  • IRU - Helium contamination Low -
    Extensive measures taken to
  • reduce He exposure
  • ALI - Self contamination Low - Heaters
    added to drive off
  • in vacuum contamination,
  • - Rate of accumulation appears
  • to be decreasing
  • Inexperienced prime S/C Low - Close
    relationship with GSFC,
  • contractor (Swales) - Some highly experienced
    former
  • GSFC personnel on Swales team

12
EO-1 MISSION READINESS REVIEWINDEPENDENT
READINESS ASSESSMENT
  • EO-1 RESIDUAL RISK ASSESSMENT (Continued)
  • Issue Residual Risk Mitigation
  • Late addition of Hyperion Low - None
  • (Spring 1998, 1 year delivery,
  • 10 mass, 20 power for S/C)
  • Hyperion Cal Lamps - Primary Very Low -
    Secondary lamps show lamps
  • lamps failed, cause unknown no problems so
    far,
  • - Short on-orbit life requirement,
  • - Cal can be done using moon
  • Sprague Capacitors tbd - Under
    investigation

13
EO-1 MISSION READINESS REVIEWINDEPENDENT
READINESS ASSESSMENT
  • EO-1 RESIDUAL RISK ASSESSMENT (Continued)
  • Issue Residual Risk Mitigation
  • The usual suspects
  • Interpoint Converters Low
  • Tin Whiskers n/a
  • - Thorough review, risk action
  • ATC Capacitors Low assessment and
    corrective
  • (as appropriate) by Code 562
  • Vishay Resistors Low
  • Optocouplers Low
  • OVERALL ASSESSMENT - MEDIUM RISK MISSION

14
EO-1 MISSION READINESS REVIEWINDEPENDENT
READINESS ASSESSMENT
  • Safety
  • No Open Issues for EO-1
  • Routine Verification Tracking Log items remain to
    be worked as planned
  • NOTE SAC-C safety data package overdue

15
EO-1 MISSION READINESS REVIEWINDEPENDENT
READINESS ASSESSMENT
  • Recommendation
  • Subject to resolution of Sprague capacitor issue
    and closeout of remaining RFAs
  • Ready for Final Launch Processing

16
EO-1 MISSION READINESS REVIEWINDEPENDENT
READINESS ASSESSMENT
  • Backup - Spacecraft/Mission Complexity
  • ACS - Three axis stabilized
  • Pointing Accuracy 0.022o, Jitter lt5 arcsec, 20
    arcsec instrument alignment
  • Star Camera, GPS, Hemispherical Resonator IRUs
  • Independent Safehold Processor
  • POWER - Deployed, Articulated S/A, 600 w EOL,
    50ah Super NiCad Battery
  • PROPULSION - Hydrazine blowdown system with 4
    thrusters _at_ 0.2 lb each
  • Formation Flying required (With Landsat-7)
  • CDH
  • Mongoose V processor _at_12 Mhz, WARP 840Mbps/48Gbit
    processor/recorder
  • 1773 Fiber optic data bus
  • X-Band Phased Array, 105 Mbps Science, S-Band, 2
    Mbps Housekeeping
  • INSTRUMENTATION
  • 2 Primary Instruments, numerous secondary
    instruments/technologies
Write a Comment
User Comments (0)
About PowerShow.com