Title: EO1 MISSION READINESS REVIEW
1EO-1 MISSION READINESS REVIEW
- INDEPENDENT READINESS ASSESSMENT
- Josef A. Wonsever
- October 5, 2000
2EO-1 MISSION READINESS REVIEWINDEPENDENT
READINESS ASSESSMENT
- Review and Mission Assurance Approach
- Modified GSFC Independent Review Program
Conducted by Code 300 - Spacecraft
- Primary Instruments
- Mission Operations
- EO-1 MAR Imposed for S/C and Instruments
- Some compromises for Better, Faster, Cheaper
approach - EO-1 Ground Rules
- Technology Demonstration Mission Would have
been Class C per NMI 8010.1A - Design Mission Life 1 year
- ALI and Hyperion are Primary Instruments/Technolog
ies - X-Band Phased Array technology needed for science
downlink - AC, LFSA, PPT, CCR, EFF are significantly less
important - KSC Responsible for Delta 7320-10 ELV, including
DPAF
3EO-1 MISSION READINESS REVIEWINDEPENDENT
READINESS ASSESSMENT
- EO-1 Spacecraft/Mission Reviews
- Review Date RFAs Status
- S/C Requirements Review 6/7/96 Working Meeting
- No RFAs - Design Convergence Review 11/21/96 Working
Meeting - No RFAs - Gnd. Syst. Requirements Review 2/27/97 Working
Meeting - No RFAs - Confirmation Review 5/6/97 21 Closed
- Critical Design Review 6/25-27/97 40 Closed
- Mission Operations Review 11/6/97 23 Closed
- Delta Critical Design Review 9/23/98
18 Closed - Delta Confirmation Review 10/14/98 6 Closed
4EO-1 MISSION READINESS REVIEWINDEPENDENT
READINESS ASSESSMENT
- EO-1 Spacecraft/Mission Reviews (continued)
- Review Date RFAs Status
- L-1 Review 1/22/99 28 Closed
- Delta Mission Operations Review 1/28/99
20 Closed - Pre-environmental Review 6/10/99
2316 Closed - T/V Readiness I/II/III Reviews 9/7-10/1/99
10 Closed - Flight Operations Review 11/16-17/99 15 Closed
- Pre-Ship Review 12/15/99 289 Closed
- T/V II Readiness Review 6/12/00 3 Closed
- Delta Pre-Ship Review 8/9-10/00 22
In Review - Operations Readiness Review 10/3/00 3 1
Open
5EO-1 MISSION READINESS REVIEWINDEPENDENT
READINESS ASSESSMENT
- EO-1 Instrument Reviews - ALI
- Review Date RFAs Status
- Requirements Review 6/7/96 Working Meeting -
No RFAs - Design Convergence Review 1/29/97 Working
Meeting - No RFAs - Critical Design Review 6/4-5/97 30 Closed
- Pre-Environmental Review 8/5/98 10 Closed
- Pre-Ship Review 1/20/99 5 Closed
6EO-1 MISSION READINESS REVIEWINDEPENDENT
READINESS ASSESSMENT
- EO-1 Instrument Reviews - HYPERION
- Review Date RFAs Status
- Concept Design Review 8/6/98 47 Closed
- Pre-Environmental Review 4/13/99 16 Closed
- Pre-Ship Review 6/30/99 10 Closed
7EO-1 MISSION READINESS REVIEWINDEPENDENT
READINESS ASSESSMENT
- Except as noted, All RFAs For EO-1 Reviews Have
Been Closed - Remaining Reviews
- Flight Readiness Review 11/9/00
- Launch Readiness Review 11/15/00
8EO-1 MISSION READINESS REVIEWINDEPENDENT
READINESS ASSESSMENT
- EO-1 RESIDUAL RISK ASSESSMENT
- Issue Residual Risk Mitigation
- Single string design Medium - None
- with complex mission
- EEE Parts level Medium - None
- Grade 3, Some commercial
- WARP - No EM unit,Troubled Medium -
Successful extended test period - development/test history
9EO-1 MISSION READINESS REVIEWINDEPENDENT
READINESS ASSESSMENT
- EO-1 RESIDUAL RISK ASSESSMENT (Continued)
- Issue Residual Risk Mitigation
- AST Startracker - Troubled Medium - Known
problems have been - history, DS-1 failure addressed,
- - IMAGE tracker working well
- Project understaffing and Medium - Schedule
slips have helped - schedule pressure relieve pressure,
- - Additional temporary staff
- augmentation for part of IT
- Late paperwork closeout Medium - Augmented
staff helped work - through large bow wave of paper,
- - Recently paperwork has
- been kept reasonably current
10EO-1 MISSION READINESS REVIEWINDEPENDENT
READINESS ASSESSMENT
- EO-1 RESIDUAL RISK ASSESSMENT (Continued)
- Issue Residual Risk Mitigation
- Transponder - Late replacement, Low - Passed
all tests, - Inconclusive failure analysis - Workmanship
issues believed - not applicable to Triana unit,
- - Minor ACG spikes probably not
- related to original EO-1 failure
- DPAF first flight Low - Thorough Boeing
process for - new hardware
- Personnel turnover Low - None
- (Very few left from 96)
11EO-1 MISSION READINESS REVIEWINDEPENDENT
READINESS ASSESSMENT
- EO-1 RESIDUAL RISK ASSESSMENT (Continued)
- Issue Residual Risk Mitigation
- IRU - Helium contamination Low -
Extensive measures taken to - reduce He exposure
- ALI - Self contamination Low - Heaters
added to drive off - in vacuum contamination,
- - Rate of accumulation appears
- to be decreasing
- Inexperienced prime S/C Low - Close
relationship with GSFC, - contractor (Swales) - Some highly experienced
former - GSFC personnel on Swales team
12EO-1 MISSION READINESS REVIEWINDEPENDENT
READINESS ASSESSMENT
- EO-1 RESIDUAL RISK ASSESSMENT (Continued)
- Issue Residual Risk Mitigation
- Late addition of Hyperion Low - None
- (Spring 1998, 1 year delivery,
- 10 mass, 20 power for S/C)
- Hyperion Cal Lamps - Primary Very Low -
Secondary lamps show lamps - lamps failed, cause unknown no problems so
far, - - Short on-orbit life requirement,
- - Cal can be done using moon
- Sprague Capacitors tbd - Under
investigation
13EO-1 MISSION READINESS REVIEWINDEPENDENT
READINESS ASSESSMENT
- EO-1 RESIDUAL RISK ASSESSMENT (Continued)
- Issue Residual Risk Mitigation
- The usual suspects
- Interpoint Converters Low
- Tin Whiskers n/a
- - Thorough review, risk action
- ATC Capacitors Low assessment and
corrective - (as appropriate) by Code 562
- Vishay Resistors Low
- Optocouplers Low
- OVERALL ASSESSMENT - MEDIUM RISK MISSION
14EO-1 MISSION READINESS REVIEWINDEPENDENT
READINESS ASSESSMENT
- Safety
- No Open Issues for EO-1
- Routine Verification Tracking Log items remain to
be worked as planned - NOTE SAC-C safety data package overdue
15EO-1 MISSION READINESS REVIEWINDEPENDENT
READINESS ASSESSMENT
- Recommendation
- Subject to resolution of Sprague capacitor issue
and closeout of remaining RFAs - Ready for Final Launch Processing
16EO-1 MISSION READINESS REVIEWINDEPENDENT
READINESS ASSESSMENT
- Backup - Spacecraft/Mission Complexity
- ACS - Three axis stabilized
- Pointing Accuracy 0.022o, Jitter lt5 arcsec, 20
arcsec instrument alignment - Star Camera, GPS, Hemispherical Resonator IRUs
- Independent Safehold Processor
- POWER - Deployed, Articulated S/A, 600 w EOL,
50ah Super NiCad Battery - PROPULSION - Hydrazine blowdown system with 4
thrusters _at_ 0.2 lb each - Formation Flying required (With Landsat-7)
- CDH
- Mongoose V processor _at_12 Mhz, WARP 840Mbps/48Gbit
processor/recorder - 1773 Fiber optic data bus
- X-Band Phased Array, 105 Mbps Science, S-Band, 2
Mbps Housekeeping - INSTRUMENTATION
- 2 Primary Instruments, numerous secondary
instruments/technologies