T76'4115 Iteration Demo

Description:

... server, PostqreSQL 7 & 8 Support, CentOS linux support, Java 5, HTML 4.10 strict ... Based on Java's general conventions. Why recreate something that works? ... – PowerPoint PPT presentation

Number of Views:49
Avg rating:3.0/5.0
Slides: 27
Provided by: sober
Category:
Tags: demo | iteration | javas | t76

less

Transcript and Presenter's Notes

Title: T76'4115 Iteration Demo


1
T-76.4115 Iteration Demo
  • PP Iteration24.10.2007

2
Agenda
  • Project status (20 min)
  • Achieving the goals of the iteration
  • Project metrics
  • Realization of tasks
  • Resource usage
  • Work results (15 min)
  • Project plan
  • Requirements
  • Draft of architectural design
  • Used work practices (10 min)

3
Introduction to the project
  • Business simulation games are used in educational
    purposes
  • Some evidence of the learning results is needed
  • Project topic Learning Assessment Tool
  • For business simulations
  • Primary goals of the learning assessment tool
    project are the following
  • To extract and store key performance data from
    the game system on an ongoing basis
  • To generate reports that compare the performance
    of a team or a group to the average performance
    or set performance targets in the game
  • To generate reports that compare the performance
    of a team or a group to their performance in the
    previous rounds of the game
  • To provide what-if analysis to the players, e.g.
    "What would have been the bottom line effect of
    raising the price of my product by 1 on round
    3?"

4
Status of the iterations goals
  • Goal 1 Project planning
  • OK in general. Technical design MOVED LATER,
    because meetings with the customer were so late.
  • Goal 2 Understanding the domain (and getting to
    know the game)
  • OK
  • Goal 3 Requirements specification on general
    level including most important functional
    requirements and use cases
  • Requirements elicitation OK.
  • Requirements analysis, OK, except use-cases MOVED
    LATER.
  • Managing changes in requirements OK, changes will
    be documented in the requirements document and in
    agilefant backlog management tool.
  • Goal 4 Creating prototypes to understand
    technologies
  • MOVED LATER, because all the technologies used in
    development are not selected yet

5
Status of the iterations goals
  • Goal 5 Defining roles and responsibilities
  • OK
  • Goal 6 Selecting working methods and tools
  • OK. Some development tools may be selected later
  • Goal 7 Preparing for the development work
    (building infrastructure, studying)
  • NOT OK. Building infrastructure was delayed
    because the team server was not available. We
    also thought we had a wrong WikiSysop password
    and thats why the wiki is not very well
    organized yet.
  • Goal 8 AgileFant installation and introduction
  • Installation OK. Introduction MOVED LATER, this
    week?
  • Goal 9 Risk analysis
  • OK

6
Status of the iterations deliverables
  • Project plan
  • OK, except chapters 6.3 and 6.4, because the
    later iterations are not planned yet
  • Requirements document
  • OK, Business goals, main domain concepts, user
    groups and all the important functional,
    non-functional requirements and contstraints have
    been collected and documented. Functional
    requirements are divided into three groups.
    Use-cases will be done later.
  • SEPA diaries
  • OK, except chapter 3, it will be added later when
    there are some experiences of SEPA methods

7
Realization of the tasks (1)
  • 27 planned tasks
  • 34 at the end of iteration
  • 6 new tasks
  • PM013 Meetings preparation
  • PM014 Reviewing project plan
  • PM015 Writing PP iteration plan
  • Separated from PM007 Writing project plan
  • RE004 Reviewing requirements document
  • ST007 SEPA Heuristic evaluation
  • ST008 SEPA Pair programming
  • Risk management split in two tasks
  • PM011 Risk identification
  • PM016 Risk analysis


unplanned task ( a new task added during the
iteration)
8
Realization of the tasks (2)
(A sample table)
9
Realization of the tasks (3)
10
Realization of the tasks (4)
  • All hour reports not received yet
  • Differences planned realized (shoud be r p,
    fixed later)
  • It seems like the corresponding tasks were not
    always found from the time tracking system
  • Group meetings include all kinds of meetings
    among the group members
  • Some other tasks were carried out in the meetings
    (for example risk identification), but the time
    is still reported as group meetings time


11
Realization of the tasks (5)
  • Interesting discrepancies
  • PM002 Internal communication 16
  • Did not realize that reading e-mail would also
    take time!
  • PM004 Communicating with customer -4
  • Quite low?
  • PM006 Defining project goals 6,5
  • Reported somewhere else
  • PM012 Specifying tasks -8
  • No-one else than PM did?
  • Other major discrepancies are caused by
    unfinished tasks
  • Architecture is still to be planned and technical
    solutions designed
  • No time reports of requirements engineering
  • Infrastructure is not ready, because
  • We dont have the server yet
  • We thought we had a wrong WikiSysop password


12
Resource usage
Original plan (in the beginning of the iteration)
Realization and updated plan (22.10. To be
updated later!)
(realized hours and updates)
13
Resource usage explanations
  • The PP iteration plan was done quite in a hurry
    and so were the estimations
  • We forgot to estimate hours for I1 and I2!
  • Although the architect thought in the project
    planning phase that he was allocating hours for
    I1
  • No persons responsible declared for tasks!

14
Risks
  • Materialized risks
  • 2. A member is unexpectedly unavailable (for
    example a member becomes ill)
  • 3. Lack of skill, knowledge or expertice
  • 9. SoberIT server is down
  • 10. Unequally divided work
  • 11. Inadequate commitment to the project due to
    other than project activities (full day jobs,
    other studying)

15
Results of the iteration
  • Major deliverables of the iteration
  • Project plan
  • Requirements
  • And
  • System architecture designed this far

16
Project plan - stakeholders
  • Stakeholders and staffing
  • The project group Iteration X

Other stakeholders
17
Project plan - stakeholders
  • Stakeholders and staffing organizational chart

18
Project plan project goals
  • Project goals (discuss most important goals and
    verification criteria)
  • 1. Code quality and documentation
  • Code quality 1) Unit test reviews and code
    reviews. 2) Test coverage.
  • Code documentation Javadocs
  • Arhitectural documentation Reviewed with the
    customer
  • 2. Functionality
  • Functionality Reviewed with the customer
  • Performance Will be measured using J-Meter
  • Limitations Functionality and performance tests
  • 3. Production Use
  • Data Collection Augmented after the first
    iteration
  • Analysis Functionality and performance in
    production use is reviewed with the customer
  • 4. User Documentation
  • Content Reviewed with the customer
  • Integration Incorporating user documentation to
    Cesim's standard documentation build process

19
Project plan project practiced and tools
  • Some important practices and tools
  • Weekly meetings
  • Weekly reports
  • WR Time tracker for time tracking
  • Estimations on how much time is left for
    completing backlog items will be tracked with
    Agilefant

20
Project plan phasing
  • PROJECT PLANNING (25.9. - 24.10.2007)
  • IMPLEMENTATION 1 (25.10. - 12.12.2007)
  • Sprint 1 (25.10. - 15.11.2007)
  • Design core architecture
  • Basic implementation tasks
  • Sprint 2 (16.11. - 6.12.2007)
  • After 2nd sprint the most important architectural
    solutions are implemented as well as the most
    common use cases.
  • Sprint 3 (7.12.2007 - 14.1.2008)
  • Refactoring the code, planning and performing
    tests. Enjoying the Christmas vacation.
  • IMPLEMENTATION 2 (15.1. - 5.3.2008)
  • Sprint 4 (15.1. - 5.2.2008)
  • Implementing additional functional requirements.
  • Sprint 5 (6.2. - 26.2.2008)
  • Last changes are made and the software is ready
    20.2. Peer testing.
  • Sprint 6 (27.2. - 5.3.2008)
  • Documenting and presenting the final product to
    the customer and mentor.

21
Requirements
  • System overview

22
Requirements
  • Functional goals
  • Implementing statistics, analysis and learning
    assessment of results, decisions and selected
    aggregates
  • Implementing what-if analysis
  • Implementing alternative sets of calculation
    features
  • Non-functional goals
  • System needs to be fast, it must support enough
    concurrent users and all features must be
    available with one login
  • Constraints
  • Http-protocol, only acceptable plugin is
    Macromedia Flash, Resin web-server, PostqreSQL 7
    8 Support, CentOS linux support, Java 5, HTML
    4.10 strict

23
Architechture overview
  • Based on modules, to keep data management and
    userview separate
  • A WebService backend for loading procedure
  • Customers original project will be extended to
    support extracting data through WS.
  • MVC based frontend to show the results
  • All data handling will be done with persistence
  • All SQL/XML handling is done using POJOs
  • Results might change with time
  • Queries have to be configureable
  • New parameters can be indexed from original data
  • Original data is saved in the database as objects

24
Architechture overview
25
Coding conventions
  • Based on Javas general conventions
  • Why recreate something that works?
  • Extended to suit our preferences
  • Extensions
  • Exception handling
  • Catch only whats necessary, not more
  • Test driven development
  • JUnit is used with every module
  • Improves documentation
  • Commenting
  • Javadoc is used with every method
  • Comments inside the method, where necessary
  • Logging
  • Internals of the system are logged
  • Using different levels, debug, info and error
  • Good Object-Oriented coding
  • Small interference with insides of other objects
  • Functional cohesion and message coupling, if
    possible

26
Used work practices (updated on 23.10.)
  • How have you been using the planned work
    practices, what are the experiences of
  • mandatory practices time reporting, version
    control,
  • any other practices
  • Are you going to
  • adopt some new practices
  • change the use of the current practices
  • stop using some adopted practices