Title: NuMI Magnet Power Supply System
1NuMI Magnet Power Supply System
- WBS 1.1.3 Power Supply System
- Level 3 Manager
- Nancy Grossman
- FNAL
- July 11, 2001
2Outline
- Overview and Specifications (Nancy Grossman, 20)
- Conventional Power Supplies and Cables (PS)
- Kicker Power Supply and Cables (PS)
- Status of Refurbished PS (Steve Hays, 30)
- Status of Kicker PS (Chris Jensen, 30)
- Status of Cooling System for PS (Dave Pushka,
30) - Cost/Schedule/Concerns (Nancy Grossman, 10)
3Overview of the Magnet Power Supply System
- Conventional Power Supplies (PS) (all existing
PSs to be refurbished or bought from FNAL spares
inventory Steve Hays, Bob Ducar) - Ten 500 KW PS
- 1 Main Ring PS
- Three 240 KW PS (one used at MI8 for testing
horns) - Ten 20 KW PS
- PS for 12 Main Injector trim magnets
- 1 Kicker PS (to be designed, built and tested
Chris Jensen) - AC (480 panel to PS) and DC Power Supply Cables
and Connectors (Steve Hays, Bob Ducar) - All large power supplies are ramped.
- All quad and trim PSs are DC and have their own
PS.
4Refurbished Magnet Power SuppliesSpecifications
- Conventional Power Supplies and Cables (Steve
Hays, Bob Ducar) - Must provide reliable, stable power to beamline
elements while minimizing power consumption. - The NuMI facility is expected to be operational
for of order ten years, and the power supply
system has been designed with this in mind. - Power supplies must accommodate a repetition
period of 1.9 seconds (1 msec flatop). - Want PS to stabilize at flatop, read it to check
current and have time to still extract. - Personnel safety must be assured from possible
electrical, mechanical and radiological hazards
during installation and operations. - Voltage and current requirements for the various
beamline elements determine what power supplies
and cables will be needed. - Table summarizes these requirements and indicates
the chosen power supply for each case. - For beam tuning and focusing, each trim and
quadropole magnet has its own power supply. - Bend circuits use several 500 kW supplies in
series (or for the V105 circuit a Main Ring Power
Supply) in order to obtain the desired voltage
levels.
5Refurbished Magnet Power SuppliesMI60
6Technical Progress Status HV101 PS at MI60
7Technical Progress Status V100, LAM60 and
Quad PS MI60
8Refurbished Magnet Power SuppliesMI62
9Refurbished Magnet Power SuppliesTarget Hall
Service Building
10Refurbished Magnet Power Supply Regulation
- Power supply regulation requirements shown
below - Groundwater irradiation
- Stability of beam on target
- 720 Hz line ripple effect on the PS currents is
shown in the table below. - Need filters on all bend strings
11Refurbished Magnet Power Supply Regulation
- Simulations were run for the NuMI V105 string,
assuming a constant reference voltage. - 5 change in line voltage was easily corrected
for at the level of 25 ppm - with standard voltage regulation. (most
variation one would expect) - 5 load change (resistance) gave a 240 ppm
current variation. - Corresponds to about a 100 C change in the copper
in the magnet or the LCW changing 150C - Need additional regulation.
- HOLEC transductor (5K/string) Special FNAL
regulation electronics (5K/string) - Both are designed and installed in the Main
Injector - This combination of electronics would give
another factor of 2 120 ppm
12Refurbished Magnet Power Supply Regulation
Three strings are still above the required
specifications. So now what?
13Refurbished Magnet Power Supply Regulation
- Bandwidth
- Each string will be tuned for maximum bandwidth.
- 20 Hz is assumed in the previous calculations, 40
Hz may achieved (but not guaranteed). - Gives a factor of 2 in current stability.
- Auto-tune
- Load changes are typically slow changes and thus
Auto-tune can correct for these. - One could then argue why do you need the extra
power supply regulation too? - Auto-tune does not always work.
- Needs beam and working beam position monitors to
work. - Assumes next beam pulse like the previous one.
- Experience at FNAL where significant beam control
is needed says do both. - Since the power supply regulation is also driven
some by groundwater concerns, we want something
that is always working.
14Refurbished Magnet Power Supply Regulation
- NuMI bend string power supply regulation levels
will be achieved by - Filters on all 7 strings.
- HOLEC and FNAL Electronics on all 7 strings.
- Auto-tune.
- Tuning for maximum bandwidth.
- Quadropole power supplies (20 KW PEIs)
- Standard regulation is at /- 0.05 of the
maximum current (100 or 200 amps) - Corresponds to up to /-0.44 variation in
operating current. - Believed to be sufficient.
- Main Injector Trim Magnet power supplies
- Standard regulation is at /- 0.1 of the maximum
current (15 amps) - Believed to be sufficient.
15Refurbished Magnet Power SuppliesStatus
- Conventional Power Supplies and Cables (Steve
Hays, Bob Ducar) - MI60 Power Supply Cables
- DC cable pulls complete (except kicker PS),
including termination on PS side. - AC cabling of power supplies is complete (except
kicker PS). - MI62 Power Supply Cables
- AC cabling done except for Main Ring PS.
- Conventional Power Supplies
- 9 refurbished, 4 for Target Hall still need to be
refurbished. - Ones in existing construction are also in place
(except MR PS and Kicker PS). - 6 large power supplies, 7 quads and 12 trim power
supplies. - Testing of the PS will begin shortly.
- Filter chokes and the Main Ring PS need to be
installed (not behind schedule). - Scheduled to happen soon.
- All ahead of schedule and within budget.
16Specifications for the Extraction Kicker
- Minimum Integrated Field 2.24 kG - m
- Kick Angle _at_ 120 GeV 563 µrad to inside of
ring - Field Rise Time (1-99) 1.30 µs
- Field Fall Time N/A
- Field Flattop Time 9.78 µs minimum( 6 batches)
- Flattop During Pulse 1
- Flattop pulse to pulse 1
- Repetition Rate 1.9 seconds
- Required Charging Time 1.5 seconds
- Magnet Location Immediately Downstream Q602
- Power Supply Location MI-60 Service Building,
South Power Supply Room
17Kicker Power Supply
- Kicker Power Supply - based on MI-52 kicker
design (Chris Jensen) - Design modifications to change polarity of
supply. (Significant design effort.) - Pulse Forming Network driving two (or three
series/parallel) magnets in parallel. - PFN has 32 sections, 33 nF/section, 825
nH/section, 46 kV at minimum kick - Increase coupling of Pulse Forming Network
(versus MI-52) - Longer lifetime capacitors for PFN (versus MI-52)
18Kicker Power Supply
- Work on the charging power supply specification
is in progress. - Drafting is in progress
- Design is 40 complete
- Swtich tube enclosure 50 complete.
- Some long lead time parts ordered
- End of line clipper diodes
- Controls parts
- Kicker controls are 30 complete.
- Much of the design is delayed due to magnet
design questions (ceramic tube) - Much of the kicker construction, machining and
purchase orders will be delayed to FY2003. - Due to funding profile with re-baseline
- Still allows several months of float in the
kicker construction, testing and installation.
19Other Presentations
- Overview and Specifications (Nancy Grossman, 20)
- Conventional Power Supplies and Cables (PS)
- Kicker Power Supply and Cables (PS)
- Status of Refurbished PS (Steve Hays, 30)
- Status of Kicker PS (Chris Jensen, 30)
- Status of Cooling System for PS (Dave Pushka,
30) - Cost/Schedule/Concerns (Nancy Grossman, 10)
20Costs
- Refurbished Power Supply Cable Costs
- Total Budget 900K
- Percent Complete48
- Cables, MR PS, regulation/filters, testing
- Kicker Power Supply and Cables
- Based on 2 magnet design.
- Total Budget 534K
- Percent Complete 40
- Need new cost estimate based on 3 magnet design -
in progress.
21Schedule Milestones
22Concerns/Summary
- Refurbishing of conventional PS and installation
of their AC and DC cables is ahead of schedule
and within budget. - Regulation requirements are tight, but doable
- Concerned about integration of the power supply
regulation/readout into the NuMI Beam Permit
System - Kicker Magnet Power Supply
- On schedule and budget so far, but
- Will the magnet design change to 3 magnets versus
two due to having to use a shorter ceramic tube? - Cost/schedule implications of that are in
progress and nearly complete.