Title: Reducing Project Duration
1Reducing Project Duration
2(No Transcript)
3Time Is Money Cost-Time Tradeoffs
- Reducing the time of a critical activity always
incurs additional direct costs. - Cost-time solutions focus on reducing (crashing)
activities on the critical path to shorten
overall duration of the project. - Reasons for imposed project duration dates
- Customer requirements and contract commitments
- Time-to-market pressures
- Incentive contracts (bonuses for early
completion) - Unforeseen delays
- Overhead and goodwill costs
- Pressure to move resources to other projects
4Options for Accelerating Project Completion
- When Resources are NOT constrained
- Adding Resources
- Outsourcing Project Work
- Scheduling Overtime
- Establishing a Core Project Team- (eliminates
drain of multi-tasking on other projects or work) - Do It TwiceFast (prototype, temporary) and
Correctly (final solution)
- When Resources are constrained
- Fast-Tracking (rethink the network
dependencies) - Critical-Chain (eh)
- Reducing Project Scope
- Compromise Quality (eh)
5Explanation of Project Costs
- Project Indirect Costs
- Costs that cannot be associated with any
particular work package or project activity - Supervision, administration, consultants, and
interest - Costs that vary (increase) with time
- Reducing project time directly reduces indirect
costs. - Direct Costs
- Normal costs that can be assigned directly to a
specific work package or project activity - Labor, materials, equipment, and subcontractors
- Crashing activities increases direct costs
6Reducing Project Duration to Reduce Project Cost
7Project CostDuration Graph
- Find total direct costs for selected project
durations. - Find total indirect costs for selected project
durations. - Sum direct and indirect costs for these selected
project durations. - Compare additional cost alternatives for benefits.
FIGURE 9.1
8Determining Activities to Shorten
- Shorten the activities with the smallest increase
in cost per unit of time. - Ok, so how do we get the costs per activity?
- Assumptions
- The cost relationship is linear. You can crash
less than the limit. - Normal time assumes low-cost, efficient methods
to complete activity - Crash time represents a limitthe greatest time
reduction possible under realistic conditions. - Slope represents a constant cost per unit of
time. Typically its the per-day crash cost - Any acceleration must be bounded so that activity
duration is within the normal and crash times.
9Activity Graph
FIGURE 9.2
10CostDuration Trade-off Example
- Assume we want to reduce project duration and
have recourses to do so - we value each day it is shorted at 50K
Predecessors -- A A A B C,D E,F
Calculate these
- First, calculate Slope (in days) and max Crash
time - Next build the AoN network, with normal times
(we can also do this in excel) - Lastly, crash activities that are most cost
effective to reduce overall project duration
until cost of crashing exceeds benefits
FIGURE 9.3
11CostDuration Trade-off Example (contd)
Put duration shortened, too
FIGURE 9.3 (contd)
12CostDuration Trade-off Example (contd)
FIGURE 9.4 (contd)
13CostDuration Trade-off Example (contd)
FIGURE 9.4 (contd)
14CostDuration Trade-off Example (contd)
FIGURE 9.4 (contd)
15Summary Costs by Duration
- Indirect costs must be calculated, perhaps from
accounting or - client services department (ex. Contracts for
late/early delivery) - May not be as easy to estimate as the book claims
FIGURE 9.5
16Project CostDuration Graph
FIGURE 9.6
17Hey, Wheres the Software Demo?
- Notice theres no How to use MS Project to
crash section in the book or slide deck. - While the .mpp can be adjusted to account for
crashed activities, it is rarely the case that
all activities can be crashed. - Even if multiple activities can be crashed,
crashing is something you want to consider
closely and look at manually, and justify all
decisions.
18Group Exercise
- Consider the following project
19Group Exercise, Continued
- What is the normal duration? What is the fastest
time in the project could be completed in
(without re-sequencing, outsourcing or condensing
tasks or reducing scope). - Indirect costs are reduced by 2000 per day
shortened. What is the crashing plan that
reduces total direct and indirect costs? Is it
the same crashing plan as above? - How would you summarize your recommendations to
get approval for the funds?