Reducing Project Duration - PowerPoint PPT Presentation

1 / 19
About This Presentation
Title:

Reducing Project Duration

Description:

Cost-time solutions focus on reducing (crashing) activities on the ... Predecessors. A. A. A. B. C,D. E,F. First, calculate Slope (in days) and max Crash time ... – PowerPoint PPT presentation

Number of Views:1353
Avg rating:3.0/5.0
Slides: 20
Provided by: charli148
Category:

less

Transcript and Presenter's Notes

Title: Reducing Project Duration


1
Reducing Project Duration
  • Chapter 9

2
(No Transcript)
3
Time Is Money Cost-Time Tradeoffs
  • Reducing the time of a critical activity always
    incurs additional direct costs.
  • Cost-time solutions focus on reducing (crashing)
    activities on the critical path to shorten
    overall duration of the project.
  • Reasons for imposed project duration dates
  • Customer requirements and contract commitments
  • Time-to-market pressures
  • Incentive contracts (bonuses for early
    completion)
  • Unforeseen delays
  • Overhead and goodwill costs
  • Pressure to move resources to other projects

4
Options for Accelerating Project Completion
  • When Resources are NOT constrained
  • Adding Resources
  • Outsourcing Project Work
  • Scheduling Overtime
  • Establishing a Core Project Team- (eliminates
    drain of multi-tasking on other projects or work)
  • Do It TwiceFast (prototype, temporary) and
    Correctly (final solution)
  • When Resources are constrained
  • Fast-Tracking (rethink the network
    dependencies)
  • Critical-Chain (eh)
  • Reducing Project Scope
  • Compromise Quality (eh)

5
Explanation of Project Costs
  • Project Indirect Costs
  • Costs that cannot be associated with any
    particular work package or project activity
  • Supervision, administration, consultants, and
    interest
  • Costs that vary (increase) with time
  • Reducing project time directly reduces indirect
    costs.
  • Direct Costs
  • Normal costs that can be assigned directly to a
    specific work package or project activity
  • Labor, materials, equipment, and subcontractors
  • Crashing activities increases direct costs

6
Reducing Project Duration to Reduce Project Cost
7
Project CostDuration Graph
  • Find total direct costs for selected project
    durations.
  • Find total indirect costs for selected project
    durations.
  • Sum direct and indirect costs for these selected
    project durations.
  • Compare additional cost alternatives for benefits.

FIGURE 9.1
8
Determining Activities to Shorten
  • Shorten the activities with the smallest increase
    in cost per unit of time.
  • Ok, so how do we get the costs per activity?
  • Assumptions
  • The cost relationship is linear. You can crash
    less than the limit.
  • Normal time assumes low-cost, efficient methods
    to complete activity
  • Crash time represents a limitthe greatest time
    reduction possible under realistic conditions.
  • Slope represents a constant cost per unit of
    time. Typically its the per-day crash cost
  • Any acceleration must be bounded so that activity
    duration is within the normal and crash times.

9
Activity Graph
FIGURE 9.2
10
CostDuration Trade-off Example
  • Assume we want to reduce project duration and
    have recourses to do so
  • we value each day it is shorted at 50K

Predecessors -- A A A B C,D E,F
Calculate these
  • First, calculate Slope (in days) and max Crash
    time
  • Next build the AoN network, with normal times
    (we can also do this in excel)
  • Lastly, crash activities that are most cost
    effective to reduce overall project duration
    until cost of crashing exceeds benefits

FIGURE 9.3
11
CostDuration Trade-off Example (contd)
Put duration shortened, too
FIGURE 9.3 (contd)
12
CostDuration Trade-off Example (contd)
FIGURE 9.4 (contd)
13
CostDuration Trade-off Example (contd)
FIGURE 9.4 (contd)
14
CostDuration Trade-off Example (contd)
FIGURE 9.4 (contd)
15
Summary Costs by Duration
  • Indirect costs must be calculated, perhaps from
    accounting or
  • client services department (ex. Contracts for
    late/early delivery)
  • May not be as easy to estimate as the book claims

FIGURE 9.5
16
Project CostDuration Graph
FIGURE 9.6
17
Hey, Wheres the Software Demo?
  • Notice theres no How to use MS Project to
    crash section in the book or slide deck.
  • While the .mpp can be adjusted to account for
    crashed activities, it is rarely the case that
    all activities can be crashed.
  • Even if multiple activities can be crashed,
    crashing is something you want to consider
    closely and look at manually, and justify all
    decisions.

18
Group Exercise
  • Consider the following project

19
Group Exercise, Continued
  • What is the normal duration? What is the fastest
    time in the project could be completed in
    (without re-sequencing, outsourcing or condensing
    tasks or reducing scope).
  • Indirect costs are reduced by 2000 per day
    shortened. What is the crashing plan that
    reduces total direct and indirect costs? Is it
    the same crashing plan as above?
  • How would you summarize your recommendations to
    get approval for the funds?
Write a Comment
User Comments (0)
About PowerShow.com