World Bank ERPA Features

1 / 18
About This Presentation
Title:

World Bank ERPA Features

Description:

that can manage risk and expedite process (1) ... that can manage risk and expedite process (2) Other practical considerations ... – PowerPoint PPT presentation

Number of Views:39
Avg rating:3.0/5.0
Slides: 19
Provided by: charlott76

less

Transcript and Presenter's Notes

Title: World Bank ERPA Features


1
  • World Bank ERPA Features
  • and
  • Risk Profile of JI Projects

Jari Vayrynen Operations Team Leader Carbon
Finance Unit World Bank March 2007
2
World Bank ERPAs- purpose-key features
3
Generation of CERs ERPA
ERUs
ERPA

Issuance of ERUs by the Host Country
Verification by an independent auditor
(Independent Accredited Entity)
Generation of Emission Reductions
4
Purpose of ERPA
  • Record agreement
  • Identify responsibilities
  • Establish rights
  • Manage risk

5
Basics of World Bank ERPAs
  • Goals consistency, flexibility, reducing
    transaction costs
  • Two parts
  • General Conditions - standard terms, conditions,
    rights/ obligations
  • Negotiated agreement - purchase amount, price,
    payment terms, preconditions, representations and
    warranties

6
WB ERPA Features
  • Sale and Purchase agreement
  • Object is the commodity of ERs
  • Amount, Price and Delivery/Payment Schedule
  • Defines who does what with regard to
  • Validation
  • Registration
  • Monitoring
  • Verification Certification
  • Provisions on payment for ERs and
    preparation/supervision cost recovery (if any)
  • Payment generally upon delivery, some advance
    payments possible
  • Recovery of cost, if any, capped and defined
  • Events of Defaults and Remedies
  • E.g. under delivery of ERs
  • Other than for willful breach, no tough
    penalties, preferred option to amend ER delivery
    schedule
  • WB ERPAs typically do not include delivery
    guarantee from seller

7
Risk Profile of JI Projects- principle of risk
allocation- key elements of risk - impact on
pricing- some practical considerations
8
Risk Allocation between Buyer and Seller
  • Risk is allocated to the party best able to bear
    it
  • Three key risk categories
  • Underlying project risks
  • Kyoto Protocol risks
  • ERPA structuring/terms risk
  • Rules of thumb
  • Project risks borne by seller
  • Kyoto Protocol risk primarily borne by either the
    seller (ERU) or buyer (VER)
  • ERPA structuring/terms risk relatively less
    important and matter of negotiation

9
Kyoto Protocol Risks (1)
  • Risk may be allocated either to seller or buyer
  • VER buyer takes Kyoto risk gtgt lower price
  • ERU Project owner takes Kyoto (including host
    country compliance) risk gtgt higher price
  • Important price determinant because if the
    project does not meet Kyoto requirements, it
    generates no asset for Kyoto compliance needs

10
Kyoto Protocol Risks (2)
  • Main component is risk of project determination
  • methodology, additionality
  • Letter of Approval
  • Other component ERU issuance risks
  • Risks related to proper monitoring and
    verification
  • Risks related to host country actually issuing
    and transferring the ERUs to buyer

11
Project Risks
  • Risk of the underlying project
  • Construction, operation, delays,
    licensing/permits
  • Reliability and level of complexity of the
    technology used
  • Generally borne by Project Entity but can be
    limited by e.g.
  • conservative ER estimates
  • Also a very important price determinant as has
    direct impact on likelihood and timing of the
    physical ERs being generated

12
Risks related to ERPA Structure (1)
  • ERU delivery guarantees required by buyer or not
  • 3rd important price determinant
  • If guarantees provided by seller, can get 10-30
    higher price but a big risk to take
  • Large variation on how delivery guarantee defined
  • WB ERPAs typically do not include delivery
    guarantee from seller
  • Advance Payments
  • Risk to buyer that the project is not completed
    and does not deliver the emission reductions
  • The price may be discounted to reflect this risk
    taken by buyer
  • Can be mitigated by the seller providing a
    guarantee for the advanced amount

13
Risk Related to ERPA Structure (2)
  • Preparation costs
  • If buyer pays for them, may discount the price to
    reflect this
  • Structure of delivery
  • If buyer has rights to all/first ERUs generated,
    likely to pay a higher price

14
Some practical considerations/lessons learned
15
Other practical considerations that can manage
risk and expedite process (1)
  • Prepare technical and financial (pre-)Feasibility
    study
  • Ensure clear commitment from company management
    (and not just operational staff)
  • E.g. included in the business plan
  • Establish clear institutional set up between
    project owner, advisers, and technology
    provider/sub-contractor important
  • Advanced stage of negotiations with equity and
    debt financiers is helpful
  • Compliance with environmental regulations,
    including transparent stakeholder consultations

16
Other practical considerations that can manage
risk and expedite process (2)
  • Application of an already approved CDM
    methodology makes a big difference
  • Cuts down JI preparation time and reduces risk of
    non-Determination
  • Typically point source reductions or clearly
    defined systems are easier
  • e.g. landfill gas flaring, N20 catalyzer,
    utilization of coal mine methane
  • e.g. wind power project displacing coal in the
    national grid
  • Dispersed or multi-component/measure projects
    tend to be more challenging
  • expect a longer preparation time
  • e.g. transportation, household level energy
    efficiency
  • e.g. complicated industrial energy efficiency
    improvement programs or complex district heating
    system upgrades

17
Other practical considerations that can manage
risk and expedite process (3)
  • Consider your commercial strategy for ER sales
    carefully
  • Sell all ERs or part of the ERs, save some for
    sale at the spot market?
  • Sell all ERs to one buyer or to several buyers?
  • What is the delivery schedule of the ERs to the
    buyer(s)
  • E.g. deliver all of them in the first 2 year of
    the project OR, for example, deliver 400,000
    ERs/year over five years?

18
Thank youwww.carbonfinance.org
Write a Comment
User Comments (0)