Installation and Commissioning of the - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

Installation and Commissioning of the

Description:

Split silicon allows installation with end calorimeters & end irons on platform ... Cognizance of fixed end date an important ingredient in our deliberations ... – PowerPoint PPT presentation

Number of Views:228
Avg rating:3.0/5.0
Slides: 19
Provided by: Jonathan5
Category:

less

Transcript and Presenter's Notes

Title: Installation and Commissioning of the


1
  • Installation and Commissioning
    of the
  • D0 Detector
  • Overview since last review
  • Organization
  • Current status
  • Installation sequence, logistics
  • Schedule, timelines
  • Commissioning status, plans
  • Conclusions
  • Jon Kotcher
  • Brookhaven National Laboratory
  • D0 Collaboration
  • DoE Review
  • Fermilab
  • June 6-7, 2000

2
Overview of Last Six Months
  • Directors Review of Installation
    Commissioning, December 7-8, 1999
  • Extensive review
  • Detectors, electronics, infrastructure, DAQ,
    trigger, online,
  • Much learned, useful exercise
  • Detailed reconsideration(s) of installation
    sequence in recent months
  • Split silicon allows installation with end
    calorimeters end irons on platform
  • Removes constraint of remaining in open
    configuration for its installation
  • Large pieces can be put in final position earlier
  • Can be installed, serviced, removed (upgrades) in
    Assembly or Collision Hall
  • Same 39 gap between calorimeters exists in both
    locations, access not an issue
  • Uninterrupted hookup commissioning time where
    it matters most
  • Full six months prior to roll in
  • Chosen sequence relieves pressure on end game
  • Resources, manpower needs distributed more evenly
    in time
  • Early confrontation of potential difficulties,
    recovery
  • Cognizance of fixed end date an important
    ingredient in our deliberations
  • March 1, 2001 taken quite seriously
  • Carefully optimize remaining time in order to
    roll in complete, physics-ready detector for Run 2

3
Organization
  • Installation Core Group
  • J. Kotcher (APM - Installation Commissioning)
  • R. Hance (Project Engineer Electrical)
  • K. Krempetz (Project Engineer Mechanical)
  • D. Miller (Technical Supervisor)
  • Weekly Monday Installation Meeting
  • Attended by all primary players, including
    detector representatives, Commissioning
    Coordinator (J. Yu)
  • Schedule all jobs
  • Monitor progress
  • Track potential interferences (space allocation)
  • Allocation of manpower, other resources
  • Surveyors, welders, crane, engineering,
  • Safety considerations, requirements,
    documentation
  • All work of significance requires presentation to
    this group 1 month in advance before it can be
    scheduled
  • Any work in Assembly or Collision Hall requires
    our approval
  • Core group collaborates closely on all issues
  • Priorities set by Kotcher, with extensive input
    from many others
  • Ensure appropriate allocation of limited
    resources, space, etc.
  • Timely decision-making

4
Approach to Schedule
  • Durations/logistics discussed in detail with
    principals, including
  • Detector installation, cabling, checkout
  • Logistics/interleaving of electronics
    installation
  • Conservative assumptions in many durations,
    intended to compensate for
  • Ramp-up of tasks
  • Possible delays in engineering/design completion,
    fabrication, etc.
  • Unforeseen difficulties
  • Reconsideration of durations associated with
    movement of large pieces
  • Put large pieces in place as soon as possible
  • Platform, trusses, Forward Muon octant
    installation, roll-in hookup in Collision Hall,
  • Competing needs for space taken into account
    wherever possible
  • Most remaining installation of Forward Muon
    octants assumed to be done serially
  • Crane availability
  • Unique needs, availability of specialized
    personnel
  • Double shifts assumed, will begin June 19
  • Hand-picked four-man team dedicated primarily to
    Forward Muon installation
  • Limit scope of work safety, etc.
  • Needed for timely completion of octant
    installation before roll-in
  • Durations of associated tasks reduced by 30 -
    quite conservative

5
Installation Status
  • Solenoid
  • Installed, tested, mapped
  • Hall probes calibrated in situ
  • Central Preshower
  • Installed with solenoid
  • Central Muon
  • Inner A-? counters, cosmic cap scintillation
    counters, refurbished PDTs
  • Installed, being commissioned
  • Level 1 2 Trigger Framework
  • Installed, being exercised, commissioned
  • Forward Preshower, Inter-cryostat Detector,
    Luminosity Monitor
  • Mounted on faces of end calorimeters end April,
    2000
  • Forward Muon
  • All (16) A-layer MDT octants installed on end
    irons
  • EMC trusses in Hi Bay, being prepped for move to
    sidewalk

These are final Run 2 systems, in place, varying
stages of hookup/commissioning
6
Muon Detector Upgrade
Central Trigger Scint (A-f )
PDTs
Forward Trigger Scint (Pixels)
Shielding
Forward Tracker (MDTs)
Bottom B/C Scint
7
Partial Installation Task List
  • Below represents 10 of full Installation Task
    List
  • Each task discussed in detail in weekly meeting,
    status updated
  • List is priority ordered, maintained by Core
    Group

 
8
Representative Completed Tasks
9
C-layer MDT Being Assembled in Lab F
  • Size, weight, number of Forward Muon octants
    places significant demands on resources/labor
  • Critical sub-system during coming months

10
Commissioning Status
  • Commissioning Coordinator appointed (J. Yu)
  • Weekly Commissioning Meeting attended by all
    principals
  • Progress reports, priorities set, monitoring of
    long- and short-term milestones, daily run plans
  • (3) mini-workshops in DAB
  • focus work toward achieving milestones
  • Commissioning considerations being integrated
    into installation priorities
  • Proper application of resources to ensure timely
    availability of crucial items
  • infrastructure, cabling, electronics
    installation, etc.
  • Installation commissioning intimately linked
  • Recent accomplishments associated with March 15
    and May 19 milestones
  • Established multi-detector, multi-crate readout
  • Central Muon scintillation detectors, PDTs
  • Calorimeter (instrumented with Run 1 electronics)
  • Prototype Level 1 muon trigger exercised in situ
  • Silicon front-end read out through VRBs
  • Implemented cosmic ray triggers
  • Two data paths exercised
  • Primary data path, through Trigger Framework and
    Level 3
  • Secondary path using crate control computers

11
Commissioning Status (contd)
  • Established data transfer to DAB from SiDet
  • Additional Run 2 functionality being developed
  • Trigger Framework exercised
  • Centralized run and communication control
  • Online data shipped to Feynman Center, logged
  • Online event monitoring and displays
  • Development of SMT calibration system and
    databases
  • Training of DAQ experts
  • Documentation in place, maintained
  • Extensive system tests/commissioning at remote
    laboratories
  • SiDet (10 test)
  • Cosmic test (CFT, Preshowers) at Lab 3
  • Critical training bed
  • Hardware, expertise, software applied directly to
    commissioning of experiment
  • Integral part of D0 commissioning effort

12
Future Global Commissioning Milestones
  • Jun 15 Begin SiDet full readout test
  • Aug 01 Prepare front-ends for checkout during
    CFT waveguide installation
  • Implement multi-run DAQ
  • Complete necessary infrastructure (cabling, rack
    preparation, etc.)
  • Prepare necessary safety documentation (ORCs) for
    unattended running
  • Sep 15 Complete cabling and checkout of
    CFT-South
  • Begin DAQ long-term stability test
  • Commission Level 3 hardware, filters
  • Commission FAMUS-North A-layer MDTs
  • Dec 15 Begin cosmic ray commissioning of inner
    trackers (SMT-S, CFT), central muon
  • Track reconstruction
  • CFT muon triggers
  • Commission quadrant of central calorimeter
    electronics

13
Conclusions
  • Installation sequence well understood, many steps
    performed before by same people
  • Work carefully organized and monitored, excellent
    support staff
  • Schedule contains many conservative assumptions,
    still requires tightly choreographed series of
    steps
  • Commissioning aggressively being pursued,
    plans/needs taken into account in installation
    scheduling
  • Have not deviated from original plan to have
    complete detector hooked up in February, 2001

14
Installation Fallback Options
  • CFT is done
  • Only detector that, delayed, would have prevented
    movement of large pieces into final configuration
  • Not an issue
  • Fully expect both halves of silicon to arrive as
    scheduled
  • Far prefer to install in Assembly Hall
  • Ease of access, more forgiving time constraints,
    etc.
  • Installation in Collision Hall would have to be
    scheduled
  • But dont have to
  • Infinite schedule contingency in this system
  • Full Forward Muon system should make it
  • Production lines set long ago to respect A, C, B
    installation sequence will not be altered
  • Schedule is conservative, durations generous
  • If portion of B-layer cant be mounted in time,
    roll-in without it
  • We believe this layer can be installed in
    Collision Hall, if necessary
  • Electronics can be installed after roll in, if
    needed
  • Short accesses required, accelerator ramp up
  • Have appropriate complement for detector hookup
  • Commissioning time prior to roll-in will be
    optimized as fully as possible
  • Will continue during initial exposure to beam

15
Installation Approach
  • Installation is integrated part of each
    sub-project
  • sub-detector design takes into account
    installation constraints, interferences, end game
    scenario
  • designs developed from extensive discussions
    between groups
  • A-? counter design based on detailed survey
    measurements
  • design of forward pixels/MDTs in part driven by
    proximity to end iron
  • FPS modular design motivated by
    installation/repair/access concerns
  • CFT connector design developed within very tight
    spatial constraints
  • Evolution of installation plan, activities in
    Assembly Hall, discussed in weekly meeting
    amongst principals
  • More specific, detailed issues discussed in
    sub-project or other integration meetings
  • Silicon, Fiber Tracker, Tracker Integration and
    Installation, Muon Commissioning, ...

16
Installation Approach (contd)
  • Installation of detector is spatially very
    tightly constrained
  • DØ is highly hermetic, sub-detectors very closely
    nested
  • Ways in which it can be assembled very limited
  • Choreography very well understood
  • done before by many of the same people (Level 2
    sub-project managers and other physicists,
    technical staff)
  • collaboration has experience bringing complex
    detector system online quickly, efficiently
  • immediately started taking physics data upon
    roll-in for Run I with no engineering run
  • Appreciate complexity of Run 2 system,
    concomitant demands on planning and execution

17
Organizational Overview
  • Developing integrated approach to installation
    and commissioning
  • intimately linked, natural way to approach it
  • facilitates establishing priorities, decision
    making, related to
  • spatial considerations, interferences
  • availability of detectors, components, resources
  • order in which things are done
  • One person overseeing both operations at
    managerial level
  • physicists, project engineers responsible for
    individual inst/comm sub-tasks (commissioning,
    tracker installation, mechanical/electrical
    infrastructure)
  • sub-projects remain primary players in
    installation/commissioning of their individual
    sub-systems
  • detailed plan for their sub-detectors developed
    by them

18
Tracking System Overview
0.5 m
1.3 m
All detectors in this volume use SVX II readout
Write a Comment
User Comments (0)
About PowerShow.com