COSOPs'ppt - PowerPoint PPT Presentation

1 / 35
About This Presentation
Title:

COSOPs'ppt

Description:

GMAHS Asset Management Support Unit. Brief overview of ... De-super heaters on chillers. Space Heating control. Water Management (flow restrictors etc) ... – PowerPoint PPT presentation

Number of Views:89
Avg rating:3.0/5.0
Slides: 36
Provided by: mday2
Category:
Tags: cosops | heaters | ppt

less

Transcript and Presenter's Notes

Title: COSOPs'ppt


1
Greater Murray Area Health Service
Energy Performance Contracting in WA NSW Case
Studies
AEPCA Seminar Perth, WA October 2003
Stephen Butt Manager, Asset Management Greater
Murray Area Health Service, NSW
2
Presentation Introduction
  • Brief overview of Greater Murray Area Health
    Service
  • Quantify our energy consumption and costs
  • Background to GMAHS energy initiatives and why
  • Overview of EPC initiatives at WWBH/ABH GBH
  • Discuss some of the items that require
    consideration, risk investigation and what we
    have learnt
  • Summary and close
  • Questions

GMAHS Asset Management Support Unit
3
Greater Murray Area Health Service
GMAHS Asset Management Support Unit
4
Greater Murray Area Health Service
  • serves 260,000 people
  • approx. 3000 FTE
  • 300 m operating Budget
  • 29 Hospitals
  • 40 Community Health Buildings

GMAHS Asset Management Support Unit
5
GMAHS Energy Consumption and Costs
  • Approximately 160 physically metered sites
  • Total consumption of 184,037 Gj (01/02)
  • Total Cost of 2.914 m for 01/02
  • Major costs associated with hospitals
  • 3 Base hospitals consume significant portion of
    energy (60/40)

GMAHS Asset Management Support Unit
6
GMAHS Energy Initiatives and WHY ?
  • Initiatives
  • EPCs at WWBH ABH in place for 2 years
  • Current EPC at GBH nearing completion
  • Energy Manager
  • Small site GEEIP opportunities
  • Every project (big or small) has an energy review
  • Create a culture of treating every maintenance /
    building action as an energy opportunity

GMAHS Asset Management Support Unit
7
GMAHS Energy Initiatives and WHY ?
  • Why
  • GEMP
  • Ailing and failing plant
  • Funding opportunities
  • Professional responsibilities
  • It makes financial sense
  • Dont loose the opportunity

GMAHS Asset Management Support Unit
8
HOW MUCH DO WE NEED TO SAVE TO MEET OUR TARGETS
GMAHS Asset Management Support Unit
9
GMAHS GEMP
GMAHS Asset Management Support Unit
10
Case Study 1 Facility Overviews
  • Wagga Wagga Base Hospital
  • Large regional referral base hospital (250 beds)
  • Mixture of building stock
  • Floor area of 24,000 m2
  • Annual Energy spend of 475,000
  • Mixture of old and new, efficient and inefficient
    energy plant
  • Mixture of regional hospital services

GMAHS Asset Management Support Unit
11
Case Study 1 Facility Overviews
  • Albury Base Hospital
  • Large regional base hospital (150 beds)
  • Relative new building stock (1994) but DC
    Construction
  • Floor area of 18,000 m2
  • Annual Energy spend of 440,000
  • BMS throughout
  • Typically the same energy saving issues as at
    WWBH

GMAHS Asset Management Support Unit
12
EPC Process
  • signed EPC in late 1999 after over 2 years of
    negotiations (at WWBH
    ABH)
  • Investment approximately 0.8 m
  • IRR approximately 20
  • CO2 reductions of 5,820 tonnes (20 of MJ
    target)
  • 8 year agreement
  • total savings in excess of 200,000 per annum
  • currently reviewing performance of all ECMs

GMAHS Asset Management Support Unit
13
WW AB Hospitals Project Cost Summary
  • Project Summary

GMAHS Asset Management Support Unit
14
Energy Conservation Measures Case Study 1
  • Lighting (both sites) - (50 0f electricity
    savings)
  • BMS Upgrades
  • Plant re-commission and balancing (50 of gas
    savings)
  • De-super heaters on chillers
  • Space Heating control
  • Water Management (flow restrictors etc)
  • Power factor correction
  • currently reviewing performance of all ECMs

GMAHS Asset Management Support Unit
15
Case Study 2 - Griffith Base Hospital Overview
  • Small regional base hospital (100 beds)
  • Mixture of building stock
  • Floor area of 16,000 m2
  • Annual Energy spend of 280,000
  • Scaled down service after centralisation of
    support services
  • Significantly inefficient energy plant
  • No major energy improvements made for 20 years

GMAHS Asset Management Support Unit
16
Griffith Base Hospital Overview
  • Specific Current Energy profile

GMAHS Asset Management Support Unit
17
Griffith Base Hospital Cogeneration system
  • To be delivered as part of a site EPC
  • Small system (211 kVa) to provide base load
  • Total project spend 940k
  • IRR 12
  • Funded from NSW Treasury loan
  • EPC contract period is 7 years
  • Provided best GHG reduction option (1,081 tonnes)

GMAHS Asset Management Support Unit
18
Griffith Base Hospital Cogeneration system
  • To provide 100 of domestic hot water load
  • To provide significant of heating load
  • We required 100 back up of heating services
  • Have alternative diesel fired gen. set for whole
    site as emergency back up (and maintenance
    outages)

GMAHS Asset Management Support Unit
19
Items for consideration
  • Do nothing
  • Capital investment requirements
  • Weekend support and resource issues
  • Increasing maintenance costs
  • Miss matched plant

GMAHS Asset Management Support Unit
20
Items for consideration
  • Cogeneration
  • Energy prices (sensitivity analysis)
  • Gas contracts (competition)
  • Engine maintenance (how much and who)
  • Alternative supply during maintenance and failure
  • Other ECMs and their effect on your load
  • Protection issues, authority approval
  • Know your alternative heat sources

GMAHS Asset Management Support Unit
21
Items for consideration
  • Demand charge risk for short off line experiences
  • Electricity contract flexibility
  • Our Particular installation
  • Noise
  • Fire Rating of installation
  • Rural location and associated project management
  • Engine maintenance

GMAHS Asset Management Support Unit
22
Reduce your risk
  • Through modelling worst case scenarios
  • Catastrophic engine failure
  • Energy price shifts
  • Site characteristics changes
  • Contract issues dependent on delivery method

GMAHS Asset Management Support Unit
23
Griffith Base Hospital Project Cost Summary
  • Project Summary

GMAHS Asset Management Support Unit
24
Specific EPC Considerations
  • Operating in a Rural / Regional environment
  • youre in the country now
  • increased travel costs / time
  • resource issues
  • supervision and timetables
  • difficulties in integrating into, and understand
    the sites

Engineering in the Greater Murray
2003
2000
2001
2002
....
....
....
....
GMAHS Asset Management Support Unit
25
Specific EPC Considerations
  • Maintenance Savings
  • great in theory !!
  • however text book maintenance just doesnt
    happen in hospitals
  • be careful maintenance savings arent used to
    boost the IRR
  • ensure maintenance savings are fully explained
  • in future provide the information and protocol
    for life cycle costing analysis that is
    realistic.

Engineering in the Greater Murray
2003
2000
2001
2002
....
....
....
....
GMAHS Asset Management Support Unit
26
Specific EPC Considerations
  • Deferred Capital Investment
  • great in theory !!
  • do we all have TAM fully implemented ??
  • Do we value our assets in a financial context,
    similar to private industry ??
  • Specify how you want these issues handles. In
    some cases they are better excluded
  • be mindful of the tender analysis process that
    is still to come

Engineering in the Greater Murray
2003
2000
2001
2002
....
....
....
....
GMAHS Asset Management Support Unit
27
Specific EPC Considerations
  • Maintenance Procedures
  • keep your options open
  • be clear on what you want to achieve
  • remember the long term nature of these contracts
  • search for further benefits such as contract
    consolidation, coverage of extra equipment,
    training opportunities for staff, total business
    approach
  • beware of hidden costs and agendas

Engineering in the Greater Murray
2003
2000
2001
2002
....
....
....
....
GMAHS Asset Management Support Unit
28
Specific EPC Considerations
  • Design standards and plant redundancy
  • EPCs dont follow typical building / plant
    procurement processes
  • ensure your requirements are clear and fully
    explained
  • beware of proprietary systems and inter company
    relationships
  • ensure you have a fall back position (i.e.
    redundancy)

Engineering in the Greater Murray
2003
2000
2001
2002
....
....
....
....
GMAHS Asset Management Support Unit
29
Specific EPC Considerations
  • Data, data, data . !
  • Dont ever think you have enough data already to
    run an EPC
  • you need to understand every single function of
    your sites energy use and its possible influences
  • ensure consistency of message and documentation
  • get it correct the first time otherwise you may
    pay in the long run

Engineering in the Greater Murray
2003
2000
2001
2002
....
....
....
....
GMAHS Asset Management Support Unit
30
Specific EPC Considerations
  • Baselines
  • keep them simple
  • some variables will be out of your engineering
    control
  • engage the facility executive staff, and hope
    they understand
  • think energy impact in all your decisions

Engineering in the Greater Murray
2003
2000
2001
2002
....
....
....
....
GMAHS Asset Management Support Unit
31
Specific EPC Considerations
  • Internal Rate of Return (IRR)
  • beware of the bottom line
  • dont miss out on the potential for maximising
    capital investment
  • contractors need to be briefed correctly
  • weight your evaluation criteria carefully

Engineering in the Greater Murray
2003
2000
2001
2002
....
....
....
....
GMAHS Asset Management Support Unit
32
Specific EPC Considerations
  • Implementation timetables
  • Year 0 issues
  • building industry programming/ performance
    relevance
  • slow implementation means lost opportunities
    which should be compensated
  • the client is the one who has most to lose !!

Engineering in the Greater Murray
2003
2000
2001
2002
....
....
....
....
GMAHS Asset Management Support Unit
33
Further Benefits
  • sharing the benefits to other sites
  • standardisation
  • become your own energy performance contractor at
    sites that warrant them
  • use the EPC process and outcomes as a catalyst
    for change, particularly for Engineering staff.

Engineering in the Greater Murray
2003
2000
2001
2002
....
....
....
....
GMAHS Asset Management Support Unit
34
Summary
  • We have lived through the development of EPCs
    and survived, and are soon to prosper.
  • Its horses for courses and choose your projects
    and funding models wisely.
  • Dont expect that the EPC Company will come in
    and do it all for you, be prepared for a lot of
    work and get your data organised which will help
    with returns.
  • These are long term undertakings and be prepared
    to wait
  • Good understanding of your site, its loads and
    consumptions will ensure business confidence in
    your choice.

GMAHS Asset Management Support Unit
35
Questions ?
NSW Case Studies
AEPCA Seminar October 2003
Stephen Butt Manager, Asset Management Greater
Murray Area Health Service, NSW
Write a Comment
User Comments (0)
About PowerShow.com