Title: Dale Crosby, P'E'
1Trail Design Beyond Case Studies
- Dale Crosby, P.E.
- July 27, 2005
2A Community Connection Project
- A multi-use trail project like no other
- Lessons learned/dos donts
- Real life applications
- Creating alternative transportation corridors
3A Community Connection Project
- Vanasse Hangen Brustlin, Inc.
- Borrelli Associates
- Southeastern Surveying
- Ardaman Associates
- EMS
4Challenges
- Undefined corridor without R-O-W
- Mandated by Citizen Referendum
- Multiple Municipal Jurisdictions
- Environmental Impacts
- Railroad Crossings
- Utility Company Approvals
5Challenges
- Public Involvement
- Safety Issues Busy crossings, remote setting,
environmental constraints - Budget and Schedule
6A Community Connection Project
- Location Seminole County, Florida
- Client Seminole County
- Approximately 6.5 miles in length
- Budget Right-of-way and design 1.7M
Construction 6.5M - Funded by Bonded ad valorem tax referendum
7A Community Connection Project
- Create high quality trail experience
- Connect to local schools neighborhoods
- Connect to natural lands parks
- Use environmental construction innovations
(boardwalk, tree protection, construction
material selections, constructions means and
methods, etc.) - Coordinate with local businesses property
owners to minimize impacts - Create a cost-effective functional alignment
8Greenwood Lakes Middle School
Begin Project
Library
Greenwood Lakes Park
Lake Mary High School
YMCA
Soldier's Creek Park
Big Tree Park
Environmental Studies Center
Winter Springs School Site
End Project
9Schools Libraries
- New Winter Springs School
- Lake Mary High School
- Greenwood Lakes Middle School
- Northwest Branch Library
10Existing Recreational Uses
- Environmental Studies Center
- Soldiers Creek Park
- Big Tree Park
- Seminole County Family YMCA
- Greenwood Lakes Park
- Natural lands
11Natural Lands
12A Unique Central Florida Project
- Complex conditions, design diversity
- Pioneering trail design
- Innovative approaches, specific challenges
- Teamwork and trails
13Preferred Alignment
14Alignment Details
15Alignment Details
16Alignment Details
17Alignment Details
18Alignment Details
19What does it take to design a project like this?
- VHB..Attitude
- Genuine interest in community and the people
- Commitment to project
- Investment of time and energy
- Willingness to take risk up front
- Right team
- Right relationship with client
- Take ownership of the project
- County.Outcome-focused design
20Multiple Agencies and Stakeholders
CSX Progress Energy Florida Power
Company FDOT Natural Lands/FDEP Seminole County
School District SJRWMD ACOE City of Winter
Springs Landowners (a total of 362 were
contacted) Public Involvement
21Multiple Agencies and Stakeholders (cont.)
- Seminole County Departments
- Planning Department
- Development
- Natural Lands
- Parks Recreation Department
- Environmental Services
- Public Works
- Traffic Engineering, Roads Stormwater
22Project Schedule
2003
2004
2005
J F M A M J J A S O N D J F M A M J
J A S O N D J F M A M J J A S O N D
CONCEPTS REPORT Data Collection Public
Involvement Analysis/Report FINAL ENGINEERING
Phase I Plans Phase II Plans Public
Involvement Permitting Final
Plans CONSTRUCTION PROJECT DURATION
Completed
23Community Connections
24Trail Amenities Master Plan
25Alternative Typical Sections
26Alternative Typical Sections
27Alternative Typical Sections
28Alternative Typical Sections
29Railroad Corridors Crossings
Soldiers Creek
CR 427
CR 427
30Roadway Corridors Crossings
CR 427
17/92 Crossing
Greenway Blvd.
CSX Crossing
General Hutchinson Parkway
31Utility Corridors
- Florida Power Light
- Progress Energy (Florida Power)
- Ongoing relationships with utility companies
32Power Line Corridors
Progress Energy
Progress Energy
Progress Energy
FPL
33Boardwalk
- Various Materials Considered
- Selection Criteria
- Credible projects completed within the last
three years - Competitive cost/maintenance attractive life
cycle cost
34Boardwalk
35Construction Phase
- Typical section package
- Sanford Oveido Road reconstruction
- Typical field conditions
- Construction plans convey County intent for
quality outcome
36Construction
37Structural Components
38Structural Components
ACEC Award Winner
ACEC Award Winner
American Trails Award Winner