Title: The ISACII Accelerator
1The ISAC-II Accelerator
- Outline
- Overview of ISAC-II
- Status
- Latest Highlights
- Cryogenic system progress
- Cryomodule cold test
- Alignment Studies
2Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
3Stage 0 - 2005
E4.5MeV/u A/q6
S0
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
4Stage 1 - 2007
E6.5MeV/u A/q7
S0
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
5ISAC-II SC Linac
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
6- Outline
- Overview of ISAC-II
- Status
- Latest Highlights
- Cryogenic system progress
- Cryomodule cold test
- Alignment Studies
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
7ISAC-II Present Status
- SCRF development active in new lab
- High Beta Cavity design initiated
- 21 Medium ß Cavities received
- Eight production cavities BCP completed
- Remaining thirteen to receive BCP at JLAB
- First cryomodule being tested
- First cooldown April 23, 2004
- First rf cold test in June 2004
- Five medium ß and two high ß solenoids ordered
- Two received, two more expected next month
- Refrigerator contract awarded to Linde
- phase I 500W
- Due for commissioning in Dec. 2004
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
8ISAC-II Linac
- Composed of quarter wave bulk niobium cavities
and superconducting solenoids housed in box-like
cryomodules - Initial installation of five medium beta
cryomodules schedule for commissioning Nov. 2005 - Prototype medium beta cryomodule now being cold
tested
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
9Medium Beta Cryomodule
- First Medium beta cryomodule in assembly
- First cold test successfully completed April
23-25 - Stainless steel vacuum enclosure
- LN2 cooled copper shield
- mu metal for magnetic field suppression
Lid Assembly in Assembly Frame
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
10Medium Beta Cavity
- Prototype developed in collaboration with A.
Facco of LNL and fabricated in E. Zanon - Simple construction suitable for industry
production - Twenty cavities received from E. Zanon in Italy
- Four BCP CERN, four BCP JLAB
- Remaining cavities to be polished at JLAB
Chemical Polishing at CERN
Frequency Measure at Zanon
Four Cavities at TRIUMF
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
11Cavity Performance
- All cavities meet or exceed the design gradient
(6MV/m _at_7W) in off-line cold tests
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
12First Cold Test of Flattened Cavity
- Meets design goals Ea6MV/m _at_ lt7W
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
13Everson Solenoid
Prototype Solenoid at Everson
- Medium beta prototype received incomplete from
Everson Electric due to bankruptcy - Solenoid was completed at TRIUMF
- Cold test results match design
Solenoid with Helium Reservoir
Axial Field Map
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
14Superconducting Solenoids
Prototype Solenoid at Accel
- Focussing in the SC Linac is provided by
superconducting solenoids (B?9T) - End fringe fields controlled with active
bucking coils (Bcavity?0.1T) - Medium beta prototype received incomplete from
Everson Electric due to bankruptcy - Production Medium and high beta solenoids in
fabrication at Accel - See table for specifications
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
15RF Systems
Forward power required for Ea6MV/m and given
bandwidth
- RF power
- Provide useable bandwidth by overcoupling
- Require Pf 200W at cavity for f 1/220Hz at
Ea6MV/m, ß200 - Coupling loop
- Developing LN2 cooled loop
- Achieved lt0.5W to LHe for Pf250W
- Mechanical tuner
- Precise (0.3Hz), fast (gt5Hz/sec) tuner with
dynamic range of 8kHz and coarse range of 32kHz - Tuning plate
- Spun, slotted, oil-can tuning plate to improve
tuning range
Coupling Loop
Mechanical Tuner
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
16ISAC-II Mechanical Tuner
- Deflects niobium tuning plate at base of cavity
(6 Hz/µm) - Lever mechanism with zero backlash hinges and
stiff rod connected to precision linear motor
(Kollmorgan) in air - In cold tests control loop was phase locked and
tuner maintained frequency during rapid forced
helium pressure fluctuations (1Hz/Torr)
f1/225Hz
17Coupling Loop with Direct Cooling
- Developed from INFN Legnaro adjustable coupling
loop - Modifications
- Stainless steel body for thermal isolation
- Copper outer conductor thermally anchored to
copper LN2 cooled heat exchange block - Aluminum Nitride dielectric inserts thermally
anchor the inner conductor to the outer conductor - Removed fingerstock to control microdust
- Achieved lt0.5W helium heating with Pf250W
18- Outline
- Overview of ISAC-II
- Status
- Latest Highlights
- Cryogenic system progress
- Cryomodule cold test
- Alignment Studies
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
19Cryogenic System
- The cryogenic system will be installed in two
equal stages - Timing will follow staged installation of linac
- Smooths cash flow
- Allows redundancy in final configuration
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
20Cryogenic Loads (Phase 1)
13W
13W
13W
13W
13W
14W
14W
3W
24W
24W
24W
24W
24W
36W
36W
6W
CM1
CM6
CM2
CM3
CM4
CM5
CM7
Medium Beta (4)
High Beta (6)
96W
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
21Cryogenic Loads (Phase 12)
13W
13W
13W
13W
13W
14W
14W
3W
15W
2W
2.W
3W
22W
8W
64W
8W
0W
0W
64W
32W
32W
32W
32W
32W
48W
48W
CM1
CM6
CM2
CM3
CM4
CM5
Medium Beta (4)
High Beta
CM7
530W
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
22Phase 1 Refrigerator
- TC50 comprises
- Cold box
- Main compressor
- Kaeser ESD441
- Recovery compressor
- Kaeser BSD62
- ORS and gas management system
- TRIUMF to install Linde components plus
- Helium dewar, buffer tank, warm piping and cold
distribution
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
23ISAC-II Building
f1/225Hz
f1/225Hz
f1/225Hz
Compressor Room
Buffer Tanks
Refrigerator Room
Linac Distribution
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
24Cold Distribution
Cold Helium Return
LHe
CM1
CM2
CM3
CM4
Cold Box
Dewar
Warm Helium Return
- Parallel supply feed from dewar through main
header (4.5K) - Cold helium return (lt20K) during normal operation
- Warm helium return (gt20K) to compressor suction
used during cooldown and for power lead cooling
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
25Cold Distribution Cryomodule
- Individual vacuum jacketed lines for supply and
return - U-tubes for supply and return to cryomodule from
main trunk-line
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
26Cryogenic Distribution (Phase 1)
- Specification in preparation
- Required for June 2005
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
27Cryomodule Distribution
- Cryomodule cooled by forcing helium vapor to
bottom of each cold element with a distribution
spider
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
28- Status
- Phase I refrigerator expected July 2004
- Commissioning expected before year end
- Warm piping, buffer tank, helium dewar
specifications ready for issue - Cold distribution in design
- First cooldown of cryomodule complete
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
29Cryomodule Cooldown
- Expected static loads
- Med. Beta Cryomodules
- load to helium - 13W/module
- 6 ltr/hour LN2
- First cooldown April 23-25/ 2004
- Alignment of cold mass measured by Wire Position
Monitor (WPM) System
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
30Vacuum Tank
- 1.9cm thick stainless steel (316L) with external
reinforcing ribs - L176cm, W99cm, H196cm
- All services through 44 flanged ports on lid
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
31Assembly Frame
Cryomodule Assembly Frame
- For clean room assembly of cryomodule lid and
contents including rf cavities and solenoid - Top mounting surface and end plates mimic the
vacuum tank top flange and beam ports for
pre-alignment of cavities
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
32Nitrogen Heat Shield
- 10mm ID copper tube soldered to copper sheet
arranged in a box-like structure - Copper nickel plated to reduce emissivity
- Solder applied on hot table without flux in inert
gas environment - Copper cooling tubes run in series
- L36m
- ?P1.9PSI warm and 0.1PSI cold
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
33Cryomodule Alignment
WPM Monitors on Cavities
- the tolerance on solenoid and cavity
misalignments are ?200 ?m and ?400 ?m
respectively - we are collaborating with INFN Milano on the
development of a Wire Position Monitor for cold
alignment with precision of 20 ?m - Stripline monitor attached to each device driven
by rf signal along a reference wire
Plan View
WPM
RF shield
Wire Position Stripline Monitor
Optical target
solenoid
cavities
Optical target
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
34Medium Beta Cryomodule
- First Cooldown preparation
- Pumpdown April 1
- LN2 cooldown April 8-10, April 18-20, May 2-6
- LHe cooldown April 23-25
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
35Cryomodule Pre-cool Test
- Cryomodule cooled with Helium April 23/04
- Pre-cool manifold and spider worked well to
cool cavities and solenoid uniformally
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
36- Pre-cool manifold and spider worked well to
cool cavities and solenoid uniformally
Cooldown Temperatures Main Components
Solenoid
Reservoir
Helium flow
Time (hours)
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
37Cryomodule Static Load
- April 25 First cooldown
- Cooldown and fill consumed 1400ltr LHe
- 200ltr liquid He accumulated in cryomodule
- After thermalization boil-off equivalent to 10W
static load
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
38LN2 Consumption
- Regulated exhaust flow at constant pressure
- 6.2ltr/hour produced 80K shield
- 4.7ltr/hour warmed shield to about 120K
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
39Cold Alignment Test
- Cold Alignment Cycles
- LN2 cooldown April 8-10, April 18-20, May 2-6
- LHe cooldown April 23-25
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
40Alignment Calibration
- Optical targets in first and last cavity were
periodically measured with telescope to calibrate
the temperature contraction of WPM brackets
WPM1 vs West Cavity Target - Horizontal
WPM6 vs East Cavity Target Vertical
WPM1 vs West Cavity Target
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
41Alignment Repeatability
- Cryomodule thermally cycled three times from room
temperature to LN2 temperature - WPM data analyzed to note repeatability of
alignment at cold temperatures - Alignment repeatable to within 80microns
vertically and to within 120microns horizontally
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF
42Cooldown Summary
- First cooldown went smoothly
- Vacuum - 5e-9Torr when cold
- Static load to liquid helium after thermalization
- 10W - LN2 flow to thermal shield 5ltr/hour
- Cold alignment studies using WPM in progress
- Rf test of the first cryomodule is scheduled for
June
Bob Laxdal, The ISAC-II Accelerator, ACOT, May
14,2004, TRIUMF