1MCQUAY DIGITAL SCROLL SYSTEM
Installation
2INSTALLATION
- Bad Installation System will not operate as per
design - Waste of Money
- Waste of Time
- Bad Image
- 3 Major Categories
- Unit Installation
- Piping Installation
- Wiring Installation
3INSTALLATION
- Unit Installation
- Indoor Unit
- Outdoor Unit
Note Installation of indoor unit is same as
normal direct expansion unit.
4INSTALLATION
- Outdoor Unit Installation
- Sufficient area around the unit. No barrier for
supply air and discharge air. - Avoid discharge air return to the unit (Hot Air
short-circuiting) - Strong foundation for the unit
5INSTALLATION
Handling Outdoor Unit
Correct
6INSTALLATION
Handling Outdoor Unit
Wrong
7INSTALLATION
Correct
Wrong
8INSTALLATION
9INSTALLATION
Outdoor Unit Spacing (Single Outdoor Unit)
Wall / Barrier higher than unit
Wall / Barrier lower than unit
Side View
10INSTALLATION
Outdoor Unit Spacing (Single Outdoor Unit)
Top View (Barrier higher than unit)
11INSTALLATION
Outdoor Unit Spacing (Single Outdoor Unit)
Top View (Barrier lower than unit)
12INSTALLATION
Outdoor Unit Spacing (More than 1 unit)
Top View (Wall / Barrier restriction same as 1
outdoor unit)
13INSTALLATION
Outdoor Unit Spacing (More than 1 unit)
Top View (Wall / Barrier restriction same as 1
outdoor unit)
14INSTALLATION
Outdoor Unit Spacing (More than 1 unit)
Top View (Wall / Barrier restriction same as 1
outdoor unit)
15INSTALLATION
- Outdoor Unit Foundation
- Floor location strength
- Able to withstand the unit weight and vibration
- Layout for drainage, piping cables
- Different level, avoid blocking.
- Important for MDS260300B(BR). Oil balancing pipe
must be lower than the connection joint - Screw bolt required to further tighten the unit
- Avoid the unit from falling due to earthquake
16INSTALLATION
- Piping Installation
- Ensure piping is dry, clean and no air leakage
17INSTALLATION
- Piping Installation
- Refnet distributor joints to be install
horizontally
18INSTALLATION
- Piping Installation
- Refnet distributor joints to be install
horizontally
19INSTALLATION
- Piping Installation
- EXV box to be install vertically
20INSTALLATION
- Piping Installation
- Insulation
- Able to withstand the pipe heat
- Heatpump Unit heat resistance polyethylene
foamed ( gt 120 Deg C) - Cooling only - Polyethylene ( gt 100 Deg C)
- Insulation method
- Thickness of insulation
21INSTALLATION
Insulation Method
Wrong Method
Correct Method
22INSTALLATION
- Thickness of insulation
- Depends on pipe diameter
- Notes
- Hot and wet environment, increase then thickness
of the insulation - Cooling with ambient less than 10 deg C,
recommended to insulate the liquid pipe.
23CONTROL
Communication
- Twisted Pair wired with shielding (20AWG)
- Shield wire to be earth on 1 end of the network
- Connected serially to the adjacent unit (Daisy
Chain Connection) - Same polarity between units
24CONTROL
Communication
For the last indoor, Jumper JP-7 need to be
shorted (Top left Corner of the indoor board)
System Wiring
25CONTROL
Communication
System Wiring
Ain Terminal 30 Bin Terminal 31 APC
Terminal 32 BPC Terminal 33
26CONTROL
Communication
MDS080240
Outdoor PCB
Indoor PCB
27CONTROL
Communication
For the last indoor, Jumper JP-7 need to be
shorted (Top left Corner of the indoor board)
System Wiring - MDS260300B(BR)
28CONTROL
Communication
MDS260/280/300
MDS130/150BRS
MDS120/150BRM
Indoor Units
29CONTROL
Control Monitoring Software
RS485
Gateway
RS232
1. Review indoor unit status and error history 2.
Monitor and control all indoor unit 3. Weekly
timer and holiday timer setting
Computer
Indoor units
Outdoor units
Centralize Control
30Thank You