Title: Mark Kowaleski,
1ICESat Ground System (IGS)Kick-Off
MeetingTechnical Management Implementation
PlansMarch 11, 1999
- Mark Kowaleski,
- ICESat Operations Manager
- 301-286-7816
- mark.kowaleski_at_gsfc.nasa.gov
2Agenda Purpose
- AGENDA
- ICESat Mission Overview
- IMIT Team IMIT Monthly Meetings
- Short-Term Activities
- Documentation Flow
- Schedules Schedule Drivers
- Baseline Architecture Major Interfaces
- Top-Level Trades in process
- Wrap-up
- PURPOSE
- Get everyone up to speed regarding everything
that is presently known about the status of the
ICESat Ground System. - Document our operating processes (surprise - ISO
9001). - Identify short term work to be done.
- Identify overall project activities, drivers,
etc. - Give everyone involved a chance to meet everyone
else. - Share Information
3ICESat Mission Profile
- Mission
- July 1, 2001 launch date (depends on rocket)
- 600 km orbit _at_ 94 degree inclination.
- 3 to 5 years to EOL.
- Science - Measure ice sheet height, cloud
structure, topography. - Spacecraft - Ball Aerospace RS2000 bus
derivative. - Instrument - Geoscience Laser Altimer System
(GLAS) by Code 924. - Launch Vehicle - Athena or Delta - TBD.
- SOMO provides
- EPGS operations
- EDOS operations
- Ebnet/NISN operations
- ESDIS provides
- EDOS development
- DAACs
- TBD (this discussion)
- Mission Operations Center
- Flight Operations Team
- Flight Dynamics
- Science Provides
- SCF
- ISIPS
- ISF
- IOT
4ICESat Information Resources
- ICESAT PROJECT - http//icesat.gsfc.nasa.gov/
- GLAS
- http//glas.gsfc.nasa.gov/
- http//glas.wff.nasa.gov/
- EOSDIS - http//spsosun.gsfc.nasa.gov/New_EOSDIS.h
tml - Ball - http//www.ball.com/aerospace/batchp.html
- Science Team - http//ltpwww.gsfc.nasa.gov/eib/gla
s_sci_team.html
5IGS Key Points of Contact (the I-TEAM)
- Highly integrated team from many organizations.
- Direct working interface with OM for
coordination, direction, clarification, problem
resolution, status reporting.
6IGS Team Member Responsibilities
- Help identify Requirements and Deliverables.
- Provide Cost Estimates for their respective IGS
element. - Provide Element Schedule.
- Attend Working Groups Regular Meetings for
Mission Planning support. - Prepare and present Design Status at various
project reviews. - Provide ICDs, Systems, Documents, Operational
Agreements, etc. - Provide Monthly Status Reporting to IGS
Operations Manager.
7IGS Implementation Team (IGSIT) Communications
Project Managers
Science
Instrument
Systems
Spacecraft
Matrixed Support
IGS MIT
8IMIT Meetings Schedule Purpose
- Meeting Guidelines
- Week 1
- Lasts 1 hour maximum (guaranteed).
- 100 PM each accounting Thursday.
- Week 2 -Working Week
- Week 3
- Lasts as long as necessary.
- 830 AM start time TBD.
- At YOUR location.
- Week 4 - Status Reports due
9ICESat Project System Engineering Meeting
Schedules
10Monthly Status Reporting Flow Format
- Contents
- Accomplishments This Month
- Planned Activities Next Month
- Schedule Status
- Implementation Status
- Mission Operations Status
- Top 10 Issues
- Concerns
- Standard Reporting Templates to be provided that
MUST be used.
11IGS Short-Term Major Activities
- 1. Establish the IGS Implementation Team, regular
meetings, Working Groups, etc. - 2. Finalize the IGS requirements and establish a
baseline - MORD. - 3. Develop an integrated end-end IGS
implementation schedule. - 4. Develop cost estimates to explore the
viability of alternate approaches as needed. - 5. Determine IGS procurement items and
acquisition funding flow for each element. - 6. Establish a commitment from each IGS element
to provide systems and services. - 7. Develop an integrated IGS Test Plan.
- 8. Provide monthly status directly to 401.6 and
423.
IGS
12IGS Reviews Major Scheduled Activities
- Short Term
- IMIT Splinter Working Groups (monthly)
- Project Status Review (PSR) to 423/401.6
(monthly). - MOWG II, July, 1999. Others to be scheduled TBD.
- IGS Requirements Peer Review (informal),
September, 1999. - Mission Operations Review, planned December, 1999
but TBD. - Long Term
- Version 1 ISIPS release, December, 2000
- GLAS IT (assembly) starts February, 2000
- 1st S/C Basic CMD/TEL Compatibility Test
(GSCT1), April, 2000 - IGS Test Readiness Review, June, 2000.
- Flight Operations Review, April, 2001.
- Launch Readiness Review, June, 2001.
13ICESat Ground System Schedule Drivers
14IGS Documentation Flow
15Supporting Documentation Available to Date
- ICESat Mission Systems Requirements Document
(MSRD) -Final. - ICESat Mission Operations Requirements Document
(MORD) -Draft. - RF ICD -Near Final.
- Data ICD - Very rough Draft!
- Various Ball Spacecraft documents (TC Hnbk,
Spacecraft Requirements document, etc.). - GLAS Instrument Requirements Document - Final.
- Various Science Computing Facility Documents -
Draft Final. - GLAS Instrument Description Document - Draft
16Schedule Development Needs the Following Elements
- Facilities Readiness
- Personnel (when available training)
- Procurement Items (any items needed)
- Documentation (ICDs, Manuals, Operational
Agreements, Support Plans, Users Guides,
MOU/MOA, etc.) - Hardware Software Procurements
- Equipment Installation Check-out
- Software Coding, Installation, and Check-out
- Element Testing
- Ground System Test Readiness
- Simulation Rehearsal Support
- Reviews Status Reports
- DEPENDENCIES (predecessors) for element
schedules.
17IGS Master Schedule - Line Item Elements to be
Developed
- Major Reviews Documents
- EPGS WFF
- Ebnet NISN
- EDOS
- SCF ISIPS
- DAAC
- MOC FOT
- FDS
- ISF IOT
- IGS Testing, Simulations, Rehearsals
- LEO Support
- Calibration Validation Support
- Normal Operations
18IGS Overview (as it stands today - the Baseline)
19IGS Major Interfaces I2 Chart
20Organizational Funding Considerations
21Top-Level IGS Trades in Process
- Trade A Flight Dynamics System
- GSFC FD (GSFC develops and provides LEO support,
then turns over to MOC/FOT for routine
operations). - Ball FD - Ball does it all.
- Trade B S-band RT, PB, and CMD Data Processing
- EPGS (via PTP/SAFS) processes RT PB S-band
simultaneously - EPGS processes CMDs from MOC.
- EPGS processes just RT telemetry and forwards
to MOC. - EDOS processes PB only and forwards to MOC.
- Trade C X-band Level Zero Data Processing
- EDOS does all X-band processing and strips out
GPS raw data. - EPGS does all X-band processing.
- SIPS Extention - all X-band processing.
Most likely decision.
22Top-Level Trades Overview
23Wrap-Up
- March Splinter Meetings will focus on the
following - Baseline IGS Element Leads.
- IGS Requirements Definition and MORD release.
- IGS Master Schedule Draft.
- Complete Cost Estimate process.
- Baseline IGS Architecture.
- Identify Elements Documentation.
- Status Reporting Templates.
- Continue MOC procurement.
- Next IMIT Meeting on 4/8/99.