2HEC-23 MATRIX FOR SELECTING COUNTERMEASURES
P.F. Lagasse, Ph.D., P.E. Transportation Research
Board 2002 Annual Meeting Sponsored By A2A03
Committee on Hydrology, Hydraulics and Water
Quality
3PURPOSE
- Identify stream instability and scour
countermeasures implemented by various SHAs - Develop a matrix which summarizes countermeasure
application throughout the US. - Provide design guidelines for selected
countermeasures
4THE COUNTERMEASURES MATRIX
- COUNTERMEASURE GROUPS
- FUNCTIONAL APPLICATIONS
- SUITABLE RIVER ENVIRONMENT
- MAINTENANCE
- INSTALLATION EXPERIENCE BY STATE
- DESIGN GUIDELINE REFERENCES
5- THE COUNTERMEASURES MATRIX
- COUNTERMEASURE GROUPS
- GROUP 1 Hydraulic Countermeasures
- Group 1.A. River Training Structures
- Group 1.B. Armoring Countermeasures
6- THE COUNTERMEASURES MATRIX
- COUNTERMEASURE GROUPS
GROUP 2 Structural Countermeasures
- Foundation Strengthening
- Pier Geometry Modification
7- THE COUNTERMEASURES MATRIX
- COUNTERMEASURE GROUPS
GROUP 3 Monitoring
- Fixed Instrumentation
- Portable Instrumentation
- Visual Monitoring
8- THE COUNTERMEASURES MATRIX
- FUNCTIONAL APPLICATIONS
- l Well Suited / Primary Use
- w Possible Application / Secondary Use
- Unsuitable / Rarely Used
- N/A Not Applicable
9THE COUNTERMEASURES MATRIX Suitable River
Environment
- Bed Material
- Ice / Debris Load
- Bank Condition
- Floodplain (Width)
- River Type
- Stream Size (Width)
- Bend Radius
- Flow Velocity
10(No Transcript)
11(No Transcript)
12- Design Guideline 1 - Bendway Weirs/ Stream Barbs
- Design Guideline 2 - Soil Cement
- Design Guideline 3 - Wire Enclosed Riprap
Mattress - Design Guideline 4 - Articulated Concrete Blocks
- Design Guideline 5 - Grout Filled Mattresses
- Design Guideline 6 - Concrete Armor Units
13- Design Guideline 7 - Grout/Cement Filled Bags
- Design Guideline 8 - Rock Riprap at Abutments
Piers - Design Guideline 9 - Spurs
- Design Guideline 10 - Guide Banks
- Design Guideline 11 - Check Dams/ Drop
Structures - Design Guideline 12 - Revetments
14- DESIGN GUIDELINE 1
- Bendway weirs / Stream barbs
- Sources
- Colorado Department of Transportation
- Washington State Department of Transportation
- NRCS
- U.S. Army Corps of Engineers
- Application
- Bankline protection and flow alignment in
meandering channel bends
15(No Transcript)
16(No Transcript)
17- DESIGN GUIDELINE 2
- Soil Cement
- Sources
- Portland Cement Association
- Pima County Department of Transportation
- Maricopa County, Arizona
- Application
- Revetment for banklines and sloping abutments,
drop structures and bed armor
18(No Transcript)
19- DESIGN GUIDELINE 3
- Wire Enclosed Riprap Mattress
- Sources
- New Mexico State Highway and Transportation
Department - Application
- Revetment for banklines, guidebanks, and sloping
abutments
20(No Transcript)
21- DESIGN GUIDELINE 4
- Articulated Concrete Block System
- Sources
- Hydro Review and Hydraulic Engineering 93
- Maine Department of Transportation
- Minnesota Department of Transportation
- Application 1
- Bankline and abutment revetment and bed armor
- Application 2
- Pier scour protection
22(No Transcript)
23- DESIGN GUIDELINE 5
- Articulating Grout Filled Mattress
- Sources
- Oregon Department of Transportation
- Arizona Department of Transportation
- Application
- Bankline and abutment revetment and bed armor
24(No Transcript)
25- DESIGN GUIDELINE 6
- Concrete Armor Units
- Sources
- Pennsylvania Department of Transportation and
Tested at Colorado State University - A-Jacks Testing Manual (CSU)
- and Design Manual (Ayres Associates)
- Application
- Pier scour and abutment scour protection
26(No Transcript)
27(No Transcript)
28(No Transcript)
29(No Transcript)
30- DESIGN GUIDELINE 7
- Grout / Cement Filled Bags
- Sources
- Maryland State Highway Administration
- Maine Department of Transportation
- Application
- Protection of undermined areas at piers and
abutments and bed armor