John Deere Team. Weekly Status Report. Week 2. Josh Ebeling. Jamari Haynes ... Task assigned by John Deere is the open-ended modification of their six wheeled ... – PowerPoint PPT presentation

Number of Views:362
Avg rating:3.0/5.0
Slides: 12
Provided by: ecsGa2
Category:
Tags: deere | john | report | status | team | week | weekly

less

Transcript and Presenter's Notes

Title: John Deere Team Weekly Status Report Week 2


1
John Deere TeamWeekly Status ReportWeek 2
  • Josh Ebeling
  • Jamari Haynes
  • James June
  • Mike Reno
  • Ben Spivey
  • Gary Twedt

2
Project Modification of Gator for Handicap
Accessibility
  • Task assigned by John Deere is the open-ended
    modification of their six wheeled Gator Utility
    Vehicle to facilitate handicapped accessibility
  • Two primary suggestions wheelchair hoisting
    mechanism and controls modification

3
Preliminary Meeting
  • Main contact Bobby Henebry
  • Parameters of project
  • 2000 Budget
  • Modification of Gator for handicapped
    accessibility
  • Parallel projects
  • UIUC Seat/Suspension altered to slide out

4
Project Bids Possible Modifications
  • Bid 1 Hoisting Mechanism
  • Utilization of a pneumatic or otherwise
    mechanical hoisting mechanism to move wheelchair
    from ground to vehicle bed
  • Bid 2 Controls Modification
  • Integration of existing gas and brake control
    pedals into an apparatus designed to be operated
    totally by hand

5
Project Bids Possible Modifications (continued)
  • Bid 3 Wheelchair Integration
  • Modification of the Gator to allow the wheelchair
    to travel up a ramp and act as the drivers seat
  • Bid 4 Bed Modification
  • Modification of bed to raise and lower in order
    to place the wheelchair (via hoisting mechanism)
    below the bed, causing no loss of available
    loading space

6
Project Bids Possible Modifications (continued)
  • Bid 5 Storage Rack
  • Addition of a storage rack somewhere along the
    body of the Gator, allowing storage of the
    wheelchair with no loss of cargo space
  • Bid 6 Wheelchair Modification
  • Modification of existing wheelchair design to
    include a removable seat, allowing seat to be
    moved into position as a drivers seat

7
Project Bids Possible Modifications (continued)
  • Bid 7 Controls Kit
  • Design of a modified controls system that can be
    added onto existing Gator design as a kit to be
    sold separately
  • Bid 8 Roll Over Protective Structure
  • (ROPS) addition of a roll bar to protect
    passengers as well as facilitate the entrance of
    the vehicle by handicapped persons through the
    use of handles on the structure

8
New Action Items
  • Continued contact with Bobby and other John Deere
    personnel to facilitate web conferencing with
    teams at other schools.
    Responsibility Gary Twedt
  • Continued updating of webpage with relevant
    documents. Responsibility Gary
    Twedt

9
New Action Items (continued)
  • Contact Handicapped Driver Services, Inc. for
    information and advice on incorporating
    wheelchairs as the driver seat on the Gator
    vehicle. Responsibility Ben Spivey
  • Contact wheelchair company through contacts in
    order to possibly obtain free equipment to use
    and test with. Responsibility Ben Spivey

10
New Action Items (continued)
  • Investigate preliminary design possibilities for
    implementation of steering wheel-controlled gas
    and brake pedals.
    Responsibility Josh Ebeling
  • Compile information into weekly progress report.
    Responsibility Josh Ebeling

11
New Action Items (continued)
  • Investigate preliminary design possibilities for
    wheelchair hoisting mechanism.
    Responsibility Mike Reno and James June