Title: Demand Bidding at FINGRID, Finland
1Demand Bidding at FINGRID, Finland
- PLMA/IEA International Symposium on Demand
Response - Southgate Towers Hotel, New York City
- September 9-10, 2003
- Fingrid Oyj
- Power System Operation Planning
- Jarno Sederlund
- jarno.sederlund_at_fingrid.fi
- www.fingrid.fi
2FINGRID IN THE NORDIC ELECTRICITY MARKET-
Finnish System Operator in brief -
NORDEL GRID (A JOINT NORDIC GRID)
- Started operations on 1 September 1997
- Owns 99.5 per cent of the Finnish main grid and
all the major interconnections - A total of 14,000 kilometres of transmission
lines and 100 substations - Number of transmission customers 100
- Number of personnel 210 (31.12.2002)
- Turnover EUR 273 million
- Profit for the financial year EUR 39 million
- Balance sheet total EUR 1,379 million
- Consumption in Finland in 2002 84 TWh
- Peak load (winter 2002/2003) 13 920 MW
FINGRID OYJ TRANSMISSION GRID
3RESERVES- Overview in Nordic countries -
4DISTURBANCE MANAGEMENT- Maintaining of reserves -
- Fingrid is responsible for the maintenance of
reserves that are needed in the Finnish power
system according to Nordic grid dimensiong rules - Power system has to withstand any single fault
(N-1) - Maintaining of reserves is largely based on
purchased services - Disconnectable loads are used as reserve in the
event of disturbance situations in the same way
as reserve capacity of power plants
5DEMAND BIDDING AT FINGRID- Markets/Participants -
- Fingrid has signed contracts with process
industry's large customers on disconnectable
loads - Metal industry (steel works and furnaces)
- Forest industry (groundwood plants and mechanical
pulping plants) - Chemical industry (electrolyses)
- The unit size of disconnectable load varies
between 15 - 60 MW - The needed amount of disconnectable loads are
contracted with a competitive bidding procedure
on yearly bases - Additional loads can be obtained from reserve
owners on weekly basis
6DISCONNECTABLE LOADS- Techincal and functional
terms -
- Loads are disconnected from the grid by
- frequency sensitive relays (instantaneous
disturbance reserve) - manually within 15 minutes, when asked by Fingrid
(fast disturbance reserve) - Loads can also be used as system protection
scheme or in peak load situations to release
production capacity - Fingrid has the right to obtain information from
loads - day-specific forecasts of the reserve volumes for
the following calendar day - real time status data and active power
measurements of the resource to Fingrid's
SCADA/EMS
7DISCONNECTABLE LOADS- Contracts and costs -
- Contractual terms are equal and agreement model
voluntary to all participants - Payments are settled in accordance with
participants offer - The following fees are paid for the reserve
holders (in accordance with participants offer) - hourly fee for the time load has been connected
to the grid (average fee EUR 0.3 per MWh) - energy compensation for disconnection (average
fee EUR 350 per MWh) - The total volume of contract loads is
approximately 400 MW - Contracts are made with 6 industrial enterprices
- Fingrid's annual costs are approximately MEUR 1.8
-
8DISCONNECTABLE LOADS- Experiences and future
plans -
- Activation of loads in year 2002
- as instantaneous disturbance reserve 3 times
(frequency under 49.6 Hz) - Participants have chosen loads so that
disconnection does not interrupt significantly
normal operation - Future plans
- explore futher possibilities to utilize loads
e.g. in counter trades - increase the number of potential loads and
participants (now 6 companies and 18 pcs loads)
9DISCONNECTABLE LOADS- Summary -
- Fingrid can utilize disconnectable loads as
- instantaneous reserve in frequency disturbances
- same way as gasturbines in disturbances
- system protection scheme in certain problem areas
- in peak load situations
10- Further information
- www.fingrid.com