PMP Workshop - PowerPoint PPT Presentation

1 / 19
About This Presentation
Title:

PMP Workshop

Description:

PMP Workshop. Project Time Management. What is Project Time Management? ... Sample PMP. Certification Questions. PMP Workshop ... Source: PMP Exam Prep ... – PowerPoint PPT presentation

Number of Views:1763
Avg rating:3.0/5.0
Slides: 20
Provided by: mads1
Category:

less

Transcript and Presenter's Notes

Title: PMP Workshop


1

PROJECT TIME MANAGEMENT
By Marvin Adsuara Doo Cheol Park Takaaki
Koshino MBA Class of July 2005
2
What is Project Time Management?
  • Project Time Management
  • - focuses on the constrains and overall project
    objectives associated with developing schedule.
  • - one of knowledge areas including the processes
    required to ensure timely completion of the
    project.

3
Process Groups Time Mgmt Activities
4
1. Activity Definition
- identifying the specific activities that must
be performed to produce the various project
deliverables.
5
2. Activity Sequencing
- identifying and documenting interactivity
dependencies.
6
3. Activity Duration Estimating
- estimating the number of work periods that will
be needed to complete individual activities.
7
4. Schedule Development
- analyzing activity sequences, activity
durations, and resource requirements to create
the project schedule.
8
5. Schedule Control
- controlling changes to the project schedule.
9
Task Dependency Types
10
Precedence Diagramming Method (PDM)
  • Activities are represented by boxes
  • Arrows show relationships between activities
  • More popular than ADM method as used by PM
    software
  • Better at showing different types of dependencies
  • In PDM, finish-to-start is the most common
    relationship

11
Activity Diagramming Method (ADM)
  • Uses arrows to represent activities
  • Connects activities with nodes
  • Uses only finish-to-start dependencies
  • May require dummy activities to define
    relationships

12
Schedule Development
  • Fast Tracking
  • Performing critical path tasks in parallel and
    riskier than crashing
  • Eg,.Design is half finished and start coding
  • Crashing
  • Analyze cost and schedule trade-offs
  • Determine most compression for least cost
  • Crash the tasks that cost the least first,
    focusing on minimizing project cost

13
Schedule Development
  • CPM (Critical Path Method)
  • Calculates deterministic early and late start
    and finish date
  • Single estimate
  • Focus of CPM is on calculating float
  • Slack (Float)
  • The amount of time a task can be delayed
    without delaying the project
  • LF-EF or LS-ES , EFESDuration,
    LSLF-Duration
  • Activity A LF 15, EF 5
  • LF EF 15 5 10

14
Schedule Development
  • PERT (Program Evaluation and Review Technique)
  • PERT differs from CPM in that it uses the
    distributions mean instead of the most likely
    estimate used in CPM
  • Expected mean value P4(L)O/ 6
  • PERT is seldom used today, but very popular for
    cost estimating obtaining MEAN and standard
    deviation
  • Critical Path
  • Tasks with zero floats, path with longest duration

15
Sample PMP Certification Questions
16
Q1. The estimate for a task is O 3 days, P 7
days, M 4 days. What is the standard deviation
of the task? A. 5/6 of a day B. 2/3 of a day C. 1
½ days D. 5 2/3 days
Source PMP Exam Prep by Rita Mulcahy
17
  • Q2. You are the project manager for a new project
    and have figured out the following dependencies
  • Task 1 can start immediately and has an estimated
    duration of 3 weeks
  • Task 2 can start after Task1 is completed and has
    an estimated duration of 3 weeks
  • Task 3 can start after Task 1 is completed and
    has an estimated duration of 6 weeks
  • Task 4 can start after Task 2 is completed and
    has an estimated duration of 8 weeks
  • Task 5 can start after task 4 is completed and
    after Task 3 is completed . This task takes 4
    weeks.
  • What is the duration of the critical path?
  • A. 18.5 weeks
  • B. 19 weeks
  • C. 20 weeks
  • D. 18 weeks

Source PMP Exam Prep by Rita Mulcahy
18
Q3. A project has three critical paths. Which of
the following BEST describes how this affects the
project? A. It makes it easier to manage B. It
increases the project risk C. It requires more
people D. It makes it more expensive
Source PMP Exam Prep by Rita Mulcahy
19
Q4. You are taking over a project and determine
the following Task B has an early finish of day
3, a late finish of day 6, and an early start of
day 2. Task L is being done by a hard-to-get
resource. The CPI is 1.1 and the SPI is 0.8.
Based on the information above, what would you be
most concerned about? A. Float B. Resources C.
Cost D. Schedule
Source PMP Exam Prep by Rita Mulcahy
Write a Comment
User Comments (0)
About PowerShow.com