Title: Reflections on A Decade with Alternative Project Delivery On Texas Construction Projects
1Reflections on A Decade with Alternative Project
Delivery On Texas Construction Projects
- Progress, Problems, and the Future
Curt Martin Construction Resolutions,
LLC Houston, Texas Curt_at_Construction-Resolutions.c
om Curt_at_Construction-Counsel.com
2Overview Current Status
- Vertical public construction has
- Choice in construction delivery methods
- and
- Discretion in choosing contractor / CM
3A Brief History
- 1995 Choices (SB 1)
- 1997 Structure (SB 583)
- 1999 Modest changes (SB 669)
- 2001 Cities, counties and River authorities (SB
510) - 2003 Navigation districts, ports, toll roads
and turnpikes (HB 3028) - 2003 TxDOT may use CDAs) (HB 3588)
41995 SB 1
- Discretion allowed!
- Choose Method of Procurement
- Use Qualifications-Based Selection
- Applied to K-12 Schools and some higher ed
facilities
51995 SB 1
- Methods of Procurement allowed
- Design / Build (Bridging)
- Construction ManagerAgent
- Construction Manager-at-Risk
- Selection through Competitive Sealed Proposals
- Selection through Competitive Bidding
61995 SB 1
- Schools could use various procurement methods
upon finding that this method provided Best
Value. - But beyond that there was little guidance.
71997 SB 583
- Added Universities
- Provided guidance
- Described how procurement was to be done for each
delivery method - Identified criteria that could be used in
selection - Required user to identify and publish criteria
for selection
81999 SB 669
- More refinement
- Clarified delegation of selection
- Clarified process of CM _at_Risk receiving sub bids
- Strengthened requirement for publishing selection
criteria
9 2001 SB 510
- Extended Alt. Del. Procurement authority to
- Cities
- Counties
- River Authorities
- Excluded Alt. Del. Procurement from
- Highways, water supply projects, other
horizontal construction
10 2003 HB 3028
- Extended Alt. Del. Procurement to
- Ports (for certain work)
112003 HB 3588
- Authorized TxDOT use of Comprehensive
Development Agreements (CDAs)
12What History Tells Us
- Demand for Alternative Delivery continues to
expand - Guidelines needed on how to use these systems
- Some minor adjustments required
13Current status
- Available Alternative Delivery Methods
- CM agent
- CM at risk
- Competitive sealed proposals
- Job order contracting
- Design build
- Competitive bidding
14Current Issues
- Following procedures?
- Transparency
- Standards for Construction Managers?
- Can other procurement methods be used?
- Extension of D/B to Horizontal
- Inter-local Agreements
- Job Order Contracting
15Job Order Contracting
- Ed. Code 44 governs all procurement
- Allows Procurement via
- Competitive bidding
- Competitive sealed proposals
- Request for proposals
- Catalog purchase
- Interlocal contract
- Design/Build contract
- Construction Management
- Job Order Contracting
16Job Order Contracting
- Ed. Code 44 governs all procurement
- Allows Procurement via
- Competitive bidding
- Competitive sealed proposals
- Request for proposals
- Catalog purchase
- Interlocal contract
- Design/Build contract
- Construction management
- Job order contracting
17JOC Controversy
GISD to Build 8,000,000 Middle School Renovation
using Job Order Contracting
18JOC Controversy
HISD Creates JOC Contracts for 20 Regions Across
Texas
19JOC Controversy
HISD arranges Inter-Local agreement with Texas
Assn. of School Boards (TASB)
20JOC Controversy
(TASB) provides HISD JOC to Galveston ISD
21JOC Controversy
Citizens Group Protests Judge issues
Preliminary Injunction
STOP
22JOC Controversy
23JOC Controversy
- Can JOC be procured through Interlocal
Agreements?
24Other Controversies
- Criteria not published
- Criteria not followed
- Rankings not made public
- Improper delegations
- Construction management
- Who?
- What role?
252005 HB 2525
- Consolidation of statutes
- Consistency between various statutes
- Expansion of CM at risk and CSP to infrastructure
- Delegation of authority
- HB 2525 passed both houses, vetoed
26What We Have Learned from History (2)
- Interest in Alternative Delivery Systems
continues / increases - With discretion comes abuse
- Need vigilance, transparency, accountability
272007
- Son of 2525
- Expand Design/Build to horizontal construction
- Attack on indemnification for sole negligence
28Continued Goals
- Consistency
- Low transactional costs
- Transparency
- Enforceability
- Design and construction as service