Title: TP Assembly Update


1
TP Assembly Update
  • Robert Bradford
  • University of Rochester
  • MINERnA Group Meeting
  • January 16, 2008

2
MINERnA space allocation
3
Outfitting Wideband
  • Ethernet has been installed
  • Electrical work on mapper cage and control area
    complete.
  • Submitted request for phone service to south end
    of hall.
  • General cleanup underway.
  • Furnishings delivered.
  • Magnetic coils being removed.

4
Pb Adhesion
  • Have tested 3 epoxies
  • Heigl
  • Scotchweld 2216
  • Resinlab EP1290
  • All 3 handled well (no odors)
  • Scotchweld and Resinlab bonded best.
  • Resinlab
  • Available in cartridges
  • Inexpensive
  • Holding up well in week-long bucket test
  • Have ordered Resinlab for the TP.

5
Other
  • Have completed large tooling/equipment orders
  • One vendor shipped to Robert Bradford National
    Lab
  • Small parts arrived yesterday
  • Scintillator lifting jig
  • Design complete
  • Waiting for quotes
  • Will have scintillator prep tables built once
    template arrives from WM.
  • Have met with Alignment to discuss survey needs.

6
Module Mapper
  • Cone design complete
  • 32o/64o cone angle
  • R. Flight soliciting quotes
  • Al and Kelly
  • Have begun to cable the mapper
  • Lots of small parts coming through Johns Shop
  • Al has made modifications to DAQ.
  • Target date of Feb. 4 to commission DAQ.

7
T2K Mapper
  • Have identified and hired programmer
  • Jason Hiltner
  • Will meet with him on Monday
  • Have final quotes on device
  • ShopBot
  • 25K
  • Will arrange to meet vendor once funding cleared
    up.
  • Sending cone information to Stony Brook this
    afternoon.

8
TP Installation
  • Working with Dave Boehnlein on system to track
    assembly configuration
  • Bar code label scheme
  • Labels scanned as modules assembled/TP installed
  • Data input through CRL.
  • Dave is authoring forms.
  • Will test with Pb scans.