Title: LIQUID ARGON CALORIMETERS LAr Calorimetry: Status Summary
1LIQUID ARGON CALORIMETERSLAr Calorimetry Status
Summary
- ATLAS Plenary Meeting 25-June-2004
- H. Oberlack
- MPI für Physik, Munich
2CONTENT
- Cryostats Integration of Calorimeters
- Beam tests
- Electronics
- Installation Commissioning
- Conclusion
3 M o d u l e P r o d u c t i o n C o m p l e t e
!!! A l l W h e e l s A s s e m b l e d !!!
4Barrel Cryostat
-
- Both wheels inserted.
- Final welding of cold vessel successfully
completed. - Solenoid integration finished.
- Decided on slower cool-down to safe-guard e.m.
detectors - Gas N2 instead of liquid N2 through heat
exchanger. - Cool-down started end April, completed beginning
June. - Argon transfer to the cryostat started Tuesday,
8-June, - completed three days later.
- Purity of LAr in the cryostat 0.15 ppm O2
equivalent
5Cool-down Barrel Cryostat
4.5 K/day
6First Look at HV after Filling
Presampler
Calorimeter
7Commissioning Tests of Barrel
AA wheel CC wheel Tests -TPA -LC -RRcalib -R
EFreflectometry
w31
w30
w29
w28
July
HV AC
HV on C (18 days)
HV on A
TPA on A
FEC on C
LC on A
RLC on C
w34
w33
w35
w32
August
HV on A (20 days)
TPA on C
R on A
REF on AC
8FORWARD CALORIMETERS
- FCAL-C
- Calibration run of complete FCAL-C completed
2003. - Modules inserted into cryostat can.
- Integration
- Insertion into cryostat end July-04.
- FCAL-A
- All three modules complete.
- Cold test successfully done Jan/Feb-04.
- Insertion into cryostat can in Sep-04..
9Integration of End-Cap C
10End-Cap Cryostats Trial FCAL Insertion
- Successful trial insertion and extraction
- Sag as expected
- FCAL-A can available for detector
assembly/insertion
11END-CAP CRYOSTAT C
-
- ECPS, EMEC, HEC1 and HEC2 inserted and
commissioned. - FCAL to be inserted in July-04.
- Decided for slower cool-down to safe-guard e.m.
detectors. - Due to the larger mass of the EC calorimeters a
different procedure has to be applied than in
the barrel - Blow He gas into the EC cryostat.
- Use H1 system.
12END-CAP CRYOSTAT A
- Large Omega seals and cold cover modified.
- Pressure test at 3.4 b mechanically successful.
- Large seals leaked at 2.6/2.8 b, when 2.7 b
required. - No leak of large seals at 2.7 b during cold test.
- Influx of heat into FCAL measured to be lt 10 W /
m2 - (ltlt 80 W / m2, the critical value)
13Welding the End-Cap Cryostats
- The EC cryostats were not tight at 3 bar (working
pressure 2.7.bar) - We decided to weld the cold vessels of the
cryostats shut. - Start welding ECC July-04
- Start cool-down Sep-04
14Welding the End-Cap Cryostats
Welded frame
- Welding test probe
- Hydraulic pressure test
- 4 bar for 2 hours
- 10 bar, no visible deformation
- 37 bar leak opening, pin hole at a stop/start on
the weld. No crack. Front band deformed. - Accepted.
15Integration End-Cap A
ECA PS All modules installed. HV tested. All
o.k.
EMEC A wheel fully assembled. Wheel rotated. HV
checks done. Globally better than ECC.
16BEAM TEST ACTIVITIES
- Test beam runs of series modules
- EMB Finished in 2002. 4 / 32 modules tested.
NIM - EMEC Finished in 2002. 3 / 16 modules tested.
NIM - HEC Finished in 2001. 24 / 128 modules tested.
NIM - FCAL Beam calibration in June/Sep-03 3 / 6
modules. - Combined test beams
- EMEC / HEC Finished in Aug/Sep-2002. NIM
- EMEC / HEC / FCAL Data taking.
- EMB / Tilecal ATLAS Data taking.
17FRONT-END ELECTRONICS - 1 -
- DMILL
- SCA Production yield slightly higher than
expected. - Combined wafers for analog chips OK
- Combined wafers for digital chips OK
- DSM
- SCA controller and a few smaller chips produced.
- Being tested.
- Rad.tolerant prototypes of all boards exist.
- All FE electronics boards passed PRRs in
March-04. - Production started, still on schedule.
18FRONT-END ELECTRONICS - 2-
- LV PS
- 2 prototypes received, met specs.
- PRR successful mid Mar-04.
- Order passed
- First articles expected Nov/Dec-04
- Series delivery (4 / week) starting end Mar-05.
- Delivery dates are critical for installation on
barrel in truck position. - Negative voltage regulators
- Version six works and is rad.tolerant. Go ahead
given. - Series chips expected soon.
19FRONT-END ELECTRONICS - 3 -
- Complete test of full FE crate
- One half crate with all boards in test 14 FEBs,
controller, calibration, tower builder,monitoring.
- Started in Oct-03, ended in Mar-04.
- Lots of test data (1 TB). Very active data
analysis. - Problems with event synchronization via optical
links, traced to TTC system, modified FEB to
include QPLL. - Use FE electronics now in H8 beam test.
- Prepare to measure noise in barrel cryostat with
FE electronics.
20OPTICAL READOUT LINKS
- System PRR successful
- Transmitter OTx
- Production started.
- PAR held, recommended small modification.
- New preseries of 100 pieces in production.
- Receiver ORx
- Production started.
- Preseries of 100 pieces in production.
- Optical cables
- Architecture of cable defined.
- To be ordered when length received from TCn.
21BACK-END ELECTRONICS
- ROD system
- Agreement with Tilecal for common ROD production.
- No hardware changes since a few months.
- Build entire system within CORE frame.
- System test of the back-end electronics (BE Crate
test) - Location LAr-EMF at Point1.
- Defined tasks and responsibles.
- BEC test delayed by several months due to delay
of hardware. - Serious problem to get online software going.
- BEC test in full operation now.
- Shifted ROD PRR to 25-June-04.
22CABLES SERVICES
- Trigger cables
- Arrived in LAr-EMF.
- One connector per cable.
- Company to put 2nd connector in USA15 after
installation - Progress on other cables / services is slow.
- Becoming critical, need to speed up and order.
- Logical error
- TCn asks LAr to provide cables for cable
campaign. - We need to order, but TCn cannot provide cable
lengths. - Order 25 more and accept extra cost???
23Installation Overview
- LAr system installation
- 3 Cryostats TCn (LAr)
- Cryogenics CC team
- Electronics Front-End LAr
- Electronics Back-End LAr
- Cables Services TCn (LAr )
- Installation system established and working
- Most baseline decisions taken
- First installation operations starting in
July-04.
24Electronics Installation
- FE installation on cryostat front faces (Truck
and IP positions) - Most coordination and organisation needed due to
strong interconnection of different boards and
systems. - Establish common installation team (FEIC).
- FE installation document agreed.
- Task lists established, time and manpower
estimates agreed. - BE installation in USA15
- Document similar to FE note close to completion.
- WP tables in advanced state
- Time and manpower estimates, assignment of
responsibilities. - Installation ASSO 12/13-July-04 together with
Tilecal.
25Installation Time Line
- Mid-End July Water manifolds and supports in
lower half tilecal - End October Transport and lowering of LAr
Barrel - October TCn Installation of LAr cables from
USA15 to cavern - December Tilecal Barrel completed
- December Continue infrastructure including
FE crates - December January
- Prepare FE boards in EMF
- Prepare readout system for USA15 in EMF
- Prepare test needs in UX15 and USA15
- water, readout, temporary Truck-USA15
cables, DCS - February Lower a full set for one FE Crate
incl. LVPS - April (?) FEC 2 (when 1 is running
more boards and LVPS available), ... FEC
i1 ... - End August Barrel moves to IP
26CONCLUSIONS
- Module production and wheel assembly completed.
- Barrel and ECC cryostats filled with wheels.
- Integration of calorimeter wheels in ECA is in
full swing. - Cold tests of barrel under way, cold test of ECC
cryostat being prepared. - Slower cooling procedures for barrel and end-cap
detectors being implemented. - Implications for ATLAS under investigation.
- Front-end electronics production started after
successful PRR. - Back-end electronics with slow start for BEC
test. PRR this afternoon. - Installation of calorimeter system into ATLAS
preparing for Installation ASSO.