LIQUID ARGON CALORIMETERS LAr Calorimetry: Status Summary - PowerPoint PPT Presentation

1 / 26
About This Presentation
Title:

LIQUID ARGON CALORIMETERS LAr Calorimetry: Status Summary

Description:

Argon transfer to the cryostat started Tuesday, 8-June, completed three days later. ... We decided to weld the cold vessels of the cryostats shut. Start welding ... – PowerPoint PPT presentation

Number of Views:56
Avg rating:3.0/5.0
Slides: 27
Provided by: hober
Category:

less

Transcript and Presenter's Notes

Title: LIQUID ARGON CALORIMETERS LAr Calorimetry: Status Summary


1
LIQUID ARGON CALORIMETERSLAr Calorimetry Status
Summary
  • ATLAS Plenary Meeting 25-June-2004
  • H. Oberlack
  • MPI für Physik, Munich

2
CONTENT
  • Cryostats Integration of Calorimeters
  • Beam tests
  • Electronics
  • Installation Commissioning
  • Conclusion

3

M o d u l e P r o d u c t i o n C o m p l e t e
!!! A l l W h e e l s A s s e m b l e d !!!
4
Barrel Cryostat
  • Both wheels inserted.
  • Final welding of cold vessel successfully
    completed.
  • Solenoid integration finished.
  • Decided on slower cool-down to safe-guard e.m.
    detectors
  • Gas N2 instead of liquid N2 through heat
    exchanger.
  • Cool-down started end April, completed beginning
    June.
  • Argon transfer to the cryostat started Tuesday,
    8-June,
  • completed three days later.
  • Purity of LAr in the cryostat 0.15 ppm O2
    equivalent

5
Cool-down Barrel Cryostat
4.5 K/day
6
First Look at HV after Filling
Presampler
Calorimeter
7
Commissioning Tests of Barrel
AA wheel CC wheel Tests -TPA -LC -RRcalib -R
EFreflectometry
w31
w30
w29
w28
July
HV AC
HV on C (18 days)
HV on A
TPA on A
FEC on C
LC on A
RLC on C
w34
w33
w35
w32
August
HV on A (20 days)
TPA on C
R on A
REF on AC
8
FORWARD CALORIMETERS
  • FCAL-C
  • Calibration run of complete FCAL-C completed
    2003.
  • Modules inserted into cryostat can.
  • Integration
  • Insertion into cryostat end July-04.
  • FCAL-A
  • All three modules complete.
  • Cold test successfully done Jan/Feb-04.
  • Insertion into cryostat can in Sep-04..

9
Integration of End-Cap C
10
End-Cap Cryostats Trial FCAL Insertion
  • Successful trial insertion and extraction
  • Sag as expected
  • FCAL-A can available for detector
    assembly/insertion

11
END-CAP CRYOSTAT C
  • ECPS, EMEC, HEC1 and HEC2 inserted and
    commissioned.
  • FCAL to be inserted in July-04.
  • Decided for slower cool-down to safe-guard e.m.
    detectors.
  • Due to the larger mass of the EC calorimeters a
    different procedure has to be applied than in
    the barrel
  • Blow He gas into the EC cryostat.
  • Use H1 system.

12
END-CAP CRYOSTAT A
  • Large Omega seals and cold cover modified.
  • Pressure test at 3.4 b mechanically successful.
  • Large seals leaked at 2.6/2.8 b, when 2.7 b
    required.
  • No leak of large seals at 2.7 b during cold test.
  • Influx of heat into FCAL measured to be lt 10 W /
    m2
  • (ltlt 80 W / m2, the critical value)

13
Welding the End-Cap Cryostats
  • The EC cryostats were not tight at 3 bar (working
    pressure 2.7.bar)
  • We decided to weld the cold vessels of the
    cryostats shut.
  • Start welding ECC July-04
  • Start cool-down Sep-04

14
Welding the End-Cap Cryostats
Welded frame
  • Welding test probe
  • Hydraulic pressure test
  • 4 bar for 2 hours
  • 10 bar, no visible deformation
  • 37 bar leak opening, pin hole at a stop/start on
    the weld. No crack. Front band deformed.
  • Accepted.

15
Integration End-Cap A
ECA PS All modules installed. HV tested. All
o.k.
EMEC A wheel fully assembled. Wheel rotated. HV
checks done. Globally better than ECC.
16
BEAM TEST ACTIVITIES
  • Test beam runs of series modules
  • EMB Finished in 2002. 4 / 32 modules tested.
    NIM
  • EMEC Finished in 2002. 3 / 16 modules tested.
    NIM
  • HEC Finished in 2001. 24 / 128 modules tested.
    NIM
  • FCAL Beam calibration in June/Sep-03 3 / 6
    modules.
  • Combined test beams
  • EMEC / HEC Finished in Aug/Sep-2002. NIM
  • EMEC / HEC / FCAL Data taking.
  • EMB / Tilecal ATLAS Data taking.

17
FRONT-END ELECTRONICS - 1 -
  • DMILL
  • SCA Production yield slightly higher than
    expected.
  • Combined wafers for analog chips OK
  • Combined wafers for digital chips OK
  • DSM
  • SCA controller and a few smaller chips produced.
  • Being tested.
  • Rad.tolerant prototypes of all boards exist.
  • All FE electronics boards passed PRRs in
    March-04.
  • Production started, still on schedule.

18
FRONT-END ELECTRONICS - 2-
  • LV PS
  • 2 prototypes received, met specs.
  • PRR successful mid Mar-04.
  • Order passed
  • First articles expected Nov/Dec-04
  • Series delivery (4 / week) starting end Mar-05.
  • Delivery dates are critical for installation on
    barrel in truck position.
  • Negative voltage regulators
  • Version six works and is rad.tolerant. Go ahead
    given.
  • Series chips expected soon.

19
FRONT-END ELECTRONICS - 3 -
  • Complete test of full FE crate
  • One half crate with all boards in test 14 FEBs,
    controller, calibration, tower builder,monitoring.
  • Started in Oct-03, ended in Mar-04.
  • Lots of test data (1 TB). Very active data
    analysis.
  • Problems with event synchronization via optical
    links, traced to TTC system, modified FEB to
    include QPLL.
  • Use FE electronics now in H8 beam test.
  • Prepare to measure noise in barrel cryostat with
    FE electronics.

20
OPTICAL READOUT LINKS
  • System PRR successful
  • Transmitter OTx
  • Production started.
  • PAR held, recommended small modification.
  • New preseries of 100 pieces in production.
  • Receiver ORx
  • Production started.
  • Preseries of 100 pieces in production.
  • Optical cables
  • Architecture of cable defined.
  • To be ordered when length received from TCn.

21
BACK-END ELECTRONICS
  • ROD system
  • Agreement with Tilecal for common ROD production.
  • No hardware changes since a few months.
  • Build entire system within CORE frame.
  • System test of the back-end electronics (BE Crate
    test)
  • Location LAr-EMF at Point1.
  • Defined tasks and responsibles.
  • BEC test delayed by several months due to delay
    of hardware.
  • Serious problem to get online software going.
  • BEC test in full operation now.
  • Shifted ROD PRR to 25-June-04.

22
CABLES SERVICES
  • Trigger cables
  • Arrived in LAr-EMF.
  • One connector per cable.
  • Company to put 2nd connector in USA15 after
    installation
  • Progress on other cables / services is slow.
  • Becoming critical, need to speed up and order.
  • Logical error
  • TCn asks LAr to provide cables for cable
    campaign.
  • We need to order, but TCn cannot provide cable
    lengths.
  • Order 25 more and accept extra cost???

23
Installation Overview
  • LAr system installation
  • 3 Cryostats TCn (LAr)
  • Cryogenics CC team
  • Electronics Front-End LAr
  • Electronics Back-End LAr
  • Cables Services TCn (LAr )
  • Installation system established and working
  • Most baseline decisions taken
  • First installation operations starting in
    July-04.

24
Electronics Installation
  • FE installation on cryostat front faces (Truck
    and IP positions)
  • Most coordination and organisation needed due to
    strong interconnection of different boards and
    systems.
  • Establish common installation team (FEIC).
  • FE installation document agreed.
  • Task lists established, time and manpower
    estimates agreed.
  • BE installation in USA15
  • Document similar to FE note close to completion.
  • WP tables in advanced state
  • Time and manpower estimates, assignment of
    responsibilities.
  • Installation ASSO 12/13-July-04 together with
    Tilecal.

25
Installation Time Line
  • Mid-End July Water manifolds and supports in
    lower half tilecal
  • End October Transport and lowering of LAr
    Barrel
  • October TCn Installation of LAr cables from
    USA15 to cavern
  • December Tilecal Barrel completed
  • December Continue infrastructure including
    FE crates
  • December January
  • Prepare FE boards in EMF
  • Prepare readout system for USA15 in EMF
  • Prepare test needs in UX15 and USA15
  • water, readout, temporary Truck-USA15
    cables, DCS
  • February Lower a full set for one FE Crate
    incl. LVPS
  • April (?) FEC 2 (when 1 is running
    more boards and LVPS available), ... FEC
    i1 ...
  • End August Barrel moves to IP

26
CONCLUSIONS
  • Module production and wheel assembly completed.
  • Barrel and ECC cryostats filled with wheels.
  • Integration of calorimeter wheels in ECA is in
    full swing.
  • Cold tests of barrel under way, cold test of ECC
    cryostat being prepared.
  • Slower cooling procedures for barrel and end-cap
    detectors being implemented.
  • Implications for ATLAS under investigation.
  • Front-end electronics production started after
    successful PRR.
  • Back-end electronics with slow start for BEC
    test. PRR this afternoon.
  • Installation of calorimeter system into ATLAS
    preparing for Installation ASSO.
Write a Comment
User Comments (0)
About PowerShow.com