Title: Operational Readiness Review


1
Readiness ReviewCourse
ORR Team Leader Detailed Responsibilities Mod 6
2
Learning Objectives
  • Describe the ORR Team Leaders detailed
    activities and considerations associated with
    planning and conducting an ORR/RA including

Authorization Authority Plan of Action Event
Dates Draft Implementation Plan Team Selection
Criteria Team Level of Experience Team
Qualification Requirements
Logistics/Planning Management of the
Team Interfaces - Oversight Entities -
Startup Authority - Facility
Contractor Necessary Briefings/Meetings ORR Final
Report
3
Readiness Review Process
6 Months Prior to RR
1 Year Prior to RR
4
Team Leader Roles and Responsibilities
  • Reference DOE-HBK-3012-2003 for specific details
    on Team Leaders Roles and Responsibilities
  • Assemble team,
  • Begin developing implementation plan,
  • Logistics - required room, equipment, security,
    training,
  • Assemble document request,
  • Arrange briefings,
  • Arrange tours.

5
Team Selection Criteria
  • Team Members and size of Team derived from the
    POA Breadth and Scope
  • Selected by the Team Leader
  • DOE O 425.1C Requirements
  • Technical competence
  • Assessment experience/training
  • Independence in the Review area.
  • Sample Forms Available
  • Standard (3006-00) and DOE/NNSA Web Pages.
  • Other Qualities
  • Writing skills
  • Team player
  • Big Picture . . .

6
Plan of Action
  • Is your writing guide used to develop your
    Implementation Plan
  • Names you as the Team Leader
  • Defines the Breadth and Scope of the RR
  • Defines prerequisites
  • Provides a proposed start date
  • Used to Identify Team Members and Functional
    Areas to Review
  • Approved by DOE/NNSA Authorization Authority for
    both CORR/CRA and DOE/NSA ORR/RA.

7
Team Member Selection, Typical Functional Areas
  • Engineering Support
  • Fire Protection
  • Occupational Safety (IH/IS)
  • Management
  • Configuration Management
  • Procedures
  • Radiation Protection
  • Procedures
  • Level of Knowledge
  • Operations
  • Safety Envelope
  • DOE Organization
  • Training and Qualification
  • Quality Assurance
  • Software Quality Assurance
  • Criticality Safety
  • Environmental Protection and Waste Management

13
8
Implementation Plan
  • Your responsibility . . . You draft it and
    approve it!
  • You and the team prepare it
  • You resolve/consider comments with oversight
    organizations (internal, external)
  • What do you commit to do, to answer the question
    - are the criteria within the POA scope met?

9
Team Leader Briefings and Meetings
  • Daily Team Meeting
  • Shares information, contractor, DOE/NNSA . . .
  • Team Synergy.
  • Closeout Briefing
  • Key Issues - Pre-Start Findings
  • Startup Recommendation
  • Finding Closure Recommendation.
  • Follow-up As Required

10
Managing the Interfaces
  • Interfaces
  • Oversight Entities (DNFSB, EH)
  • Authorization Authority
  • Local DOE/NNSA Points of Contact
  • Facility Contractor
  • Good Practices
  • Full Access - Best Practice
  • No Secrets, be Open!
  • Must be Fully Informed Brief periodically
  • Initiate the Communication

11
Authorization Authority
  • AA is your Boss
  • Final Readiness Review report is for his/her
    decision
  • Line decision maker for scope changes.
  • Close Interface
  • Regular briefings during review
  • Immediate notification of major issues
  • Formally direct you to commence the Readiness
    Review
  • For CORR/CRA, a Senior Line Manager will fill
    this role.

12
ORR Final ReportKeys to Success
  • Your Product!
  • Suggested Format in Standard/website
  • Select and provide an example to Team.
  • Unclassified preferred as required . . .
  • Key Elements (Order Requirements)
  • Order Compliance as per POA
  • Lessons Learned
  • ISMS Statement
  • Your Recommendation
  • Addressed to Authorization/Startup Authority.

13
ORR Final ReportKeys to success
  • Plan to complete before team leaves site . . .
  • Define Timeline and expectations to team early .
    . .
  • Provide example formats early-forms Summary . .
    .
  • Develop the report skeleton and background early
    . . .
  • Arrange for Admin support to edit, format,
    collate . . .
  • Push daily input to individual forms . . .
  • Emphasize timely factual accuracy . . .
  • Describe the review/approval process to the team
    . . .
  • Continuous classification review of product . . .

14
Team Leader (TL) Lesson Learned
  • TL not qualified Selection criteria guidance
    not detailed enough (e.g., independence,
    experience)
  • TL not assigned soon enough (POA timely
    approval)
  • TL does not communicate expectations to team with
    enough lead time
  • TL does not communicate drill/evolution
    expectations to facility
  • Site access for team not gained ahead of time
  • Logistic needs not communicated to site with
    enough lead time
  • TL does not tailor CRADs based on Pre-Visit or
    Team not at Pre-Visit, or no Pre-Visit)
  • CRAD assigned to TL .

15
If the Review Results are not Successful
  • Significant team decision. Facts must support
  • Sleep on it Confront team to defend conclusion.
  • Discuss situation and options with Authorization
    Authority (Senior Contractor Management).
  • Two Options
  • Suspend the Review. Interim Report including
    what was done and areas not done.
  • Final report for completed Functional Areas (FA)
  • High level discussion and findings for incomplete
    FAs.
  • Terminate the Review. Report results with basis
    for repeat of entire ORR/RA.

16
Final Thoughts
  • Be Flexible with Start Date!
  • You work for the AA
  • IP is yours and the teams
  • Be Alert to Recommend Pre-Event Activities
  • Emergency Preparedness (EP) Drills
  • Integrated Equipment Tests.
  • Critical Team Interface Issue . . .
  • You Must be Proactive . . .

17
Questions
18
Readiness ReviewCourse
ORR Team Leader Detailed Responsibilities Mod 6
19
Learning Objectives
  • Describe the ORR Team Leaders detailed
    activities and considerations associated with
    planning and conducting an ORR/RA including

Authorization Authority Plan of Action Event
Dates Draft Implementation Plan Team Selection
Criteria Team Level of Experience Team
Qualification Requirements
Logistics/Planning Management of the
Team Interfaces - Oversight Entities -
Startup Authority - Facility
Contractor Necessary Briefings/Meetings ORR Final
Report
20
Readiness Review Process
6 Months Prior to RR
1 Year Prior to RR
21
Team Leader Roles and Responsibilities
  • Reference DOE-HBK-3012-2003 for specific details
    on Team Leaders Roles and Responsibilities
  • Assemble team,
  • Begin developing implementation plan,
  • Logistics - required room, equipment, security,
    training,
  • Assemble document request,
  • Arrange briefings,
  • Arrange tours.

22
Team Selection Criteria
  • Team Members and size of Team derived from the
    POA Breadth and Scope
  • Selected by the Team Leader
  • DOE O 425.1C Requirements
  • Technical competence
  • Assessment experience/training
  • Independence in the Review area.
  • Sample Forms Available
  • Standard (3006-00) and DOE/NNSA Web Pages.
  • Other Qualities
  • Writing skills
  • Team player
  • Big Picture . . .

23
Plan of Action
  • Is your writing guide used to develop your
    Implementation Plan
  • Names you as the Team Leader
  • Defines the Breadth and Scope of the RR
  • Defines prerequisites
  • Provides a proposed start date
  • Used to Identify Team Members and Functional
    Areas to Review
  • Approved by DOE/NNSA Authorization Authority for
    both CORR/CRA and DOE/NSA ORR/RA.

24
Team Member Selection, Typical Functional Areas
  • Engineering Support
  • Fire Protection
  • Occupational Safety (IH/IS)
  • Management
  • Configuration Management
  • Procedures
  • Radiation Protection
  • Procedures
  • Level of Knowledge
  • Operations
  • Safety Envelope
  • DOE Organization
  • Training and Qualification
  • Quality Assurance
  • Software Quality Assurance
  • Criticality Safety
  • Environmental Protection and Waste Management

13
25
Implementation Plan
  • Your responsibility . . . You draft it and
    approve it!
  • You and the team prepare it
  • You resolve/consider comments with oversight
    organizations (internal, external)
  • What do you commit to do, to answer the question
    - are the criteria within the POA scope met?

26
Team Leader Briefings and Meetings
  • Daily Team Meeting
  • Shares information, contractor, DOE/NNSA . . .
  • Team Synergy.
  • Closeout Briefing
  • Key Issues - Pre-Start Findings
  • Startup Recommendation
  • Finding Closure Recommendation.
  • Follow-up As Required

27
Managing the Interfaces
  • Interfaces
  • Oversight Entities (DNFSB, EH)
  • Authorization Authority
  • Local DOE/NNSA Points of Contact
  • Facility Contractor
  • Good Practices
  • Full Access - Best Practice
  • No Secrets, be Open!
  • Must be Fully Informed Brief periodically
  • Initiate the Communication

28
Authorization Authority
  • AA is your Boss
  • Final Readiness Review report is for his/her
    decision
  • Line decision maker for scope changes.
  • Close Interface
  • Regular briefings during review
  • Immediate notification of major issues
  • Formally direct you to commence the Readiness
    Review
  • For CORR/CRA, a Senior Line Manager will fill
    this role.

29
ORR Final ReportKeys to Success
  • Your Product!
  • Suggested Format in Standard/website
  • Select and provide an example to Team.
  • Unclassified preferred as required . . .
  • Key Elements (Order Requirements)
  • Order Compliance as per POA
  • Lessons Learned
  • ISMS Statement
  • Your Recommendation
  • Addressed to Authorization/Startup Authority.

30
ORR Final ReportKeys to success
  • Plan to complete before team leaves site . . .
  • Define Timeline and expectations to team early .
    . .
  • Provide example formats early-forms Summary . .
    .
  • Develop the report skeleton and background early
    . . .
  • Arrange for Admin support to edit, format,
    collate . . .
  • Push daily input to individual forms . . .
  • Emphasize timely factual accuracy . . .
  • Describe the review/approval process to the team
    . . .
  • Continuous classification review of product . . .

31
Team Leader (TL) Lesson Learned
  • TL not qualified Selection criteria guidance
    not detailed enough (e.g., independence,
    experience)
  • TL not assigned soon enough (POA timely
    approval)
  • TL does not communicate expectations to team with
    enough lead time
  • TL does not communicate drill/evolution
    expectations to facility
  • Site access for team not gained ahead of time
  • Logistic needs not communicated to site with
    enough lead time
  • TL does not tailor CRADs based on Pre-Visit or
    Team not at Pre-Visit, or no Pre-Visit)
  • CRAD assigned to TL .

32
If the Review Results are not Successful
  • Significant team decision. Facts must support
  • Sleep on it Confront team to defend conclusion.
  • Discuss situation and options with Authorization
    Authority (Senior Contractor Management).
  • Two Options
  • Suspend the Review. Interim Report including
    what was done and areas not done.
  • Final report for completed Functional Areas (FA)
  • High level discussion and findings for incomplete
    FAs.
  • Terminate the Review. Report results with basis
    for repeat of entire ORR/RA.

33
Final Thoughts
  • Be Flexible with Start Date!
  • You work for the AA
  • IP is yours and the teams
  • Be Alert to Recommend Pre-Event Activities
  • Emergency Preparedness (EP) Drills
  • Integrated Equipment Tests.
  • Critical Team Interface Issue . . .
  • You Must be Proactive . . .

34
Questions