Title: RISK ALLOCATION IN CONSTRUCTION PROJECTS


1
RISK ALLOCATION IN CONSTRUCTION PROJECTS
  • Lorman Education Services
  • Eileen M. Diepenbrock
  • William A. Lichtig
  • Jay C. Davison, AIA
  • September 2, 2004

2
ALLOCATING RISKS OF DESIGN ERRORS
3
The Dilemma for the Owner
  • Owner Contractor
  • Implied warranty of plans
  • Responsibility for deficiencies
  • Recovery for extra work

4
The Dilemma for the Owner
  • Owner Designer
  • No warranty of plans
  • Breach of contract
  • Professional negligence

5
The Dilemma for the Owner
  • Professional Negligence is .. the failure
    to exercise the skill, knowledge, and care
    ordinarily possessed by members of the profession

6
The Dilemma for the A-E
  • Are design fees adequate to produce high-quality
    documents?

7
Pressures on Design Fees
  • Fee scales established in industry, often by
    agencies
  • Increasing complexity of work
  • Increasing number of tasks and specialties
  • Increasingly litigious atmosphere in the
    construction industry

8
Pressures on Firm Profitability
  • Traditionally a low-profit business
  • Increasing salary pressure
  • Shortage of qualified personnel
  • Increasing complexity of work

9
Would Increasing Design Fees Result in
Higher-Quality Documents?
  • Workload could be calibrated to available
    professional staff
  • Outside peer reviews could be initiated (and paid
    for) by A-E
  • More budget could be devoted to CA
  • Would owners have to compete for qualified
    design firms?

10
Completeness of Design Documents
  • What is shown/specified?
  • What is implied intent?
  • What is good enough?

11
Communication 1
  • Design documents attempt to communicate the
    intent of the designer
  • Bids represent the contractors understanding of
    that intent
  • RFIs represent confusion
  • Change orders represent misunderstanding

12
Communication 2
  • Has the quality of designers communication
    changed?
  • Do different contractors understand and respond
    at different levels?
  • How might this communication be improved?

13
Trends in Document Preparation
  • Show/specify an item only once
  • Do not over-detail
  • Reduce required submittals
  • Use alternative media (e.g. photos)
  • Transfer design responsibility where possible to
    do so

14
Areas With High Potential for Problems to Arise
  • Or equals and substitutions
  • Changing trade standards
  • Proprietary specifications
  • Complete and operating system

15
Constructability Reviews as a Means of Improving
the Quality of Construction Documents
16
What Means Constructability Review?
  • Coordination, conflict, completeness (Quality
    Control)
  • Code compliance
  • Program compliance
  • Standards compliance
  • Constructability
  • Value engineering

17
Quality Control Review
  • When documents 95 complete to avoid
    duplication of efforts
  • By whom another design professional (peer)
  • Why improve quality of documents to reduce
    potential misunderstanding

18
Code Compliance Review
  • When early in design development
  • By whom another design professional or an
    individual trained in code enforcement, e.g.
    licensed inspector
  • Why avoid having to modify documents at the
    last minute to comply

19
Program Compliance Review
  • When at the end of design development
  • By whom the person who developed the program
  • Why to ensure that the owner is getting all the
    items they asked for

20
Standards Compliance
  • When After specifications are well developed
    (usually in CD phase)
  • By whom the author of the standards or the
    departments that helped develop them
  • Why to ensure that the designer is specifying
    the materials and systems the owner wants

21
Constructability Review
  • When CD phase, after specifications are
    reasonably well developed
  • By whom a contractor or other construction
    professional with actual hands-on experience
  • Why to uncover details that might be difficult
    or costly to build, and materials and systems
    that are proprietary, or difficult to procure.

22
Value Engineering
  • When early and throughout design
  • By whom a certified value engineering
    professional
  • Why to save cost without comprising quality or
    design intent

23
Important Issues
  • Cost vs. benefit
  • Backcheck did review items get addressed?
  • Is this an additional service to the designer?
  • Who assumes design liability?
  • Potential bid delays

24
Owner Liability Issue
  • If a review identifies potential problems in the
    documents and appropriate corrections are not
    made, is the owners liability increased?

25
Shifting the Risk of Design Errors to the
Contractor
26
Pre-Bid Review of Construction Documents
  • Owners warranty of plans
  • Contractors obligation to review
  • How to allocate the risk

27
Pre-Bid Review
  • Time
  • Design
  • Bidding
  • Information Available
  • Owner-furnished
  • Publicly available
  • Contractor-generated
  • Contract Requirements

28
Level of Review
  • Reasonable review given thepurpose of pre-bid
    review
  • Patent or Obvious
  • Not required to second guess owner/designer

29
Coordination and Lay-Out Drawings
  • What are they
  • When
  • Who prepares
  • Purpose

30
Striking a Balance
  • Designers must accommodate identified systems
  • Contractors must coordinate identified systems

31
Resolving Conflicts
  • Not enough space
  • Routing conflicts with structuralcomponents
  • Components conflict with each other
  • Design deficiency?
  • Coordination error?

32
Composite Drawing of Typical Lab
33
Corrected Composite Drawing of Typical Lab
34
Field Verification
  • What is required
  • When
  • Examples
  • Existing construction
  • New construction

35
Financial Responsibility
  • No additional compensation
  • Affirmative liability to owner
  • Level of knowledge
  • Contract allocation

36
Who Should Bear the Risks?
37
EVERY PROJECT COSTS A CERTAIN AMOUNT
  • Costs of Design
  • Costs of Construction
  • Costs of Risks

38
How Can the Risks be Mitigated?
  • Owner Keeps the Risks and Tries to Get the Best
    A/E and Contractor
  • Owner Gives the Risks to the A/E
  • Owner Shifts the Risks as Much as Possible to the
    Contractor

39
HOW CAN THE PARTIES WORK TOGETHER TO COLLECTIVELY
REDUCE THE RISK?
40
ALLOCATING RISKS OF UNEXPECTED SITE CONDITIONS
41
TYPE I DIFFERING SITE CONDITION
  • Site Condition Which Differs Materially From That
    Indicated in Contract Documents
  • Contract Documents Indicate Type of Conditions to
    be Expected
  • Representation Must Differ Materially from Actual
    Conditions Encountered
  • Contractor Must Have Reasonably Relied on
    Contract Representations to its Detriment

42
TYPE II DIFFERING SITE CONDITION
  • Unknown Site Condition Which Differs Materially
    From That Reasonably Expected as Inherent in the
    Nature of the Work to be Performed
  • Examine Contract Documents Closely for
    Disclaimers and Definition of Contract
    Documents
  • Are site investigation studies provided for
    information only?

43
TYPE II DIFFERING SITE CONDITION
  • Heavy Burden of Proof
  • What was actually known about the site
  • Why condition encountered was unusual
  • The DSC is materially different from what is
    considered ordinary

44
THE DIFFERING SITE CONDITION CLAUSE
  • RISK ON OWNER
  • Lower Bids
  • Equitable Adjustment
  • No Restrictions
  • RISK ON CONTRACTOR
  • Higher Bids
  • May Not Be Allowed On Public Projects

45
SHIFTING RISK DISCLAIMERS
  • Disclaiming Geotechnical Information From the
    Contract
  • Disclaiming the Accuracy of Plans and
    Specifications
  • Disclaiming Inferences Drawn From Existing
    Conditions
  • Combination of all

46
DISCLAIMING GEOTECHNICAL INFORMATION FROM
CONTRACT
  • Intent is to Prevent Type I Claim
  • Disclaimer is Frequently Enforced
  • Examine Disclaimer Carefully
  • General Disclaimer is Insufficient
  • Disclaimer Must Caution Against Reliance on Data

47
DISCLAIMING WARRANTY OF ACCURACY
  • May be Restricted by the Spearin Doctrine
  • May be Restricted by Positive Misstatement of
    Conditions
  • May be Restricted by Statutes (Public Projects)

48
DISCLAIMING WARRANTY OF ACCURACY
  • Enforceable if Makes Reliance on Data
    Unreasonable
  • Effective to Disclaim Contractors Subjective
    Interpretation of Data

49
DISCLAIMING INFERENCES FROM SITE INFORMATION
  • Effective to Shift Risk of Conclusions from Data
  • Limits Implied Warranty of Data
  • Assumes Accuracy of the Date Itself

50
SHIFTING RISK SITE INSPECTION CLAUSES
  • No Apparent Restrictions
  • Enforceable to Waive Conditions Reasonably
    Discoverable
  • Failure to Comply can Cause Loss of Claim

51
SITE INSPECTION CLAUSES
  • Apparent Conflict with Differing Site Condition
    Clause
  • Reasonableness Standard Contractor is obligated
    to discover those conditions apparent through a
    reasonable investigation
  • Does not Excuse Material Misrepresentation

52
REASONS FOR DENIAL OF CLAIM
  • Failure to prove differing site condition
  • Failure to follow contract procedures regarding
    differing site conditions
  • Failure to comply with site investigation clause
  • Failure to consider effects of weather
  • Failure to document and prove damages due to
    claimed differing site condition

53
ALLOCATING RISKS OF CONSTRUCTION ERRORS AND DELAYS
54
Role of the Architect
55
Role of the Architect
  • Inspection vs. Review
  • Submittals
  • Substitutions and or equals
  • Conflicts in the documents
  • Authority to make changes

56
Role of the Architect Inspection vs. Review
  • Insurance implications
  • Liability for safety
  • Projects where inspection is required (e.g.
    schools, hospitals)
  • Level of site visits fee will support

57
Role of the Architect Submittals
  • Timeliness of submittal and speed of review
  • Purpose of submittals
  • Insurance implications
  • Legal effect of review
  • Incomplete submittals
  • Schedule implications of rejection

58
Role of the Architect Substitutions and or
equals
  • What is the difference?
  • Substitutions masquerading as equals
  • Why accept substitutions?
  • Collateral risks of substitutions
  • Who pays for review of substitutions?

59
Role of the Architect Conflicts in the Documents
  • Errors vs. Omissions
  • Common types of errors
  • Order of precedence clauses
  • How conflicts are addressed
  • Costs of errors and omissions
  • Third party (e.g. CM) involvement

60
Role of the Contractor
61
Means and Methods
  • How project will be built
  • Sequence
  • Schedule
  • Crew size
  • Techniques
  • Equipment

62
Risk to Owner
  • Specifying means and methods
  • Not allowing contractor to use selected MM
  • Examples
  • Excavation equipment
  • Sequencing

63
Risks to Contractor
  • Selected MM will be properly rejected
  • Example Thin brick
  • Selected MM will not work
  • Selected MM will be costly

64
Following/Interpreting the Contract Documents
  • Evolution of pre-bid obligations
  • Contract clauses seek to shift risk to
    contractor
  • I dont care if its not shown, you should have
    known it was there.

65
Contractors Obligation
  • Premise All contract documentswill contain
    errors and omissions
  • Contractor typically responsible for
  • Known EO
  • Should have known EO

66
Evaluating Responsibility Omitted Work
  • Contract structure
  • Necessity of work
  • Ability to price when bidding
  • Obviousness of omission
  • Scope
  • Price

67
Evaluating Responsibility Errors
  • Contract structure
  • Magnitude of error
  • Contractors experience
  • Efforts undertaken to evaluate plans
  • If discovered, when
  • Ability to discover earlier

68
Effect of Inspections
  • Purpose
  • Effect
  • Contract clauses
  • Practicality

69
Effect of Payment
  • Contract provisions
  • Effect

70
Role of the Owner
71
Role of the Owner
  • Owners responsibility for delay depends upon
  • The facts
  • The effect on the critical path

72
Role of the Owner
  • Delay in delivery of materials
  • Owner-furnished materials
  • Owner-specified materials

73
Role of the Owner
  • Owner-initiated changes
  • Effect on critical path
  • Excessive number of changes

74
Role of the Owner
  • Response time to questions
  • Specify in contracts
  • Failure to respond shifts risk

75
Role of the Owner
  • Payment
  • 30 days generally
  • Late payments bad for everyone
  • Contractor deprived of revenue
  • Owner at risk

76
Role of the Owner
  • Coordination of multiple primes is for
    sophisticated and risk-tolerant owners only!
  • Management of consultants supervision is
    required

77
Alternative Delivery Methods
78
Agency Construction Management
79
Agency Construction Management
Owner
CM firm
Architect
Contractor
Engineers
Subcontractors
Contractual
Communication
80
Agency CM
  • CM can oversee scheduling, cost control,
    constructibility review, pre-construction
    management, bidding, construction project
    management

81
Agency CM
  • Who can provide CM services
  • On private sector, can be, but do not have to be,
    performed by licensed contractors, civil
    engineers and architects as long as not acting as
    licensed contractor, engineer or architect
  • On public sector, must be performed under the
    direction and control of a licensed architect,
    registered professional engineer or licensed
    general contractor

82
Role of the Construction Manager
  • Distributing information
  • Interpreting contract documents
  • Identifying problems and ensuring timely
    resolution
  • Assigning responsibility for problems and
    consequent liability for the owner
  • Authority to make changes and responsibility for
    changes
  • Exposure to liquidated damages

83
Agency Construction Management Pros and Cons
  • Pro works well for large, complex projects
    requiring significant oversight and coordination
  • Pro useful when owner is not sophisticated about
    construction
  • Con adds level of coordination, potential
    increased time and paperwork

84
CM at Risk
85
CM at Risk
Owner
CM firm
Architect
Contractor
Engineers
Subcontractors
Contractual
Communication
86
CM at Risk
Owner
CM firm
Trade Contractor
Trade Contractor
Trade Contractor
Trade Contractor
Trade Contractor
Trade Contractor
Trade Contractor
Trade contractor
Architect
Trade Contractor
Trade Contractor
Engineers
Trade Contractor
Trade Contractor
Trade Contractor
Trade Contractor
Trade Contractor
Contractual
Trade contractor
Communication
87
Design-Build Contracting
88
Design-build
Owner
Design-builder
Architect
Contractor
Engineers
Subcontractors
Contractual
Communication
89
Design-Build Contracting
  • Use of a single entity to both design and
    construct
  • Cost-effectiveness
  • Design cost savings
  • Avoid the owners dilemma of being caught between
    design and construction teams
  • Potentially better overall price

90
Design-Build Contracting Legal Issues
  • License issues
  • Warranty issues
  • Public sector issues

91
Design-Build Contracting License Issues
  • Design-builder must have contractors license and
    design-professionals license or registration, or
    have properly licensed or registered design
    professional in charge of design
  • Contractors can subcontract design to design
    professional
  • Joint ventures check assets and insurance

92
Design-Build Contracting Warranty Issues
  • Potentially negates owners implied warranty of
    plans and specs
  • Owners warranties typically disclaimed by
    contract
  • Contractors participation in design can give
    rise to implied warranties to owner

93
Design-Build Contracting Public Sector Issues
  • Competitive bidding requirements
  • Subcontractor listing laws
  • Risk of differing site conditions likely still is
    on the owner Public Contract Code 7104

94
Best Value Procurements
95
Best Value Procurements
  • Goal and process
  • Process involves competition, negotiation and
    evaluation of factors beyond price
  • Beneficial for complex and infrastructure
    projects
  • More widely used on federal projects than state

96
Lease-Leaseback
97
Lean Construction
98
Lean Construction
  • Background
  • Taichi Ohno (Toyota)
  • The dilemma
  • The inspiration
  • The outcome

99
Lean Construction
  • Toyota Production System
  • Highly specify content
  • Yes-No direct connections for requests and
    responses
  • Pathways are simple and direct
  • Pursue perfection, under guidance of teacher

100
Lean Construction
  • James Womack Lean Thinking
  • Define value from the customers view
  • Identify the value stream
  • Make the value creating steps flow
  • Downstream process pull from upstream
  • Continually strive towards perfection

101
Five Big Ideas
102
Lean Construction
  • Last Planner System

103
(No Transcript)
104
Questions / Comments
105
The End
106
Role of the Construction Manager Distributing
Information
  • Hub of the Wheel
  • Handling of various documents, e.g. submittals
    and RFIsvalue added?
  • Tracking of speed of response by all parties
  • Early warning of cost issues

107
Role of the Construction Manager Interpreting
Contract Documents
  • Authority
  • Responding to RFIs
  • Assigning responsibility for problems
  • Design Liability

108
Role of the Construction Manager Identifying
Problems
  • Authority
  • Methods of resolution
  • Liability for outcome

109
Role of the Construction Manager Assigning
Responsibility
  • Authority (agency)
  • Financial legal implications
  • Liability for outcome

110
Role of the Construction Manager Authority to
Make Changes
  • Authority (agency)
  • Financial legal implications
  • Liability for outcome

111
Role of the Construction Manager Exposure to
Liquidated Damages
  • Responsibility authority for schedule