Title: Project Management A Tool For ATO Success
1Project ManagementA Tool For ATO Success
Presented by Pat A. Eigbe, PMP Office of
Innovations and Solutions, ATO-P February 18, 2004
2Briefing Outline
- Project Management (PM) as a Tool
- Project Management Terminology
- PM Relationship to other Disciplines
- Project Management Processes
- Project Management Tools Techniques
- Summary/Conclusion
- Questions
3Project Management as a Tool
- Minimize Fire Drills
- Efficient Use of Resources
- Develop Better Metrics
- On-time and On-budget Product Delivery
- Apply Lessons Learned
- Better Communications Between Stakeholders
- Make Proactive Decisions
4Communications
Understanding our Environment
Tell the Marine to secure a building
they will kill everybody and point guns at the
building.
Tell the Air Force to secure a building
they will drive everybody out and lease the
building to the highest bidder.
Tell the Army to secure a building
they will surround the building and point guns at
the house.
Tell the Navy to secure a building
they will turn off all the lights, lock up the
house, and go home.
5Project Management (PM) Terms
- Project - A temporary endeavor undertaken to
create a unique product or service. - ATOP or VSCS - Project has a specific purpose
with a start and an end date. - Project Management - the Application of
Knowledge, Skills, Tools, and Techniques to
Project Activities to Meet Project Requirements.
6Project Management Terms II
- Program - A group of related projects managed in
a coordinated way. Programs usually include an
element of ongoing activity. - CPDLC, SMA, URET CCLD, pFAST,as FFP1
- PM Tools Development as part of Program
Management - A Project/Program Manager (PM) - The Individual
Responsible for Managing a Project/Program.
7Project Management Terms III
- Work Breakdown Structure (WBS) - A
deliverable-oriented grouping of project elements
that organizes and defines the total scope of the
project. Each descending level represents an
increasingly detailed definition of a project
work.
8Project Management Terms IV
- FAA standard wbs1-0.ppt
- WBS Dictionary 3.1
- Requirement to use FAA Standard WBS Mandatory
9Project Management Terms V
- Deliverable Tangible, verifiable work
product/service. - Work Package A deliverable at the lowest level
of the work breakdown structure. A work package
may be divided into activities. - Activity - Work elements with expected duration,
cost, resources that may be subdivided into
tasks.
10Project Management Terms VI
- Stakeholder Individuals or Organizations that
will be Impacted by the Outcome of a Project. - OBS An Organizational Chart Relating Work
Packages to Organization Units. - Responsibility Matrix Relates Organization
Structure to WBS Ensures that each Element of
the Projects Scope is Assigned to a Responsible
Individual(s).
11Project Management Relationship to Others
Disciplines
The PMBOK
Project Management Knowledge and Practice
General Management Knowledge and Practice
Application Area Knowledge and Practice
Figure is conceptual and overlaps are NOT
proportional
12Systems Engineering/PM Relationship I
- PM Needs SE for
- Integrated PM System Design Implementation
- Requirements for HW and SW Tools
- SE Needs PM for
- Planning and tracking
- Managing Resources
- PM System Designer Must Understand both
- SE Not Necessary for PM Practitioners
13Systems Engineering/PM Relationship - II
- Risk Management
- PM - Schedule, Cost Technical/Quality
- SE Compatibility of Components of a System or
Sub-System - Quality Management
- PM - Process for Producing the Product
- SE - Ensure Product Meets the Technical or
Quality Specifications
14Systems Engineering/PM Relationship - III
- Configuration Management
- PM - Ensure Integrity of Schedule and System for
Schedule Management - SE - Ensure Integrity of the System as Designed
- Change Management
- PM - Changes to Project Scope
- SE - Changes to System Requirement
- Measurement
- PM Program cost schedule performance
- SE Technical Performance
15PMI Certification
- What is PMP
- What PMP is not
- PMP Value to Holder Employer
- PMP Certification Process link visit
- http//pm.act.faa.gov
16PM Process Groups
Project Information Flow
17PM Process Flow
18Initiation Processes
- Identify project and sponsor
- Appoint Project Manager
- Train team on
- Project Management Process
- Project Plan (PMIP)
- Develop Program Directive to Include
- WBS that Covers the Scope
- High-level Milestones
- Budget resources
19Planning Processes I
- Identify Life Cycle approach
- Evolutionary (AMS 6101, Section 2.2)
- Incremental
- Waterfall
- Risk Management plan
20Planning Processes II
- Get approval for Program Directive
- Identify quality standards - use specs, IEEE,
ISO, PMBOK - Organizational structure
- Communications - who needs, what
- Acquire human resources for projects
21Planning Processes III (Schedule Development)
- Update Decompose WBS
- Identify activities
- Sequence
- Estimate duration
- Estimate cost
- Allocate resources to work packages
- Baseline schedule
22Planning Processes IV
- Risk management detail
- Identification
- Analysis
- Response
- Procurement
23Implementation/Execution Processes
- Use the PMIP to execute project activities
- Assess Technical Performance to assure product
acceptance - Distribute project information
- Make purchases
- Develop team skills/competencies
- Develop a Configuration Management plan
24Performance Measurement
- Variances
- Performance Indices
- Schedule performance Index (SPI)
- Cost performance Index (CPI)
- Earned Value Management System (EVMS)
25Earned Value Management System Highlights
- What is EVMS
- Planning for EVMS
- Tracking Analysis
- Elements of EV Analysis
- Project Cost Schedule Forecasting
- EV Reporting
26Earned Value Management System (EVMS) - I
- EV - Tool for Measuring Project Performance
- Integrates Cost, Scope Schedule measurements
- Compares work actually accomplished to work
planned - EV is an Early Warning System
- Helps management make proactive decisions to keep
projects on course
27Earned Value Management System (EVMS) - II
- Involves Calculating 3 key Elements
- Budget - BCWS
- Actual Cost - ACWP
- Earned Value/Physical Progress - BCWP
- Basis for variance analysis
28Planning for EVMS - I
- Create a work breakdown structure
- Organize work into discrete work packages and
activities - Allocate a budget to each of the activities
- Develop a schedule and Assign resources
- Must include all project work in the schedule
- Establish the Project Baseline
29Planning for EVMS - II
- Award performance credit for physical complete
- 0-100
- Short duration tasks lt 160 hours
- EV is Zero until activity is complete
- 50-100
- Duration less than 600 hours
- 50 at start of activity 50 at completion
30Planning for EVMS - III
- Interim milestone
- Duration less than 600 hours
- Based on completed milestone for task
- Level of Effort (LOE)
- Long duration consistent tasks
- Difficult to measure - no deliverables
- Measured by duration of time used e.g. 10 weeks
support is 50 complete at 5 weeks
31Tracking Analysis
- Each update cycle/Reporting Period
- Obtain physical complete for each task
- Calculate EV for each task
- Sum up EV for all tasks as project EV
- Calculate actual expenditure for actual work
completed during the period - Compare the Cumulative EV to Actual expenditure
32Elements of EV Analysis - I
- Performance indices relate value of work
performed to dollar spent. e.g. CPI 0.65 means
that for every dollar spent, actual value of the
work performed is 0.65. - Cumulative CPI used to forecast project cost at
completion - Cumulative SPI used to forecast project
completion date
33Elements of EV Analysis - II
- Cost Variance - Difference between budgeted cost
an activity actual cost of that activity - CV EV - ACWP
- Schedule Variance - Difference between scheduled
completion actual completion of an activity - SV EV - BCWS
34Elements of EV Analysis - III
- SPI EV/Planned Value
- SPI gt 1.0, Project Schedule performing as
planned or better - SPI lt 1.0, Project not performing as planned -
needs help
35Elements of EV Analysis - IV
- CPI EV/Actual Cost
- CPI gt 1.0, Project Cost performing as planned or
better - CPI lt 1.0, Project Cost not performing as planned
- needs help - Over/Under Budget CAC - BCWS
36Tracking Analysis
- Each update cycle/Reporting Period
- Obtain physical complete for each task
- Calculate EV for each task
- Sum up EV for all tasks as project EV
- Calculate actual expenditure for actual work
completed during the period - Compare the Cumulative EV to Actual expenditure
37Project Cost Schedule Forecast Methods
- Estimate at Completion (EAC) is total cost to
complete an activity, work package, or a project
expressed as - EAC Actuals-to-date Estimate to complete
(ETC) - Cost EAC BAC/CPI
38EV Reporting
- Interpret the output of EV calculations
- Take corrective action as necessary
- Recommend corrective action as necessary
39Control Processes I
- Coordinate and control changes to project
- scope/requirements
- schedule
- budget
- Monitor and manage product quality
- Measure progress and report performance
40Control Processes II
- Monitor and control risks
- keep track of identified risks
- monitor residual risks
- identify new risks
- ensure execution of risk plans
- assess effectiveness in reducing risk
41Closing Processes
- Close out contracts
- Resolve any outstanding issues
- Document lessons learned
- Evaluate project
- Archive all project documents
42Conclusion
- Defined Frequently used PM Terminologies
- Discussed Objectives of Adopting Project
Management Principles. - Discussed PM Processes, Tools Techniques
- Discussed EVMS Overview
- Questions
43References
- Project Management Institute (PMI), 2000. A Guide
to the Project Management Body of Knowledge (the
PMBOK Guide) - Stratton R. W., 1999. Improving SPI and CPI
Calculations on LOE Heavy Programs, Proceedings
of the 30th Annual PMI Seminars Symposium - Fleming and Koppeman, 1996. Earned Value Project
Management. - Ibbs W Reginato J., 2002. Quantifying the Value
of Project Management - Kerzner H, 2003. Project Management A Systems
Approach to Planning, Scheduling, and
Controlling. - FAST _at_ http//fast.faa.gov/wbs/wbssec.htm
44Questions/Need Help?http//pm.act.faa.gov
- Pat A. Eigbe, PMP
- Ext. 5-7857
- patrick.eigbe_at_faa.gov