Title: PIKES PEAK-AMERICA
1PIKES PEAK-AMERICAS MOUNTAIN
2ON TOP OF THE WORLDSNOW REMOVAL AT PIKES PEAK
3APWA SNOW AND ICE CONFERENCE
- PRESENTERS
- JACK GLAVAN, MANAGER
- CURT SCRIVNER, SENIOR EQUIPMENT OPERATOR
- KENT IMEL, SENIOR EQUIPMENT OPERATOR
4APWA SNOW AND ICE CONFERENCE
- BACKGROUND
- EROSION AND SEDIMENTATION CONTROL PROJECT
- SNOW PLOWING OPERATIONS
5PIKES PEAK-AMERICAS MOUNTAIN
- Operates the Pikes Peak Highway and the
associated visitor facilities including the
Summit House, Glen Cove Inn and Crystal Reservoir
Gift Shop, and the recreational corridor (hiking,
picnic grounds, and interpretive trail) under a
Term Special Use Permit issued by the U.S. Forest
Service. - Revenue is generated from tollgate revenue and
concessionaire fees. These fees provide Visitor
and Ranger Services, Highway maintenance and
construction, Facility maintenance and
construction, and Interpretive and Educational
Services, and special project funding such as the
Erosion and Sedimentation Control Project.
6Special Use Permit
- First issued by USFS in 1948
- Current Permit 1990-2020
- Highway and all structures are owned by the
United States under the administration of the
USFS (except for Maintenance Garage and Crystal
Reservoir Visitors Center) - Permit is not transferable holder may sublease
use of land, concessions, etc. - All income derived from permitted uses must be
used for funding the Operating Plan and Budget.
7(No Transcript)
8EROSION AND SEDIMENTATION CONTROL PROJECT
- DESIGN 1995 2004
- CONSTRUCTION 2001 - PRESENT
9Erosion Sedimentation Control Project
- Background In April 1999 the City of Colorado
Springs signed a Consent Decree to complete the
Erosion and Sedimentation Control Project in
accordance with the approved Clean Water Act 401
Certification. - (City of Colorado Springs is responsible for
fulfilling the terms of the Settlement Agreement
and will not be relieved of this liability even
if the City terminates the permit.) - Funding comes from LART and Pikes Peak Revenues
- In 2009 LART decreased from 800,000 to 190,512
- Revenue of approximately 600,000 from new
concessionaire contract replaced LART funds - Decreased LART will jeopardize completion date
10TABLE 1 SUMMARY OF DESIGN AND CONSTRUCTION
SCHEDULE AND COSTS ( Based upon the
approved Clean Water Act 401 Certification)
- (as of Aug. 9, 2007)
- NOTES
- Final Design Approval is the date that the U.S.
Forest Service approved the plans. - Cost Expended to date Represents costs expended
by Pikes Peak-Americas Mountain for contract
work, work completed by Public Works divisions,
and Pikes Peak Highway staff (Note Costs for
PPH are estimates based upon hours expended). - Design costs include funds spent for design
contractors, subcontractors (surveying and
environmental), and quality control actions or
items, such as testing. - Estimated costs to complete are based upon
Frontier Environmental Services bid for Basins 5
and 6. Basin 7 is estimated based upon
information provided for Basins 5 and 6. There
is no escalation for these costs. Costs based
upon the construction being competitively bid.
11CONSTRUCTION OF SEDIMENT BASIN
12(No Transcript)
13(No Transcript)
14(No Transcript)
15(No Transcript)
16(No Transcript)
17CULVERTS, DITCHES ANDRIPRAP WEIRS
18(No Transcript)
19(No Transcript)
20(No Transcript)
21(No Transcript)
22(No Transcript)
23 24(No Transcript)
25(No Transcript)
26(No Transcript)
27(No Transcript)
28(No Transcript)
29(No Transcript)
30(No Transcript)
31(No Transcript)
32REVEGETATION
33(No Transcript)
34(No Transcript)
35(No Transcript)
36(No Transcript)
37(No Transcript)
38(No Transcript)
39ROAD WIDENING
40ROAD WIDENING VIDEO
41(No Transcript)
42(No Transcript)
43(No Transcript)
44Pikes Peak HighwayPriority Basin No. 3
- Paving of the initial lane (1st lift)
- about 1.6 miles, 115 trucks, 1607 tons
- August 08, 2005
45Paving Basin 3
46(No Transcript)
47Paving of the initial lane and rolling the
asphalt
48Completion of the initial lane
491607 tons of asphalt (about 115 trucks)
50Pikes Peak HighwayPriority Basin No. 4
51Removal of snow and debris adjacent to road PB-4
52Edge of highway and ditch delineation survey
layouts
53Rock debris and snow in ditches
54Reveg mesh not holding up, culvert inlet plugged
with rock/debris
55Reveg matting performance PB-3
56Pikes Peak HighwayPriority Basin No. 4 and Misc
57Inlet area/channel at sediment pond/dam at 8
mile- PB-2
58Outlet areas for spillway and outlet works
sediment pond/dam at 8 mile- PB-2
59Vegetative cover shown on downsteam slope
60Highway base placement, blading, and rolling
61SNOW PLOWING
- CHALLENGES
- PRIORITY
- CREW/EQUIPMENT
62(No Transcript)
63(No Transcript)
64(No Transcript)
65(No Transcript)
66(No Transcript)
67(No Transcript)
68(No Transcript)
69Summit House
70(No Transcript)
71PRIORITY
- OPENING TO VISITORS
- CRYSTAL VISITORS CENTER
- TANDEMS
- TRUCKS W/ SANDERS
- GLEN COVE
- TANDEMS ON PAVED SECTION
- GRADERS OR SNOWBLOWERS
- SWITCHBACKS AND SUMMIT
- GRADERS
- SNOWBLOWERS
72PRIORITY
- CHECKING FACILITIES
- ONE LANE NEEDED
- GLEN COVE
- GRADER
- SUMMIT
- GRADER
73EQUIPMENT
- TANDEM TRUCKS W/ PLOWS (2) AND SANDER (1)
- F-550 W/PLOW AND SANDER
- PICK-UPS W/PLOWS (2)
- SNOWBLOWERS (2)
- MOTORGRADERS (2)
- LOADERS (2)
- W/ BALDERSON BLADE (1)
74(No Transcript)
75(No Transcript)
76(No Transcript)
77(No Transcript)
78(No Transcript)
79(No Transcript)
80(No Transcript)
81 82(No Transcript)
83(No Transcript)
84(No Transcript)
85(No Transcript)
86(No Transcript)
87(No Transcript)
88(No Transcript)
89(No Transcript)
90(No Transcript)
91(No Transcript)
92SNOWBLOWER VIDEO
93(No Transcript)
94(No Transcript)
95(No Transcript)
96(No Transcript)
97(No Transcript)
98(No Transcript)
99(No Transcript)
100(No Transcript)
101(No Transcript)
102(No Transcript)
103(No Transcript)
104(No Transcript)
105(No Transcript)
106(No Transcript)
107(No Transcript)
108(No Transcript)
109(No Transcript)
110SUMMIT VIDEO