Title: KwaZuluNatal Department of Housing


1
KwaZulu-Natal Department of Housing
  • Presentation to the
  • Select Committee on Finance

2
Vision
  • The Vision of the KwaZulu-Natal Department of
    Housing is -
  • Enabling all people to house themselves by
    engaging various institutions and stakeholders in
    the provision of a conducive and enabling
    environment

3
Mission
  • The mission of the department is -
  • To effectively and efficiently manage the
    implementation of National and Provincial Housing
    Programmes in partnership with the relevant role
    players, by developing sustainable human
    settlements characterized by affordable and
    adequate shelter for qualifying citizens in
    KwaZulu-Natal

4
Key Focus Areas
  • The key focus areas of the department are -
  • Rationalisation and restructuring of the
    Department
  • Eradication of slums in KwaZulu-Natal
  • Strengthening governance and service delivery
  • Ensuring job creation through housing delivery
  • Accelerating housing delivery in rural areas
  • Accelerating the hostel redevelopment and upgrade
    programme
  • Completion of all blocked projects by 2007
  • Creating rental / social housing opportunities
  • Building the capacity of Housing stakeholders
  • Promotion of homeownership
  • Provision of housing for vulnerable groups
    including those affected by HIV/AIDS.

5
Review of 2005/06
  • Key achievements by the department during 2005/06
    were -
  • Houses built 24,925
  • Serviced sites completed 19,373
  • Sites transferred 11,322
  • Emergency housing provided 8,658

6
1st Quarter Expenditure
7
1st Quarter Expenditure
  • Planning and Development
  • The slower than expected rate of expenditure is
    as a result of delays in the drafting of
    Municipal Housing Plans and the late delivery of
    IT Network Infrastructure
  • Project Management
  • Delays in the receipt of claims and the accuracy
    of claims from Developers has hampered
    expenditure in this programme.
  • The department has seen the expenditure incurred
    during July and August reverse this trend of
    under expenditure

8
1st Quarter Expenditure
  • Property Management
  • A large portion of the budget of this programme
    relates to the upgrading of rental units and
    hostels, the contracts with the various
    municipalities are currently being finalised and
    this will resolve the under expenditure incurred
    during the 1st quarter
  • The department has terminated the services of the
    service provider for the EEDBS, resulting in
    delays in the programme implementation
  • The department has commenced the process of
    performing this task internally

9
Conditional Grant Expenditure
10
Conditional Grant Expenditure
  • As mentioned above the department has experienced
    challenges with regard to expenditure on the
    Integrated Housing and Human Settlement
    Development Grant including -
  • That Developers have not provided timely and
    accurate expenditure claims
  • This issue has been addressed with the developers
    and during July and August there has been a
    marked improvement in the value of claims received

11
Capacity Constraints
  • The department is in the process of finalising
    its revised organisational structure
  • The restructuring process resulted in a high
    proportion of Project Monitor posts becoming
    vacant
  • The department identified this as a key challenge
    to service delivery and fast tracked the
    appointment of Project Monitors in order to
    prevent adverse effects on service delivery
  • Interviews have been concluded and the new
    appointees will start during September and
    October 2006

12
Capacity Constraints
  • Not all Municipal IDPs include Housing Sector
    Plan for the municipality
  • A programme is being rolled out to assist the
    municipalities to develop these plans
  • Impact of the new Rates Act
  • The Act provides for an exemption for houses
    valued at under R15 000 (the old subsidy amount)
  • Current houses built by the department cost
    between R36 000 and R41 000 excluding land and
    bulk services costs

13
Capacity Constraints
  • Lack of dedicated Housing capacity in
    Municipalities
  • An agreement has been entered into with the
    Flemish Government to provide seed funding for
    the creation of housing components in 25
    Municipalities (linked to Project Consolidate)
  • Determination of Housing Demand
  • Department has developed a Housing Demand
    Database to assist Municipalities to
    scientifically analyse their housing demands

14
Service Level Agreements
  • The department does not enter into Service Level
    Agreements with Developers
  • For each Housing Development a separate Legal
    Contract is entered into
  • The department uses a Tripartite agreement
    between the department, the Developer and the
    Implementing Agent to ensure that the department
    is able to retain control over all aspects of the
    housing delivery cycle
  • The contract sets out timeframes and the
    expectations of the department with regard to the
    development

15
Thank you