Space requirement and hardware needs in PP2, PP3 and USA - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

Space requirement and hardware needs in PP2, PP3 and USA

Description:

... pixel racks already ... allocate max 16 BOCs, 4 crates are needed, 2 racks (7% spare) ... (There are free racks close to the pixel rack: it should be perfect) ... – PowerPoint PPT presentation

Number of Views:31
Avg rating:3.0/5.0
Slides: 16
Provided by: gem79
Category:

less

Transcript and Presenter's Notes

Title: Space requirement and hardware needs in PP2, PP3 and USA


1
Space requirement and hardware needs in PP2, PP3
and USA
  • C.Gemme, P.Sicho, S.Kersten

2
(Many) assumptions
  • Starting from Ver2.4 of Services Estimate
    (Danilo)
  • Main numbers
  • 120 modules, 60 optoboards.
  • Only 1 LV per module (I2A) but up to 2 HV per
    module.
  • Same services as today for the optoboards and
    overall schema.
  • USA15 installation preferred
  • easier maintenance, access and control.
  • Few pixel racks already available.
  • Splitting between two Counting Rooms would need
    more time for installation.
  • Time installation in cavern should be minimized
    (env activation).

3
Assumptions Ver 2.4 2009/01/29
4
Pixel DCS in the pit
5
DAQ crates
  • Requirements
  • One output line 160 Mbits per chip of 20mm x 20mm
    size (present B-layer has 2 DATA output lines,
    overall 160Mbits per module of 16.4mm x 60mm
    size).
  • 8-ways ribbon in and out for each optoboard (2
    modules) -gt Need 60 DATA output 8-ways ribbons
    and 60 TX input 8-ways ribbons.
  • USA15
  • As for the actual b-layer, one BOC per 8 input
    channels and receiving 8 data signal.
  • Then 60 BOCs are needed.
  • As a crate can allocate max 16 BOCs, 4 crates are
    needed, 2 racks (7 spare).
  • They have to sit no too far from the TTC crate
    (Y2905). Delay compensation for trigger cables
    propagated between racks is anyhow possible (do
    not know limit). Have also the doubt that the
    current TTC crate should need to be expanded.

6
PP2 crates
  • Current services
  • The ratio between LV module supplies/LV opto
    supplies is (72)/1.
  • Each regulator board can regulates 16 LVs up to
    14 are used for modules (2LVs per module), 2 for
    optoboards (one is redundant).
  • A PP2 crate serves up to 12 optoboard and 127
    modules.
  • IBL Requirements
  • 120 LV modules to regulate, 60 VVDC LV for the
    optoboard.
  • Ration between Modules and Opto supplies is now
    2/1.
  • Need_at_PP2
  • Need to change the input schema from Counting
    room to accommodate the 60 optoboard supplies.
  • Just assuming that
  • there are 180 LV channels to regulate
  • Each regulator board can regulate 16 channels,
  • Each crate can accommodate 12 boards
  • In principle 2 crates, one per side, should be
    sufficient (7 spare).
  • Not considered the NTC opto boxes (just passive
    PP, not cumbersome)

7
PP2 crates room
Sector 9 (detector side ) Easy access, lot of
space!
Sector 13 (bottom of the detector) Room for a
crate, not very confortable
8
LV PP4
  • Current services
  • In the actual design one LV crate is done which
    one Wiener supply (12ch) that are splitted in
    12x6-7 by a LV PP4. Up to 15 V, 15 A can be
    delivered per output.
  • 48 crates are used to supply 2722LV PP0s. 6
    crates are sitting in one rack.
  • Requirements
  • 120 LV supplies for modules. Higher current
    (2A).
  • USA15 or US15
  • Just assuming that
  • there are 120 LV channels to regulate,
  • LV PP4 splitting factor equal to 4
  • then 30 Wiener channels are needed -gt 3 crates
    (0.6 rack) are sufficient with 6 spare channels.
  • All this is based on existing Wiener crates (a 12
    channel), but there are new crates nearly ready
    which allow a much more dense packing in the rack.

9
PP2 aux PS
  • Current services
  • Some Wiener channels are also needed for the PP2
    controller board n PP2 crates, n controllers, n
    x 2 Wiener channels.
  • Requirements
  • In case 4 PP2 crates are needed, 8 Wiener
    channels should be used.
  • One extra Wiener crate could be installed where
    other PP2 aux PS are located as there is place
    for an another crate there (Y.15-14.A2).
  • No extra space requested!

10
HV PP4
  • Current services
  • One ISEG module has 16 independent floating
    channels each up to 700 V, 4mA max. output. In
    the beginning of the experiment one readout unit
    (6 or 7 detector modules) is supplied by one HV
    channel. PP4 is needed to do the splitting.
  • One rack (four crates) is powering 470 modules.
  • Requirements in USA15 or US15
  • 2120 HV supplies for modules. 240 channels.
  • Assuming no splitting ?240 HV channels -gt15 HV
    modules 2 crates (a 6U).
  • Assuming a splitting factor 4 at PP4 ? 60 HV
    channels ? 4 HV modules 1 HV crate (6U) 1
    HV-PP4 (6U)
  • In both cases 2 6U crates are needed.

11
SCOLink
  • Current services
  • SCOLink provides 4 outputs (signals) to the
    optoboard (Vpin, Viset, Opto_Rst, VVDC) and has
    an Interlock input.
  • 1 SCOlink crate (3U crate) provides 16x signals
    (16 channels).
  • Requirements in USA15 or US15
  • Assuming that the same supplies signal are needed
    for 60 optoboards in the IBL, we should assume 4
    SCOLink 3U crates (64 channels). 7 spare.

LU
  • Current services
  • LUs receive NTC module and opto temperatures and
    provide interlock to the relevant PS.
  • One LU crate (3U) has 84 NTC corresponding
    inputs.
  • Requirements in USA15 or US15
  • To connect 120 module and 60 optoboards, we would
    need 3 LU crates (28 spare).

12
BBIM/BBM/OptoServices _at_ PP3
  • PP3 opto services
  • crate splits the signals coming from SCOLink
    crate and send NTC opto to BBIM
  • we need to have 3 opto services crates 3U high
    (3x2472 channels) for 60 optoboards
  • BBIM
  • (6U high) you need to measure 12060 NTC signals,
    so you need 180 channels NTC PP2 (10 more??)
  • you need 1 or 2 BBIM crates (4 x 56 channels)
    what gives you 224 or 448 channels
  • BBM
  • BBM crate (3U high) assume 1 crate
  • OVERALL WE NEED ONE rack at PP3 (could be
    foreseen in USA??)

13
Optoboards
  • Current services
  • In the actual design detector, optoboards are
    cooled and then optoheaters may provide some more
    temperature tuning (6 opto granularity).
  • Blayer optoboards produce more power so any
    6-opto array might have a different temperature
    profile. Not optimal!
  • Not knowing which will be the future optoboards
    performances vs temperature, I think we still
    would assume a temperature regulation will be
    needed.
  • Requirements
  • 60 identical power consuming optoboards.
  • USA15.
  • Some more power supplies channels could be needed
    and should be foreseen.
  • Dont think it is an issue for the actual
    services requests but should not be forgotten.

14
Summary
  • Needed racks (requested to G.Mornacchi et al)
  • Control room (not a final assignment!)
  • 2 DAQ racks,
  • 1 rack for HV/LV
  • 1 rack for SCOlink, LU and IDB. The latter two
    could collapse in one new unique I-matrix crate.
  • 1 spare
  • PP3 1 rack (could be moved in USA15?)
  • PP2 2 PP2 crates plus NTC opto boxes. Strongly
    depending on routing out of PP1. No space problem
    in sector 9 or 13.
  • Still some space free in Pixel Racks
  • USA15 Y1614 and Y1014
  • PP3 we have in UX US side Y30.03x4 with only one
    BBIM. Nothing on USA side
  • We need 3 more racks in USA15 and one at PP3 USA
    side (There are free racks close to the pixel
    rack it should be perfect)

15
USA level2 - 14
Pixel empty racks
CR rack (3 PC inside)
From the rack wizard, view of USA15 level2
ROD racks
Write a Comment
User Comments (0)
About PowerShow.com