1
PSG Exercises - Round 2
  • TU-22.1176 Operations Management
  • February 1, 2006
  • Group 11
  • Jossas, Koskinen, Laukkanen

2
Exercise 2a
  • Setting
  • Setup times on the SMD machine to a quarter of
    the original (KS 0,25)
  • Default simulation findings
  • Uncompleted orders 27
  • Delivery accuracy 25
  • SMD setup time usage 27
  • Primary Tester for MB 16
  • Financials
  • Labor cost EUR 16 000,00
  • Inventory cost EUR 408,70
  • Result- -7,9

3
Exercise 2a
  • Problems solutions
  • Labor resource bottlenecks
  • ? increase amount of labor, especially at
    nights and weekends
  • Late deliveries
  • ? re-priorization of orders by delivery date
  • Long setup times
  • ? enlarge kanban lotsize for MB (20 ? 25) to
    decrease setup-times

4
Exercise 2a
  • Achieved solution (scenario number 8)
  • Delivery Accuracy 100 ( 75 )
  • SMD, setup-time 3 (- 24 )
  • Primary Tester for MB, setup-time 10 (- 6 )
  • Achieved financial results
  • Labor cost EUR 40 704,00 ( 24 704)
  • Inventory cost EUR 483,30 ( 74,60)
  • Result EUR 59 287,70
  • Result- 12,9
  • 1a financial result 10,3
  • reducing the setup time of SMD to 0,25 developed
    the utilization of the employees ? improved
    financial result

5
Exercise 2b
  • Setting
  • Increase the number of burn-in ovens to 2
  • Decrease setup time (KS) on mother board tester
    (MB) from 1.0 to 0.25
  • Default simulation findings
  • Uncompleted orders 41
  • Delivery accuracy 27
  • SMD setup time usage 6
  • Primary Tester for MB 16
  • Financials
  • Labor cost EUR 16 000,00
  • Inventory cost EUR 430,70
  • Result- -7,9

6
Exercise 2b
  • Problems solutions
  • Labor resource bottlenecks
  • ? increase amount of labor, especially at
    nights and weekends (again)
  • Late deliveries
  • ? re-priorization of orders by delivery date
    (again)
  • Long setup times
  • ? enlarge kanban lotsize for DB1 (20 ? 24) to
    decrease setup-times
  • High inventory cost
  • ? Decrease kanban lotsize of MB (20 ? 14)
  • The most effective way to improve results is to
    increase the number of employees ? reduced setup
    times and no late deliveries

7
Exercise 2b
  • Achieved solution (scenario number 20)
  • Delivery Accuracy 100 ( 75 )
  • SMD, setup-time 5 (- 1 )
  • Primary Tester for MB 7 (- 9 )
  • Achieved financial results
  • Labor cost EUR 34 560,00
  • Inventory cost EUR 450,40
  • Result EUR 63 064,60
  • Result- 13,8
  • Comparison between 1, 2a and 2b
  • The best result was achieved in 2b because of
    number of the ovens and the most fine
    adjustmented kanban optimizations ? idle time
    reduction

8
Exercise 2c
  • Setting
  • Demand setup base_low
  • Setup times on the SMD machine and on the MB
    tester to a quarter of the original (KS 0,25)
  • 2 kanban cards and 40 cards sizes 40 for every
    module
  • Default simulation findings
  • Uncompleted orders 0
  • Delivery accuracy 60
  • SMD setup time usage 2
  • Primary Tester for MB 2
  • Financials
  • Labor cost EUR 16 000,00
  • Inventory cost EUR 533,70
  • Result EUR 15 311,30
  • Result- 4,5

9
Exercise 2c
  • Problems solutions
  • Lower demand ? lower number of employees
  • Decreased Kanban sizes (40 ? 13/10)
  • Setup times rise
  • Comparison between 2b and 2c
  • Lower demand ? harder to affect to the assembly
    line and its efficiency
  • Lower demand reduces the profits of the line ??
    the production line has capacity to handle larger
    demand
  • Also lower number of employees needed

10
Exercise 2c
  • Achieved solution (scenario number 35)
  • Delivery Accuracy 97 ( 37 )
  • SMD, setup-time 7 ( 5 )
  • Primary Tester for MB 13 ( 11 )
  • Achieved financial results
  • Labor cost EUR 12 352,00
  • Inventory cost EUR 275,10
  • Result EUR 27 172,90
  • Result- 8,1

11
Exercise 2d
  • Setting
  • 2 MB testers
  • MB tester setup time to 0,1
  • SMD production speed to 2,0
  • SMD setup time to 2,0
  • Default simulation findings
  • Uncompleted orders 19
  • Delivery accuracy 36
  • SMD setup time usage 7
  • Primary Tester for MB 4
  • Financials
  • Labor cost EUR 16 000,00
  • Inventory cost EUR 428,50
  • Result EUR 1 266,50
  • Result- 0,4

12
Exercise 2d
  • Second setting (after the first optimizations)
  • SMD setup time to 0,25
  • Default second simulation findings
  • Uncompleted orders 28
  • Delivery accuracy 29
  • SMD setup time usage 6
  • Primary Tester for MB 2
  • Second financials
  • Labor cost EUR 16 000,00
  • Inventory cost EUR 231,20
  • Result EUR -25 076,20
  • Result- -10,2

13
Exercise 2d
  • Problems solutions (simulation part 1)
  • Idle time for SMD 1, very good
  • With Kanban cards you can affect the setup times
    and then the effiency of the whole line
  • Problems solutions (simulation part 2)
  • Need for SMD idle time reduction
  • Our idle time 17 ? not as good as in the first
    part of 2d
  • Addition of workers in the beginning of the week
    and the Kanban card size changes didnt change
    the result as we wanted ? we couldnt find the
    final cue

14
Exercise 2d
  • Achieved solution (scenario number 50, simulation
    1)
  • Delivery Accuracy 100 ( 64 )
  • SMD, setup-time 21 ( 14 )
  • Primary Tester for MB 1 (- 3 )
  • Achieved financial results
  • Labor cost EUR 31 296,00
  • Inventory cost EUR 486,60
  • Result EUR 63 092,40
  • Result- 13,8

15
Exercise 2d
  • Achieved solution (scenario number 60, simulation
    2)
  • Delivery Accuracy 100 ( 71 )
  • SMD, setup-time 2 (- 4 )
  • Primary Tester for MB 1 (- 1 )
  • Achieved financial results
  • Labor cost EUR 23 232,00
  • Inventory cost EUR 643,30
  • Result EUR 70 999,70
  • Result- 15,5

16
Summary
  • The whole production line is very ineffective
  • low utilization of almost all machines
  • Higher volume means higher profits
  • Self estimation, considering the upcoming
    sessions
  • Need for better analyze of data and more thinking
    ? save of time and work
Write a Comment