Title: Power Supply Polarity Reversal for e e American Linear Collider Physics Group Workshop University of
1Power Supply Polarity Reversal for e- e-
American Linear Collider Physics Group Workshop
University of VictoriaJuly 28-31, 2004
- R.S. Larsen, P. Bellomo C. M. Spencer
- Stanford Linear Accelerator Center
2Goals
- 1. Estimate the incremental cost of implementing
reversible power supplies throughout the positron
Injection System to enable e-e- operation. - 2. Make a similar estimate for the Beam Delivery
area. - Use available cost estimating data from 1999 and
2003 to determine the numbers types of power
supplies involved. - Since lattices are still being refined quantities
will be approximate.
3Background1
- Prior talks at e- e- LC workshops at UC Santa
Cruz considered options for enabling positrons to
be alternated with polarized electrons in an e
injection system. - Erickson (Ref. 1, 1997) reviewed potential issues
in the areas of Injection, Main LINAC and Beam
Delivery - Injection requires reversal of all magnets
- Main LINAC quads work for either e- or e with
VH beam profiles interchanged, with a p phase
shift at injection - Beam Delivery needs reversal of all magnets
- Conclusions Adding e-e- feature to existing SLC
rejected due to time cost of manual polarity
reversal in transport line and modifying
interaction region. Concluded that e- e- in TeV
machine must be planned designed up front.
4Background 2
- Late 1999, permanent magnets were being
considered for many parts of NLC Injection as
well as Main LINAC, to save power and/or costs. - Larsen (Ref. 2, 1999) considered three concepts
for Injection System - Polarity Reversal Model
- Direction Reversal Model
- Independent System Model
- 1999 Conclusion Because permanent magnets made
polarity reversal very difficult, and the
independent system would be exceedingly costly,
the Direction Reversal Model was deemed most
practical. - Actual costs not estimated Beam Delivery not
addressed.
5Direction Reversal Model 1999
6Direction Reversal Features
- New polarized e- source
- Accelerate e- in pre-linac to 2 GeV
- Build new bypass for e target section, 2 GeV
linac, pre-damping ring, DR injection line - Build new injection, extraction lines for e- in
opposite rotation in DR - Build new launch and extract lines for reverse
direction in turnaround - Add matching components to launch into main linac
- Main advantage No power supply reversal so
compatible with e permanent or electromagnets - Main disadvantage New earthworks and transport
lines, injection and extraction lines cost
significant but not estimated formally suggested
further study.
7Independent Systems Model - 1999
8Independent Systems Model
- Complete duplicate injection system for polarized
e- - e to/from e- operation quickly reconfigurable
from control room - Both systems could be brought up, switched
rapidly - Would require only modest additional space if
shared tunneling planned up front - Operationally ideal solution but not seriously
considered due to high cost - 90M for magnets and power supplies alone
9Background 3
- In late 2002, permanent magnet RD put on hold,
NLC Baseline Model returned to electromagnets for
all applications - Without PMs in picture, Polarity Reversal Model
was reconsidered. - Larsen (Ref. 3, 2003 ) Workshop paper suggests
considering H-Bridge bipolar switching supplies
throughout e injector complex. - No detailed technical or cost analysis discussed.
10Polarity Reversal Model- 2003
11In the Cold Light of Dawn
- Bipolar H- Bridge supplies not a good general
solution - Require large AC line transformer to isolate HF
switching transformer (switcher normally runs
directly off the line) - Adds considerable bulk, cost to every unit
- Control through zero not necessary
- Space requirements increase by 2X
- Solid State Reversing Switches can do the job
simpler, in less space and cheaper.
12Technical Cost Considerations
- Main additions to system are polarized e- source,
transport injection lines, and reversing
switches. - New IGBT components make reversing much simpler,
faster than mechanical switches or manual
cable-swap. - IGBT switches can be made very compact and
low-cost. - Speed of switching of the order of minutes or
longer is adequate high-speed not required since
interleaving of beams not a goal. - Power supply requirements detailed in 1999,
updated 2003, are used for determining number of
switches needed. These still need further
updating but are fine for calculating approximate
incremental cost.
13e Injection System Magnets by Type(Quantities
Rev. 071404 by C. M. Spencer)
Legend PPLePre-LINAC, PPDRePre-Damping Ring,
PDReMain Damping Ring, LTRLinac-to-Ring,
XFERTransfer, BCBunch Compressor
14Typical Power Supply Types
Corrector MCORs Bipolar
20-90 kW EMHPs
2 MW String Supply
2.5-17 kW Intermediates Solid State Inverters
290kW Bulks
15Typical PS Types 2
Rear Panel Outputs
Intermediate Rack-mounts
200kW Chopper Module
Bulk 200 kW Chopper Racks
16Reversing Switch Proposal
- Goal Operate e-/e switchover entirely remotely
from Control Room (no wrenches). - Design family of switches to match the various
classes of power supply family - For smaller rack-mount supplies, package
air-cooled switches in separate 3U high
rack-mount chassis located adjacent to supply. - For larger free-standing supplies, can easily
mount water-cooled switches inside typical large
cabinets.
17Reversing Switch Components
- IGBT Switches are packaged in 1, 2 or 4 units
depending on power ratings. - Superior on/off control, low gate drive c.f. SCR
or GCT (Gate Commutated Thyristor) switches. - Assembly consists of
- 4 IGBT switches in H-Bridge configuration
- 4 Gate Drivers
- Heatsink (air or water cooled)
- Copper bus and hardware
- Control Interface
- Enclosure and Connectors
18Cost Estimating Procedure 1
- Power Supply Systems bottom-up cost estimates
originally done for DoE Design Review in 1999,
revised by C. M. Spencer in 2003 - Designed estimated cost for every unique magnet
- Assigned power supply from commercial in-house
look-up table - Calculated cooling, AC requirements, cable plant,
IC - Summed all component costs by major sub-areas
- Gun area, e target, pre-linacs
- Pre-damping ring, transport lines
- Main damping ring, post linac, turn-around
- These data used to obtain numbers and types of
power supplies - Numbers then used to calculate incremental
Reversing Switch costs. -
19Cost Estimating Procedure 2
- Created conceptual design, cost estimate for
seven (7) Reversing Switch models (P. Bellomo,
2004). - Added columns to original 1999 power supply
spread sheet rollup. - Estimated Reversing Switch cost increment for
fully redundant e system - Power Supply redundancy model taken from 1999
estimate. - Estimates made for both Injection and Beam
Delivery.
20Reversing Switch Estimate Example
21Reversing Switch Model Summary
22Reversing Switch Cost Summary Injection Area
23Reversing Switch Cost Summary Beam Delivery Area
24Assumptions, Caveats, Disclaimers
- Costs cover completed Reversing Switch hardware,
mounted either inside purchased supply or in
separate rack-mount chassis. - Only half Pre-Damping Ring included since e- beam
traverses only half the PPDR on its way to Main
Damping Ring (JS). - Not estimated
- Polarized electron source, associated transport,
controls. - Spin rotators, polarimeter, phase shifter
- Injection extraction kickers
- EDI, installation, system integration, checkout,
commissioning, contingency, GA, sales tax,
foreign exchange, VAT, beer, wine...
25Discussion Conclusion
- IGBT Reversing Switches are a practical low-cost
solution to polarity switching for e- e-, costing
of the order of 5M for additional hardware for
Injection and Beam Delivery areas. - For comparison, the total is 5.5 of the 93M
total for power supplies for the Injection Region
alone, assuming full redundancy. - A comprehensive technical study, cost estimate
and operational model is needed if e- e- is ever
to become part of the ILC plan. - An important side-benefit of polarity reversal is
that e rings could be tested initially with
electrons (J. Sheppard).
26References Acknowledgments
- 1. Erickson, R, e- e- Collisions in a TeV
Collider Built for e e- Operation,
SLAC-PUB-7768, March 1998. - 2. Larsen, Raymond S., e- e- Switchover in the
NLC LINAC, Intl J Modern Phys A Vol.15 No. 16
(2000) 2477-2483 - 3. Larsen, R. S., Revisiting e- e- Switchover in
the NLC LINAC, SLAC-PUB-10452, February 2004. - The original models for Injection alternatives
were suggested by J. Sheppard, Head of Injection
Systems for the NLC Department, SLAC. - C.M. Spencer and P. Bellomo provided the Magnet
Systems cost data and the Reversing Switch design
and cost estimates respectively. - These contributions are gratefully acknowledged.