STAR MRPC TOF: Project Overview - PowerPoint PPT Presentation

1 / 19
About This Presentation
Title:

STAR MRPC TOF: Project Overview

Description:

The integration space available for TOF in STAR is that currently occupied by the CTB. ... Trays are re-tested at BNL: HV current, noise rates, gas leak test ... – PowerPoint PPT presentation

Number of Views:176
Avg rating:3.0/5.0
Slides: 20
Provided by: gearye
Category:

less

Transcript and Presenter's Notes

Title: STAR MRPC TOF: Project Overview


1
STAR MRPC TOF Project Overview
BNL January 26, 2006
Geary Eppley Rice University
2
Design considerations
  • The integration space available for TOF in STAR
    is that currently occupied by the CTB.
  • The space is about 2.2m from the beam line
    requires precision time measurement.
  • The clearance between the TPC and EMC is about 10
    cm.
  • The space has a uniform 0.5T magnetic field
    parallel to the beam.
  • There is limited space for nearby electronics
    outside the magnet steel.

3
MRPC development
  • Multigap glass RPCs developed in the late 1990s
    at CERN, C. Williams, et.al.
  • STAR TOF group designed STAR-specific MRPC
    modules that would fit existing CTB trays and
    tested them at CERN in 2000 2001.

4
MRPC prototypes in STAR
  • One tray of MRPC modules has been installed in
    STAR for Runs 3, 4, 5.
  • An improved tray design each year but some
    modules have been installed for all 3 years.
  • Runs 3 4 used CAMAC electronics.
  • Prototype HPTDC based electronics used in Run 5
    and Run 6

5
Electronics integral to tray
  • 95 of the electronics resides on the tray inside
    the cover
  • 4 external electronics boxes located on the
    magnet steel connect the 23k-channel system to
    STAR trigger and DAQ

6
Tray specifications
  • There are 32, 6-channel modules per tray.
  • The active area covers about 87 of -0.9ltetalt0.9
  • Occupancy in central AuAu is 12.
  • HV provides -7 kV.
  • Gas mixture 95 r134a, 5 isobutane.
  • Average noise rates are 15 Hz/channel with
    greater than 100 correlation.
  • Detection efficiency is 95.

7
Time measuring
  • Absolute times are recorded and buffered by the
    HPTDC for all hits above threshold.
  • A single 40 MHz oscillator provides the clock for
    the 2882 HPTDCs in the system.
  • Both start and stop detectors use the HPTDC to
    record times eliminating systematic uncertainty
    from the choice of counter.
  • Each HPTDC has a 21 bit clock counter providing
    a 51 us clock period. The HPTDCs are reset by a
    signal with a common origin at the beginning of
    each run giving each HPTDC a different phase that
    may be learned from the data.
  • Since this phase is always the same, the phase
    becomes a powerful tool to monitor the integrity
    of the data through buffering, trigger matching,
    event building, transmission to DAQ, and global
    event building.

8

Total time resolution from Run 5
62GeV CuCu, 124ps
200GeV CuCu, 105ps
9
Time resolution by channel
10
Timing results, Runs 3, 4, 5
11
STAR TOF publications
  • Physics
  • Open charm yields in dAu collisions STAR
    Collaboration, Phys.Rev.Lett. 94 (2005) 062301.
  • Cronin effect of identified particle at RHIC
    STAR Collaboration, Phys.Lett.B 616 (2005) 8.
  • Technical
  • B. Bonner et al., Nucl.Instr.Meth.A 478 (2002)
    176.
  • M. Shao et al., Nucl.Instr.Meth.A 492 (2002) 344.
  • W.J. Llope et al., Nucl.Instr.Meth.A 522 (2004)
    252.
  • F. Geurts et al., Nucl.Instr.Meth.A 533 (2004)
    60.
  • J. Wu et al., Nucl.Instr.Meth.A 538 (2005) 243.
  • Y. Wang et al., Nucl.Instr.Meth.A 538 (2005) 425.
  • Y.E. Zhao et al., Nucl.Instr.Meth.A 547 (2005)
    334.

12
Organization chart
13
Manufacturing overview
  • Module production and test, electronics
    production and test, and tray assembly and test
    each have a duration of 2.2 years.
  • Module production begins 3 months before the
    start of tray assembly and electronics production
    1.5 months before the start of tray assembly.
  • Modules are thoroughly tested in China with
    integral HV wire and signal cables.
  • Electronics cards are tested in groups of 17, 1
    tray, with their integral cables and sent to the
    tray assembly site as a set.
  • Modules are assembled into trays, the electronics
    added, and tested for 2-4 weeks as a complete
    detector unit.
  • Tested trays are shipped to BNL as complete
    detector units ready for insertion into STAR.
  • Trays are re-tested at BNL HV current, noise
    rates, gas leak test
  • Test beam at BNL for selected trays?

14
Gantt chart
15
TOF system functional requirements
16
Current project status
  • Cosmic ray testing of the TINO front-end board is
    ongoing.
  • Automated TINO board production has been
    achieved.
  • Upgraded 38-channel start detector under
    construction.
  • Based on a recommendation from the review, the
    China TOF project built a few new modules with
    highly resistive electrodes. Due to difficulties
    involved with the manufacturing process, the
    China groups decided to stick with the
    graphite-tape electrodes.
  • Layout of the first prototype THUB is underway.
  • The project started officially January 1. We hope
    to get the university accounts open before the
    end of February.

17
TOF Gas system
  • The TOF system will operate on a gas mixture of
    90 parts r134a and 5 parts isobutane.
  • The system will vent 12 pounds r134a per day
    during STAR operations
  • The system will be sealed but not operate during
    shutdown periods.
  • The isobutane/r134a ratio is set by the factory
    calibration of the mass flow meters. It will also
    be monitored by an isobutane analyzer.
  • The aggregate gas circulation rate through the
    trays is 450 l/h.
  • The gas is re-circulated and dried maintaining
    H2Olt20 ppm, O2lt30 ppm.
  • The system is interfaced to STAR slow controls
    through a shared disk. Isobutane content is
    alarmed to insure non-flammable gas. Gas flow is
    alarmed to maintain safe operation of the trays.

18
TOF gas system schematic
19
DOE review recommendation
  • Investigate using SF6 or C4F10 Improves MRPC
    operational characteristics.
  • Our reply Our AGS 11-week test run data confirms
    this SF6 greatly extends the HV plateau from
    lt500v to gt1000v.
  • Using SF6 will allow running at a higher voltage
    and improve timing resolution.
  • We will investigate
  • Developing standards for gas-tight integrity
  • Adding gas leak SF6 detectors
  • Adding positive air flow in the TOF tray area
Write a Comment
User Comments (0)
About PowerShow.com