SARs - PowerPoint PPT Presentation

1 / 21
About This Presentation
Title:

SARs

Description:

DoD publicly supports passage, expected by Memorial Day. 17. Nunn-McCurdy: Levin-McCain ... of the 60-day period beginning on the day the Selected Acquisition ... – PowerPoint PPT presentation

Number of Views:124
Avg rating:3.0/5.0
Slides: 22
Provided by: christin344
Category:
Tags: day | memorial | sars

less

Transcript and Presenter's Notes

Title: SARs


1
SARs Nunn-McCurdy An Update
  • 2009 Business Manager's Conference
  • May 19, 2009
  • Larry Axtell, OUSD(ATL)

2
Agenda
  • SARs
  • FY 2009 submissions
  • New Reporting Requirements (e.g., subprograms,
    DAMIR cost and funding detail)
  • Nunn-McCurdy
  • Current Breach Status
  • Weapon System Acquisition Reform Act of 2009
    (Levin-McCain)

3
SARs December 2008 Submission
  • Annual SARs due 60 days after Presidents budget
    (pursuant to 10 USC 2432)
  • Presidents budget due NLT first Monday in
    February (pursuant to 31 USC 1105)
  • Due to change in Administration, budget not
    submitted on February 2 (Obama revising Bush
    budget)
  • President submitted topline budget on February
    26 (which General Counsel determined did not meet
    31 USC 1105)
  • President submitted detailed budget on May 7
  • Major program decisions (e.g., CSAR-X, DDG 1000,
    FCS, TSAT, VH-71, etc.)
  • However, details of FY 2010 only (plus prior
    years FY 2008-9)

4
SARs December 2008 Submission
  • Without revised funding guidance for the total
    program, DoD will not submit December 2008 SARs,
    except for programs with Nunn-McCurdy breaches
  • H-1 Upgrades (significant breach from December
    2008)
  • Termination report for VH-71 (critical breach
    from January 2009 will not be certified)
  • December 2008 SARs for H-1 Upgrades and VH-71 due
    to Congress NLT July 6, 2009
  • No press release planned

5
SARs June/September 2009 Submissions
  • Quarterly Exception SARs required for programs
    with Nunn-McCurdy breaches or schedule delays of
    at least six months
  • Due to Congress 45 days after the end of the
    fiscal year quarter
  • As of June 30 reports due August 14
  • As of September reports due November 14
  • DoD plans to submit quarterly SARs for all
    programs with Nunn-McCurdy breaches
  • DoD may defer quarterly SARs for schedule slips
  • Issue with what to report for total program costs

6
SARs New Reporting Requirements
  • Subprograms
  • DAMIR cost and funding detail

7
SARs New Reporting Requirements Subprograms
  • In response to DoD, FY 2009 National Defense
    Authorization Act permits DoD to designate
    subprograms for MDAPs
  • That is, USD(ATL) can designate subprograms when
    an MDAP requires delivery of two or more end
    items that differ significantly in form and
    function
  • In DoD acquisition environment, two primary
    instances when establishing subprograms may be
    advisable
  • Evolutionary acquisition when blocks or
    increments are acquired in a sequential manner
    (e.g., JSOW)
  • Major components are dissimilar and cannot be
    combined in a rational way to track unit costs
    (e.g., NAVSTAR GPS)

8
SARs New Reporting Requirements Subprograms
  • FY 2009 NDAA requires Congress be notified 30
    days prior to taking effect (i.e., approval of
    APB)
  • DoD Components must notify OSD 60 days prior to
    submitting proposed APB to MDA
  • For ACAT ID MDAPs, USD(ATL) designates
    subprograms based on recommendations from OIPT
  • For ACAT IC MDAPs, DoD Component MDA designates
    subprograms based on recommendations from MDA
    staff
  • Note Recommendations from the OIPT or MDA
    staff should include guidance on whether
    statutory and regulatory requirements of DoDI
    5000.02 should apply at the subprogram or program
    level, i.e., Acquisition Strategy, Beyond-LRIP
    Report, CARD, etc.

9
SARs New Reporting Requirements Subprograms
  • When one subprogram is designated within an MDAP,
    all remaining elements (increments or components)
    of the program shall also be appropriately
    organized into one or more other subprograms
    (pursuant to 10 USC 2430a)
  • The DoDI 5000.02 requirement for each
    evolutionary increment to have its own APB is
    satisfied through the establishment of
    subprograms
  • If a subprogram experiences a critical Nunn
    McCurdy unit cost breach, the certification
    required for the program to continue will need to
    be made at the program level.

10
SARs New Reporting Requirements DAMIR Cost and
Funding
  • All costs/funding are to be broken out into
    year-by-year format
  • In addition, procurement is to be broken into
  • End item related recurring flyaway
  • Non item related recurring flyaway
  • Nonrecurring flyaway, and
  • Support (initial spares and other)

11
SARs New Reporting Requirement DAMIR Cost and
Funding
  • Also in base-year dollars

12
SARs New Reporting Requirement DAMIR Cost and
Funding
  • Finally, recurring flyaway dollars are to be
    aligned with quantity to reflect the
    cost-quantity relationship of the current
    estimate

13
Nunn-McCurdy
  • Current Breach Status
  • Weapon System Acquisition Reform Act of 2009
    (Levin-McCain)

14
Nunn-McCurdy Current Baseline Breaches
15
Nunn-McCurdy Original Baseline Breaches
16
Nunn-McCurdy Levin-McCain
  • In February 2009, Senators Carl Levin and John
    McCain introduced the Weapon Systems Acquisition
    Reform Act of 2009 (S.454) to Senate Armed
    Services Committee (SASC)
  • After reclama by DoD, revised S.454 passed the
    Senate in May 2009
  • Similar bill (less prescriptive H.R.2101)
    introduced by Representatives Ike Skelton and
    John McHugh (HASC)
  • DoD publicly supports passage, expected by
    Memorial Day

17
Nunn-McCurdy Levin-McCain
  • Weapon Systems Acquisition Reform Act of 2009
    (S.454)
  • Independent Performance Of Acquisition Oversight
    Functions (Section 101)
  • Oversight Of Cost Estimation (Section 102)
  • Oversight Of Systems Engineering (Section 103)
  • Oversight Of Performance Assessment (Section 104)
  • Assessment Of Technological Maturity Of Critical
    Technologies Of Major Defense Acquisition
    Programs By The Director Of Defense Research And
    Engineering (Section 105)
  • Role Of The Commanders Of The Combatant Commands
    In Identifying Joint Military Requirements
    (Section 106)
  • Acquisition Strategies Ensuring Competition
    Throughout The Lifecycle Of Major Defense
    Acquisition Programs (Section 201)
  • Additional Requirements For Certain Major Defense
    Acquisition Programs (Section 202)
  • Requirement For Certification Of Major Systems
    Prior To Milestone B (Section 203)
  • Critical Cost Growth In Major Defense Acquisition
    Programs (Section 204)
  • Organizational Conflicts Of Interest In The
    Acquisition Of Major Weapon Systems (Section 205)
  • Awards For Department Of Defense Personnel For
    Excellence In The Acquisition Of Products And
    Services (Section 206)
  • Consideration Of Trade-offs Among Cost, Schedule,
    And Performance In The Acquisition Of Major
    Weapon Systems (Section 207)

18
Nunn-McCurdy Levin-McCain
  • For programs with critical Nunn-McCurdy breaches
    (25 to the current or 50 to the original
    baseline), SecDef (after consultation with JROC)
    shall determine root causes, including
  • changes or growth in requirements
  • unrealistic baseline estimates
  • any design, engineering, manufacturing, or
    technology integration issues
  • changes in procurement quantities
  • inadequate program funding or funding
    instability
  • poor performance by government or contractor
    personnel responsible for program management or
  • other causes as identified by the SecDef

19
Nunn-McCurdy Levin-McCain
  • SecDef shall then determine whether to terminate
    or restructure the program after assessing
  • the root causes of cost growth
  • the validity and urgency of the joint military
    requirement
  • the viability of the acquisition strategy
  • the quality of program management
  • a broad range of potential material and
    non-material alternatives and
  • the need to reduce funding for other programs due
    to cost growth on this program
  • Before the end of the 60-day period
    beginning on the day the Selected Acquisition
    Report containing the information described in
    subsection (g) is required to be submitted under
    section 2432(f) of this title

20
Nunn-McCurdy Levin-McCain
  • A program may be restructured only if
  • a written certification (with a supporting
    explanation) is submitted along with the
    determination stating that
  • 1. such program is essential to the
    national security
  • 2. there are no alternatives to such
    program which will provide
    acceptable military capability at less cost
  • 3. new estimates of the unit costs are
    reasonable
  • 4. the program is a higher priority than
    programs whose funding
    must be reduced to accommodate cost growth on
    such program and
  • 5. the management structure is adequate
    to control unit costs and
  • the most recent milestone decision is revisited
    and results in approval of the restructured
    program

21
  • Thank You for Your Attention
  • Any Questions?
Write a Comment
User Comments (0)
About PowerShow.com