Title: Amendments and Additions to North Carolina's Underground Storage Tank Rules
1Amendments and Additions to North Carolina's
Underground Storage Tank Rules
- Title 15A North Carolina Administrative Code
Subchapter 2N (15A NCAC 2N) - Criteria and Standards Applicable to Underground
Storage Tanks
2Introductions
- Ruth Strauss, Permits Inspection Branch
Supervisor, ruth.strauss_at_ncmail.net - Michael Phelps, UST Inspector Supervisor,
michael.phelps_at_ncmail.net - Matt Wegner, Environmental Engineer,
matt.wegner_at_ncmail.net - Andria Merritt, Hydrogeologist,
andria.merritt_at_ncmail.net
3Logistics
- Please turn off cell phones/pagers
- Agenda
- Restrooms
- Handouts
- Slides
- UST-6 Form
- Synopsis of new requirements
- FAQ
- Inspector Map
4As of November 1st, 2007...
- The changes affect
- New installations
- Replacements on existing systems
- Notification requirements
5?
FAQ
Q Why are these changes being implemented?
A In response to North Carolina General Statute
143-215.94T and the Federal Energy Policy Act of
2005 secondary containment option.
6New Performance Standards
- Tanks
- Piping
- Associated components (e.g., dispensers,
submersible pumps) - Containment sumps
- Spill buckets
- Siting for replacement systems
- Operation and maintenance
- Emergency generator tanks
- Replacements
Apply to...
7New Performance Standards
- Vent lines
- Vapor recovery lines
- Gravity-fed vertical fill ports
Do not apply to...
8Tanks
- Non-corrodible
- Fiberglass reinforced plastic (FRP),
- Steel clad w/FRP or polyurethane, or
- Jacketed steel tanks
9Tanks (contd)
- Double-walled w/continuous interstitial
monitoring - (Must maintain 12 months of monthly printed
records of release detection results and alarm
history) - Vacuum
- Pressure
- Hydrostatic
10Piping
- Non-corrodible
- Double-walled
- Locatable once installed
(e.g.,
trace tape commonly used by utilities)
11Piping (contd)
- Continuously monitored
- (Must maintain 12 months of monthly printed
records of release detection results and alarm
history) - Vacuum,
- Pressure,
- Hydrostatic, or
- Electronic liquid-detecting sensor in sump that
piping interstice drains to with primary and
secondary wall integrity test every three years
12Piping (contd)
- Also
- Pressurized piping must still have Automatic Line
Leak Detectors (ALLDs) - Suction piping, including European, and siphon
bars must meet new standards - Flexible connectors and fittings not
double-walled must be in monitored containment
sumps
13FAQ
?
Q Do the new regulations affect siphon bars on
manifolded tanks?
A Yes, siphon bars are considered piping and
must be constructed of double-walled,
non-corrodible materials and monitored
continuously, just like all other piping.
14Associated Components
Secondary containment w/interstitial monitoring
(Must maintain 12 months of monthly printed
records of release detection results and alarm
history)
- Underground ancillary equipment
- Dispensers
- Line leak detectors
- Submersible pumps
- Remote fill pipes, etc.
15FAQ
?
Q What are the options for secondary containment
and monitoring of the associated components
listed?
A Typically, containment sumps with sump sensors
are used for every non-tank component and under
dispenser containment for dispensers.
16Containment Sumps
- Designed, constructed, installed, and maintained
to prevent water infiltration - Visually inspected annually
- Non-corrodible
17Containment Sumps (contd)
- Monitored continuously
- (Must maintain 12 months of monthly printed
records of release detection results and alarm
history) - Vacuum,
- Pressure,
- Hydrostatic, or
- Electronic liquid-detecting sensor no more than
two inches from sump bottom with integrity test
every three years
18FAQ
?
Q Do containment sumps need to be double-walled
with interstitial monitoring?
A No - As stated earlier, sumps are excluded
from the secondary containment requirement. Sumps
are considered to be the secondary barrier for
single-walled components.
19Spill Buckets
- Non-corrodible OR isolated from backfill
- Prefabricated
- Double-walled
- Designed, constructed,
- installed, maintained to
- prevent water infiltration
20Spill Buckets (contd)
- Monitored continuously
- (Must maintain 12 months of monthly printed
records of release detection results and alarm
history) - Vacuum,
- Pressure,
- Hydrostatic, or
- Electronic liquid-detecting sensor with integrity
test every three years
21FAQ
?
Q Will a single-walled spill bucket placed
inside a continuously monitored containment sump
satisfy the new requirements?
A Yes - It would be secondarily contained and
continuously monitored by a sump sensor.
22Siting For UST Systems
Installations of new and replacement systems
prohibited
- In contact with contaminated soil or free product
- Within 100 feet of well serving public water
system - Within 50 feet of any other well (human
consumption)
23Emergency Generator UST Systems
- Must comply with the new performance standards
including secondary containment and interstitial
monitoring
24Replacements
- Underground storage tanks
- UST can not be connected to piping that does not
meet new standards
- Dispensers
- Add under dispenser containment with
- continuous monitoring if the connecting
equipment is also being replaced
25FAQ
?
Q What if a dispenser is knocked over by a
reckless driver or a severe storm, such as a
hurricane?
A If an existing dispenser is replaced and the
equipment used to connect the dispenser to the
UST system is replaced, then under dispenser
containment must be added.
26Replacements (contd)
- Piping (including extensions)
- Entire piping run must meet
- new standards
- Flex connectors, submersible pumps, other
ancillary equipment - Add containment sumps with continuous monitoring
27Summary of Periodic Testing Requirements
- Sumps (monitored by liquid-detecting sensors)
- Integrity test every three years, maintain most
recent test - Visually inspect annually, empty water/regulated
substance within 48 hours of discovery - Maintain results of most recent
- visual inspection
28Summary of Periodic Testing Requirements
- Piping (that drains to monitored sumps)
- Integrity test of primary and secondary walls
every three years - Maintain results of most recent test
- Spill Buckets (monitored by liquid-detecting
sensors) - Integrity test of primary and secondary walls
every three years - Maintain results of most recent test
29Summary of Periodic Testing Requirements
- Interstitial monitoring sensors
- Checked annually for operability, proper
operating condition and proper calibration - Maintain results of most recent check
- Overfill
- Checked annually for operability and proper
operating condition - Maintain results of most recent check
- ALLDs
- Annual functionality test
- Maintain results of most recent test
30New Notification Requirements
- Effective September 21, 2007
- Applies to new installations of
- Tanks
- Piping (including extensions to existing piping)
- Tanks and piping
- Does not apply to new installations of only
- Spill buckets
- Under dispenser containment
- Containment sumps
31New Notification Requirements
OLD PROCESS
UST-8
UST-6
Installation
Pre-Installation
Post-Installation
UST-6 Notice of Intent to Install Underground
Storage Tanks UST-8 Notification for
Activities Involving Underground Storage Tank
Systems (USTs)
32New Notification Requirements
X
OLD PROCESS
UST-8
UST-6
Installation
Pre-Installation
Post-Installation
UST-6 Notice of Intent to Install Underground
Storage Tanks UST-8 Notification for
Activities Involving Underground Storage Tank
Systems (USTs)
33New Notification Requirements
NEW PROCESS
UST-6B
UST-6A
Installation
Pre-Installation
Post-Installation
UST-6A Application to Install or Replace
Underground Storage Tank Systems
(Pre-Installation) UST-6B Application to
Install or Replace Underground Storage Tank
Systems (Post-Installation)
34New Notification Requirements
NEW PROCESS
UST-6B
UST-6A
Installation
Pre-Installation
Post-Installation
UST-6A REVIEW
35New Notification Requirements
NEW PROCESS
UST-6B
UST-6A
Installation
Pre-Installation
Post-Installation
TWO INSTALLATION INSPECTIONS
36New Notification Requirements
NEW PROCESS
UST-6B
UST-6A
Installation
Pre-Installation
Post-Installation
UST-6B REVIEW PERMIT ISSUED
37New Notification Requirements
NEW PROCESS (contd)
UST-8
UST-8 Form Notification for Activities Involving
Underground Storage Tank Systems (USTs)
- Used for all other notifications such as
- Putting UST systems into temporary closure
- Changing product stored
- Changing leak detection method
38New Notification Requirements
- Three phases
- Pre Installation
- Installation
- Post Installation
39Pre Installation
- 30 days in advance you must submit
- UST-6A form
"Application to Install or Replace - UST Systems (Pre-Installation)
- UST system design plans
- prepared by a NC Professional
- Engineer
- Schedule of materials
- Scale drawings
40Pre Installation (contd)
- Schedule of Materials (e.g., make and model)
- Tanks
- Piping
- Dispensers
- Leak detection equipment
- Spill prevention equipment
- Overfill prevention equipment
- Vapor recovery equipment
41Pre Installation (contd)
- Scale Drawing(s)
- No larger than 11 x 17
- Must show the proposed locations of
- UST system features (USTs, piping, dispensers,
vapor recovery, leak detection systems, etc.) - Adjacent roadways
- Onsite structures
- Onsite water supply wells
42Pre Installation (contd)
Incomplete applications will be returned and/or
delay the application process
Please read the instructions of the UST-6
carefully when submitting your UST-6A
43?
FAQ
Q How long will it take for the State to review
the UST-6A and give approval to proceed with the
install?
A Forever.
44?
FAQ
Q How long will it take for the State to review
the UST-6A and give approval to proceed with the
install?
A State rules require notification at least 30
days before installation however, the actual
review could take two weeks or less.
45?
FAQ
Q What common mistakes/problems have been seen
on the UST-6 forms submitted so far?
A 1) Incomplete submittal of UST-6A form,
schedule of materials or scale
drawing 2) Conflicting information 3) Incorrect
model numbers for equipment 4) Poor copies /
legibility
46Installation
- If UST system design is satisfactory
- State issues an approval to construct letter
- including the name and contact information
- of your UST inspector
- Installation may begin
- Two inspections are
- required during installation
47Installation Inspections
- First Inspection
- Exterior tank surface inspection
- Tank integrity testing prior to placing tank
into excavation - Second Inspection
- Testing of all piping and fittings prior to
back-filling - Contact UST inspector at least 48 hours in
advance, not including weekends or holidays.
Installation cannot proceed until inspection has
been conducted.
48Installation Inspections (contd)
- Tank, piping, and equipment information
- Installer information for everyone installing
- Certification type
- Certificate issuer
- Certification number
- Certification date
- Approval for fuel delivery to perform final
system testing
49Installation (contd)
- Installers must
- Adhere to manufacturer installation instructions
- Ensure that all personnel installing equipment
are certified, if offered by manufacturer - Properly set up sensor locations in monitoring
console and provide descriptive labels
50Installation (contd)
- Installers must
- Refer to most recent versions of industry codes
API 1615, PEI RP100, ANSI B31.3 and B31.4
Be Aware Ball float valves should not be used
for overfill if UST system receives pressurized
deliveries, has suction piping, or has coaxial
stage 1 vapor recovery
51Summary of Installation Testing Requirements
- Tanks
- Tightness of interstice prior to placement in pit
- Post-Installation tightness test
- Piping
- Before backfilling, air/soap test
- Monitor throughout site construction
- Post-Installation line tightness testing of the
primary and interstitial spaces
52Summary of Installation Testing Requirements
- Ancillary Equipment
- Sump and spill bucket integrity tests, after
assembly but before backfill - Operability of overfill prevention equipment
- Operability of sensors
- ALLD tests
53Post Installation
- Submit
- UST-6B form, Application to Install or Replace
UST Systems - UST-20 form, Alternative Fuel Compatibility
Checklist (If applicable) - UST-15A form, Ownership of UST System(s)
- Appropriate annual operating fees
- Proof of Financial Responsibility
- Certification of Financial
Responsibility form
54Post Installation (contd)
- The UST-6B application requires
- Completed manufacturer installation checklists
for the tanks, piping, and any other applicable
equipment - Pre- and post-installation tests of tanks and
piping - As-built scale drawings
- (Note Incomplete forms will delay permitting
process)
55?
FAQ
Q Where can I obtain all the UST forms?
A http//www.wastenotnc.org
56Questions?
Thank you for attending! Division of Waste
Management - UST Section 1637 MSC, Raleigh, NC
27699 phone (919) 733-8486 fax (919)
733-9413 http//www.wastenotnc.org