Title: Construction of the Public Sector Comparator
1Construction of the Public Sector Comparator Andy
Stubbings, Private Finance Unit PPPs / Regional
Government of Madrid 3 March 2006
2Background
- Financial Consultant in the Private Finance Unit
- Team of 14 legal and financial consultants,
working closely with a team of civil servants
responsible for - reviewing and approving business cases for new
investment - helping develop and implement PFI policy in
health - managing the health PFI market
- advising on specialist legal and financial
issues. - Specialisms risk, payment mechanism, commercial
issues and funding.
3Introduction
- PFI has been used in the UK Health Sector for
about 10 years - A total of 79 schemes have reached financial
close with a capital value of 9.2 bn - Period marked by continual evolution
- Standard contract
- Increasing standardisation of performance
standards - Increasing understanding of risk transfer.
- PFI now a familiar procurement tool
4Focus of Presentation
- PFI must continue to evolve in the light of
experience - Greater emphasis on using PFI when it is right to
do so - Requirement to assess affordability and value for
money early - This has implications for
- How and when we use the Public Sector Comparator
(PSC) and - how it is constructed.
5The Public Sector Comparator (PSC)
- Costed public sector solution to deliver a
projects output specifications - Adjusted to take into account an estimate of the
risks that would be assumed by the private sector - Used as the basis for assessments of value for
money and affordability at various stages of a
project - Based on the entire life of the asset (60 years)
- Expresses the value for money of a project in a
single figure, or Net Present Cost (NPC)
6Overview of Business Case Approval
- Three key stages
- Strategic Outline Case (SOC) broad analysis of
need - Outline Business Case (OBC) more detailed
option appraisal, identification of preferred
option prior to approaching the market. PSC
developed from the preferred option - Full Business Case (FBC) comprehensive summary
of the procurement and basis for DH and HM
Treasury approval
7Approach to PSC
- New guidance issued by HM Treasury, August 2004
- More work done at OBC
- Rigorous costing of the PSC
- Early quantitative analysis
- Standard model for comparing NPCs of PFI and the
PSC - Coupled with an assessment of viability,
desirability and achievability - No further quantitative work after OBC
- Strong competition and benchmarking used to
assure value for money thereafter
8Working up the preferred option
- Services and capacity health needs and
developments - Estate options rebuild, refurbishment, other
sites - Long list produced, then subjected to standard
Option Appraisal - Resulting short list then costed
- Whole life costs discounted to give NPCs
- Based on use of public capital
- Qualitative assessment of risks and benefits
- Lowest costs per benefit point preferred option
9Costing the preferred option as the PSC (1)
- Saying what we need in terms of
- Developing a more detailed design brief covering
quality, design vision and clinical
functionality - Developing more detailed operational policies for
clinical and non-clinical services - Specifying standards that will have a material
impact on cost e.g. room sizes, circulation
space, performance, engineering and construction - Objective to be clearer about what we want, but
not prescriptive about how it is delivered.
10Costing the preferred option as the PSC (2)
- Translating design and service requirements into
costs - Build Standards Health Building Notices (HBNs)
- Capital costs for given units e.g. wards,
theatres assembled from Departmental Cost
Advisory Guides - Inflation standard index issued for tender
price inflation in the public sector - Norms for maintenance, operation and lifecycle
costs, modified according to standards required - Objective to obtain a more realistic assessment
of affordability before going to market.
11Risk and the PSC (1)
- PSC (preferred option) costed on best practice
public sector design and construction - PSC therefore adjusted according to standard risk
template and methodology - Risk that costs are underestimated addressed by
Optimism Bias - Risk transfer quantified
- Cost estimates and risk assumptions must be
tested by sensitivity analysis - Objective improving the quality of assumptions,
but recognising their limitations.
12Risk and the PSC (2)
- Points regarding Risk Transfer
- National Audit Office and Public Accounts
Committee feedback - No longer based on scheme specific estimates
- Based on standard assumptions for the sector
- Deviations from assumptions have to be justified
- Highly sensitive assumptions will be subject to
review - Heavy emphasis on sensitivity analysis
- Output is basis for quantified risk adjustment
- Objective assessment of risk informed by
experience.
13How do we use the PSC (1)?
- At OBC to
- Assess whether PFI should be the procurement
route to follow qualitatively based on past
experience - Assess whether PFI is suitable quantitatively
using a standard model to compare estimated PFI
and PSC NPCs before going to market - Assess affordability better, using more detailed
costing
14How do we use the PSC (2)?
- After OBC
- No further quantitative analysis required
- PSC only revised to reflect genuine changes in
scope, not private sector innovation - Some usefulness in benchmarking
- Some parts of the PSC may be used for briefing
the private sector - Update of qualitative factors at FBC
15What have we learned?
- PFI has proven benefits for certain types of
procurement, but not all types of procurement - Early and detailed costing provides a better
indicator of affordability - If you can explain what you want, you are likely
to get a better solution - Qualitative risk assessment should not be
over-emphasised - A better PSC helps avoid wasting both public and
private sector time, resources and cash - Approval to be concentrated earlier in
procurement
16 17Links to useful documents
DH Value for Money Guidance http//www.dh.gov.uk
/ProcurementAndProposals/PublicPrivatePartnership/
PrivateFinanceInitiative/PFIArticle/fs/en?CONTENT_
ID4120015chkt/sbV9 Costing Design Guidance
for PSCs http//www.dh.gov.uk/PublicationsAndStat
istics/Publications/PublicationsPolicyAndGuidance/
PublicationsPolicyAndGuidanceArticle/fs/en?CONTENT
_ID4122632chkxfkAF7 Links to Standard Output
Specifications for Services http//www.dh.gov.uk/
ProcurementAndProposals/PublicPrivatePartnership/P
rivateFinanceInitiative/NewStandardOutputSpecifica
tions/NewStandardOutputSpecificationsArticle/fs/en
?CONTENT_ID4016183chkC32BBiQ