Title: Mitigation of Anomalies In CIDH Piles
1Mitigation of Anomalies In CIDH Piles
- Anomaly Identification
- Design Concerns
- Remediation Methods
- Standard Mitigation Plan
One test is worth a thousand expert opinions...
Presented By Brian Liebich, P.E.
2Mitigation Process
- Anomaly Identification
- Design Review
- Contractor Plan
- Review / Approval
- Perform Repair
- Evaluation
3Mitigation of Anomalies in CIDH Piles
One test is worth a thousand expert opinions...
4Need for Non-Destructive Evaluation
- Visual Observation Difficult / Inadequate
- Structural Element Constructed Under Field
Conditions - Critical Design Requirements
5Non-Destructive Testing
- Gamma-Gamma Logging Primary Method
- Performance Evaluation for Homogeneity
- Test Every Wet CIDH Pile
6Sizing the Anomaly
- Representative Sample / Proportional
Apportionment - Can Use CSL to Further Define Anomaly
7Mitigation of Anomalies in CIDH Piles
One test is worth a thousand expert opinions...
8Designer Involvement
- Foundation Testing Knows Anomaly Location
- Designers Know Importance of an Anomaly
- Three Design Inputs Structural, Geotechnical,
Corrosion
9Structural
- Usually Most Critical
- Lateral / Shear Cannot be Transferred
- Zone of Maximum Moment
10Geotechnical
- Significant Portion of Skin Friction Reduced
- End Bearing Compromised
- Axial Capacity Diminished
11Corrosion
- Corrosive Environment
- Water Table Influence / Oxygen
- Stray Current
12Identify Critical Defects Quickly
13Mitigation of Anomalies in CIDH Piles
One test is worth a thousand expert opinions...
14Successful Repair
- No One Size Fits All
- Meets Design Requirements
- Assurance of Repair
- Timely Resolution
15How Mitigation Methods are Selected
- Contractor Selects
- Mitigation Committee Approves
- Competing Concerns Cost vs. Effectiveness
16Mitigation Methodologies
- Replacement / Supplement
- Structural Bridging
- Unearth and Recast
- Pressure Grouting
17Replace / Supplement
- Based on Design Concerns
- May not be Possible
- Typically Most Expensive
18Structural Bridging
- Core Drill Hole
- Insert Steel Supplement
- Grout into Place
19Unearth and Recast
- Physical Replacement
- Visual Inspection
- Access and Restoration
20Pressure Grouting
- Gain Access Usually PVC
- Wash and Clean Deleterious Material
- Inject Grout
21Field Inspection
- Contractor Follows Plan
- Washing Operations
- Water Test Results
- Grout Injection Volumes and Pressures
22Downhole Camera
- QA of Contractor Procedure
- Verify Anomaly Type / Extent
- Useful for Confirming Anomaly
23Mitigation of Anomalies in CIDH Piles
One test is worth a thousand expert opinions...
24ADSC Standard Mitigation Plan
- No One Size Fits All But not Reinvent the
Wheel - Cooperatively Developed ADSC - Caltrans
- Accelerated Review of Repair Plans
- Basic Repair (A) or Grouting (B)
25Basic Repairs
- Expose / Unearth
- Chip Visible Anomaly
- Recast
- Restore Soil
26Pressure Grouting
- High-Pressure Water Jetting, Clean/Scour
- Water Test for Grout Selection
- Grouting Process Detailed
- Flowchart
27Mitigation of Anomalies In CIDH Piles
- Anomaly Identification
- Design Concerns
- Remediation Methods
- Standard Mitigation Plan
One test is worth a thousand expert opinions...